| 2003-01-08 00:00:00 | BUILDING DENIED |
| | |
| | 1) A RECORDED COPY OF THE NOTICE OF |
| | COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 2) THE ENERGY CALCULATION FORM IS |
| | REQUIRED TO BE SIGNED BY THE OWNER/AGENT |
| | |
| | 3) THE UPLIFTS GIVEN ON THE ROOF FRAMING |
| | PLAN ON S2, EXCEED THE CAPACITIES OF THE |
| | SPECIFIED CONNECTORS AT SEVERAL |
| | LOCATIONS. SEE REDLINES ON PLANS. |
| | |
| | 4) CLARIFY THE CONNECTOR AND THE UPLIFT |
| | FOR THE HIP GIRDER OVER THE GARAGE. THE |
| | OUTER END HAS 1588# OF UPLIFT AND B ON |
| | S2 CONNECTOR IS SPECIFIED. THE CONNECTOR |
| | OON THE OTHER END (ENTRY) IS A USP MSH |
| | WHICH HAS A UPLIFT CAPACITY OF 785#. |
| | PLEASE REVIEW. |
| | |
| | 5) THE ROOF NAILING ZONE FOR THE GABLE |
| | END OVER BEDROOM #2 IS ZONE 3 FOR 4' |
| | FROM GABLE PLUS OVERHANG. PLEASE CORRECT |
| | THE DIAGRAM ON S2. |
| | |
| | 6) ACCORDING TO THE STORM PANEL KEY PLAN |
| | UNITS 1 & 2 ON THE INSTALLATION SCHEDULE |
| | ARE REVERSED. UNIT 6 (2) SH 25 WITH 24" |
| | TRANSOM ABOVE HAS THE WRONG OPENING SIZE |
| | LISTED ON THE SCHEDULE. THE OPENING SIZE |
| | FOR UNIT 8 IS ALSO INCORRECT. |
| | |
| | 7)PROVIDE (2) CURRENT AND COMPLETE |
| | COPIES OF SBCCI OR METRO-DADE PRODUCT |
| | APPROVALS FOR: |
| | - SLIDING GLASS DOORS |
| | - SINGLE OUTSWING DOOR WITH ONE SIDELITE |
| | - ARCHED TOP WINDOW (BEDROOM #2) |
| | |
| | 8) PROVIDE A SOIL BEARING TEST REPORT AS |
| | REQUIRED BY FBC 1804.2.2. |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)659-8096 EXT.8202 |
| | |
| | 659-8096 EXT.8202 |