| 2002-09-20 00:00:00 | ***************** UNSAT ************** |
| | |
| | PLANS REVIEWED THIRD TIME. |
| | PLEASE NOTE THAT COMMENTS ARE STILL NOT |
| | ADDRESSED FOR FIRE PUMP MAIN, FIRE PUMP |
| | SPECS AND FIRE PUMP CONTROLLER. |
| | |
| | PLEASE NOTE ELECTRICAL ENGINEER WAS |
| | CALLED ON 9/19/02 WENT OVER ISSUES. |
| | ENGINEER MENTIONED FIRE PUMP CONTROLLER |
| | WAS CHANGING AND NEW SUBMITTALS WERE |
| | COMING IN. |
| | 9/20/02 |
| | PLEASE NOTE AS PER CONVERSATION WITH |
| | JOSLYN FIRE PUMP CO. FIRE PUMP CONTROLS |
| | AND ASSC FIRE PUMP EQUIPMENT WAS NOT |
| | CHANGING AND A NEW RISER DIAGRAM IS |
| | NEEDED TO ADDRESS SECONDARY OVERCURRENT |
| | PROTECTION WHICH IS NOT PERMITTED. |
| | MAIN DISC IS GOING TO BE REVISED DELET- |
| | -ING OCP. |
| | PLEASE NOTE DISCONNECTING MEANS FOR |
| | "JOCKEY PUMP" IS TO BE SERVICE RATED |
| | AND WILL ALSO BE REVISED ON E5.1. |
| | PLEASE NOTE, "NOTES' ON E-5.1 ARE TO |
| | BE REVISED TO CORRELATE WITH FIRE PUMP |
| | COMPANYS REQ`MENTS AND TO MEET NEC. ARTS |
| | 695-4,695-5, 430-110,430-151. PLEASE |
| | ALSO SEE NFPA-20 FOR FIRE PUMPS REQ`. |
| | 6-5.1.1.1. |
| | |
| | |
| | PLEASE REVISE RISER DIAGRAM AND RESUB |
| | WHEN ALL REVIEWS ARE COMPLETE. |
| | FEES WILL BEOWED FOR PLAN REVIEW DONE. |
| | IF THERE ARE ANY QUESTIONS, PLEASE CALL. |
| | |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-659-8096 EXT 8372 |