| 2002-10-18 00:00:00 | ************** UNSAT**************** |
| | |
| | |
| | 1)NOTE: PLEASE NOTE FOOTER STEEL IS |
| | NOT SHOWN AS A PART OF THE GROUNDING |
| | ELECTRODE SYSTEM. 250-50 REQ`D. |
| | |
| | 2)NOTE: PLEASE NOTE PANEL LP-2 SHOWS A |
| | 500A MAIN BRKR ALONG WITH A 400A MAIN |
| | BRKR. THIS WAS NOTED ON PREVIOUS REVIEW. |
| | RESPONSE MENTIONS, SHOWN AS 400A. PLEASE |
| | SEE E6.2. LETTER DATED 9/30/02 #6 |
| | |
| | 3)NOTE: PLEASE NOTE THAT RISER DIAGRAM |
| | STILL SHOWS GROUNDING ELECTRODE SYSTEM |
| | COMING FROM "LP-1", PLEASE SEE 250-24 |
| | FOR CONNECTION POINT. |
| | |
| | 4)NOTE: PLEASE SEE RESPONSE LETTER FROM |
| | ZEIDLER GRINNELL, DATED SEPT 30TH, 2002 |
| | PLEASE SEE RESP. #3 MENTIONS TO SEE |
| | LOADS FOR TRACK LIGHTING IS SHOWN ON |
| | LPZ? PLEASE CLARIFY. PLEASE ALSO NOTE |
| | PANELS OR LOAD CALCS JUST NEED TO SHOW |
| | LOADING FIGURED FOR TRACK. PLANS SHOW |
| | LOADS CONNECTED. PLEASE CLARIFY HOW THIS |
| | CLARIFIES HOW MUCH LOAD PER FT WAS GIVEN |
| | ? |
| | |
| | 5)NOTE: PLEASE SEE NOTE RESPONSE#5 |
| | LETTER DATED 9/30/02. NOTE MENTIONS |
| | CHANGING 150A BRKR TO 225A, PLEASE SEE |
| | FEEDER NOTE #10 ON RISER DIAGRAM WHICH |
| | REFERS TO FEEDER SCHEDULE ON E5.2,, |
| | PLEASE NOTE, FEEDERS SHOWN AT 1/0`S |
| | PLEASE CORRELATE AND REVISE. |
| | |
| | 6)NOTE: PLEASE SEE LETTER ATTACHED, |
| | PLEASE SEE FS 553.80(2)(B) WITH RESPECT |
| | TO DOCUMENTS PREPARED BY THE DESIGN |
| | PROFESSIONALS. |
| | |
| | PLEASE SUBMIT THE ABOVE INFORMATION FOR |
| | REVIEW. IF THERE ARE ANY QUESTIONS, |
| | PLEASE CALL. |
| | |
| | DEWEY PALMER |
| | ELECTRICA PLAN REVIEW |
| | 561-659-8096 EXT 8372 |