| Date |
Text |
| 2002-05-23 00:00:00 | DENIED |
| | REFERENCE: FBC-2001 PLUMBING |
| | FBC-2001 FUEL GAS |
| | FBC-2001 CHAPTER 11 |
| | |
| | 1) PLEASE PROVIDE A SANITARY RISER DIA- |
| | GRAM FOR ALL PIPING PROPOSED FOR BATH |
| | ROOMS. |
| | 2) APPLICATION SAYS REMODEL EXISTING |
| | EXISTING BATHROOMS 1ST FLOOR, ADD POWDER |
| | ROOM, REMODEL 2ND FLOOR BATHROOM, AND |
| | ADD 2 NEW BATHROOMS ON 2ND FLOOR, BUT |
| | SAYS NOTHING OF WORK BEING DONE IN A |
| | COTTAGE. PLEASE SUPPLY A PLOT PLAN SHOW- |
| | ING ALL BLDGS ON PROPERTY. |
| | 3) SEPARATE GAS PERMIT REQUIRED FOR GAS |
| | WORK BEING DONE. PLEASE SUBMIT INFORMAT- |
| | ION REQUIRED FOR GAS PERMIT AS FOLLOWS: |
| | A. SUBMIT AN ISOMETRIC DRAWING THAT |
| | CLEARLY SHOWS ALL CUT SECTIONS OF PIPE |
| | AND CORRESPONDING LENGTHS PER FBC-2001 |
| | FUEL GAS CODE. |
| | B. SHOW TYPE OF PIPING MATERIAL BEING |
| | INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| | NUMBER OF CORRUGATED STAINLESS STEEL |
| | TUBING FOR EACH PIPE SIZE BEING USED. |
| | C. TYPE OF GAS, (LP OR NATURAL) |
| | D. BTU LOAD OF EACH APPLIANCE AND THE |
| | TOTAL BTU LOAD ON THE SYSTEM. REFER TO |
| | FBC-2001 FUEL GAS CODE. |
| | E. SHOW THE DISTANCE FROM THE POINT OF |
| | DELIVERY, (METER), TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND/OR SYSTEM PER |
| | FBC-2001 FUEL GAS CODE. |
| | F. SUBMIT CALCULATIONS FOR COMBUSTION |
| | AIR (IF APPLICABLE) PER FBC-2001 FUEL |
| | GAS CODE. |
| | G. INDICATE THE DELIVERY PRESSURE (PSI) |
| | PER FBC-2001 FUEL GAS CODE. IF NATURAL |
| | GAS SPECIFY .5 PSI OR 2 PSI. |
| | H. CLEARLY SHOW THE LOCATION AND CAP- |
| | ACITY OF LP TANK(S), TYPE OF TANK (DOT |
| | OR ASME), THE DISTANCE OF THE TANK FROM |
| | THE BUILDING AND ADJACENT PROPERTY LINES |
| | THE DISTANCE OF THE TANK FROM ALL SOUR- |
| | CES OF IGNITION, OTHER CONTAINERS, BUILD |
| | INGS, AND THE LOCATION OF ANY BUILDING |
| | OPENINGS BELOW THE RELIEF VALVE OF THE |
| | TANK PER NFPA 58, TABLE 3-2.2.2. |
| | I. CLEARLY INDICATE ON THE PLAN IF THE |
| | LP TANK IS ABOVE OR BELOW GROUND, AND |
| | SHOW REQUIRED PROTECTION OF THE TANK AND |
| | APPURTENANCES PER NFPA 58. IF THE TANK |
| | IS BELOW GROUND THE CONTAINER SHALL BE |
| | SECURILY ANCHORED PER NFPA 58 SECTION |
| | 3-2.2.7(H). |
| | 4) HC BATH #6 PLEASE SHOW DETAILS FOR |
| | HDCP BATH. SHOW CLEAR FLOOR SPACE FOR |
| | ALL FIXTURES. LAV TO BE 15" OFF THE WALL |
| | CENTERED IN CLEAR FLOOR SPACE 11-4.19.3, |
| | HEIGHT FOR LAV 4.19.2. W/C SHALL BE 1'6" |
| | TO CENTER OFF WALL, HEIGHT 4.16.3, DOOR |
| | SHALL NOT SWING INTO CLEAR FLOOR SPACE |
| | REQUIRED FOR ANY FIXTURE, 4.22.2, SHOWER |
| | STALLS 4.21 AND ALL SUBSECTIONS. PLEASE |
| | SHOW CLEAR DETAILS FOR ALL FIXTURES IN |
| | HDCP BATHROOM. |
| | 5) PLEASE INDICATE ROOM SIZE FOR ALL |
| | BATHROOMS. |
| | 6) ALL DEMO WORK SHALL BE LEFT EXPOSED |
| | FOR INSPECTION PRIOR TO COVERING. |
| | |
| | REVIEW BY KEN STEVENS |
| | (561) 659-8096 EXT 8377 |