| 2002-03-25 00:00:00 | *************BUILDING UNSAT************* |
| | |
| | 1) A RECORDED COPY OF THE NOTICE OF |
| | COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 2) IMPACT FEES MUST BE PAID TO PALM |
| | BEACH COUNTY, PLANS STAMPED BY THEM AND |
| | COPY OF RECEIPT SUBMITTED TO CITY OF |
| | WEST PALM BEACH BUILDING DEPARTMENT, |
| | BEFORE A BUILDING PERMIT CAN BE ISSUED. |
| | |
| | 3) INDICATE THE SIZE AND LOCATION OF THE |
| | REQUIRED EMERGENCY ESCAPE AND RESCUE |
| | OPENING IN THE EXISTING REAR BEDROOM. |
| | 97 SBC 1005.4 |
| | |
| | 4) THE WINDOW IN THE NEW MASTER BEDROOM |
| | MUST COMPLY WITH EMERGENCY EGRESS |
| | REQUIREMENTS OF 97 SBC 1005.4. PROVIDE |
| | THE WIDTH AND HEIGHT DIMENSIONS OR THE |
| | CALL SIZE OF THE WINDOW. |
| | |
| | 5) PROVIDE DETAILS INDICATING EXTERIOR |
| | WINDOW AND DOOR BUCK FASTENING. |
| | |
| | 6) THE ROOF OVERHANG AT THE REAR OF THE |
| | STRUCTURE ENCROACHES INTO THE 12'-0" |
| | EASEMENT. PROVIDE AN EASEMENT RELEASE OR |
| | DOCUMENTATION THAT THE OVERHANG |
| | EXTENDING INTO THE EASEMENT IS ALLOWED. |
| | |
| | 7) THE METAL TRAILER SHOWN ON THE SURVEY |
| | IS A CODE VIOLATION AND MUST BE |
| | CORRECTED BEFORE THE PERMIT CAN BE |
| | ISSUED. |
| | |
| | 8)INDICATE THE SPACING OF THE REINFORCED |
| | FILLED CELLS ON THE FOUNDATION PLAN. |
| | |
| | 9)PROVIDE A DETAIL OF THE TWO INTERIOR |
| | BEARING WALLS. INDICATE THE CONSTRUCTION |
| | AND INDICATE THE CONNECTORS USED TO |
| | TRANSFER LOADS FROM ROOF TO FOUNDATION. |
| | |
| | 10) THE NAME AND SIGNATURE OF THE PERSON |
| | RESPONSIBLE FOR THE DESIGN OF THE |
| | ADDITION IS REQUIRED ON EACH SHEET OF |
| | THE PLANS. CITY AMENDMENTS 104.2.1 |
| | |
| | 11) THE PLANS INDICATE R-30 INSULATION |
| | IN THE CEILING AND THE ENERGY FORM LISTS |
| | R-19. PLEASE CORRECT. |
| | |
| | 12) SHEET 6 LISTS SIMPSON ETA20 TRUSS |
| | ANCHORS, WHICH ARE NOT LISTED IN THE |
| | LATEST SIMPSON CATALOG. PLEASE REFER TO |
| | THE CATALOG AND SPECIFY THE PROPER META/ |
| | HETA,ETC. CONNECTOR. |
| | |
| | 13) NB2X12-24 BRIDGING IS REQUIRED FOR |
| | JOISTS SPACED 24" ON CENTER. PLEASE |
| | CORRECT. |
| | |
| | 14) THE PROPER CONNECTORS FOR TRUSS TO |
| | EXISTING MASONRY IS MTSM 20 WITH (4) 1/4 |
| | X2-1/4" TITEN SCREWS INTO MASONRY AND |
| | (10) 10D NAILS INTO TRUSS. NOT THE LTS |
| | THAT IS SPECIFIED. PLEASE CORRECT. |
| | |
| | 15) INDICATE HOW THE WOOD INTERIOR |
| | BEARING WALL IS CONNECTED TO THE NEW AND |
| | EXISTING MASONRY WALLS. |
| | |
| | 16) INDICATE HOW THE NEW FOOTER AND TIE |
| | BEAM WILL BE CONNECTED TO THE EXISTING. |
| | (DOWELS AND EPOXY ?) |
| | |
| | 17) PROVIDE SOIL BEARING TEST PER CITY |
| | OF W.P.B. AMENDMENTS TO THE 97 SBC SECT. |
| | 1804.2.2. |
| | |
| | 18)PROVIDE (2) PRODUCT APPROVALS, KEY |
| | PLANS AND INSTALLATION SCHEDULES |
| | INDICATING THE SPECIFIC TYPES OF ANCHORS |
| | TO BE USED FOR STORM PANELS. MISSILE |
| | IMPACT PROTECTION IS REQUIRED. |
| | |
| | 19)PROVIDE TWO COPIES OF ALL SUBMITTALS. |
| | PROVIDE AN ADDITIONAL COPY OF THE ENERGY |
| | FORM. |
| | |
| | 20) A MINIMUM 1/4" PER FOOT ROOF SLOPE |
| | IS REQUIRED PER 97 SBC 1503.1.2.3. |
| | |
| | 21) PROVIDE TWO (2) CURRENT AND COMPLETE |
| | COPIES OF SBCCI OR METRO-DADE PRODUCT |
| | APPROVALS FOR: |
| | - INSWING DOUBLE FRENCH DOORS WITH |
| | SIDELITES AS SHOWN ON PLANS |
| | - ADDITIONAL COPY OF PRODUCT APP. FOR |
| | SINGLE HUNG WINDOWS AND ROOF COVERING |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)659-8096 EXT.8202 |