| Date |
Text |
| 2002-01-12 00:00:00 | |
| | PHASE I |
| | |
| | PLEASE PROVIDE THE FOLLOWING INFORMATION |
| | FOR REVIEW: |
| | |
| | 1.OUTSIDE AIR CALCULATIONS AS PER |
| | ASHRAE 62-89. (FOR ALL AREAS) |
| | |
| | 2.AIR BALANCE SCHEDULE SHOWING |
| | COMPLIANCE WITH 1997 SMC 501.2. |
| | |
| | 3.PLAN SHEET M4.1 AC 2 IS SERVICING |
| | THE SHIPPING OFFICE.AC 1 IS |
| | SERVING THE RECEIVING OFFICE.THE |
| | SCHEDULE ON M-6.1 EQUIPMENT SCHEDULE |
| | DOES NOT COINCIDE WITH FLOOR PLAN. |
| | |
| | PLEASE INDICATE DUCT SMOKE DETECTORS |
| | ON PLAN SHOWING COMPLIANCE WITH 1997 |
| | SMC 406.1 |
| | |
| | 5.CLARIFY RGF- SCHEDULE REFLECTS RGF |
| | AS BEING A RETURN GRILL WITH FIRE |
| | DAMPER.PLAN SHEET M-4.1 INDICATES |
| | 2 TOTAL RGF ONE IN RECEIVING & 1 IN |
| | SHIPPING.ARE THEY FIRE DAMPERS OR |
| | BACKDRAFT DAMPERS?INDICATE ANY & |
| | ALL FIRE DAMPERS ON PLAN AS PER 1997 |
| | SMC 610.6. |
| | |
| | 6.PROVIDE INFORMATION ON THE ENGINE |
| | ROOM.INDICATE VENTILATION REQUIRE- |
| | MENTS FOR NORMAL OPERATION AS WELL |
| | AS EMERGENCY OPERATIONS.PROVIDE |
| | SEQUENCE OF OPERATION. |
| | |
| | ADDITIONAL PERMITS REQUIRED FOR ANY |
| | HOOD, FIRE SUPRESSION, FUEL AND WALK-IN |
| | COOLERS/FREEZERS.PLEASE PROVIDE PLAN |
| | AND MANUFACTURER SUBMITTAL DATA WITH |
| | PERMIT APPLICATION. |
| | |
| | PLEASE NOTE REFRIGERATION SHALL COMPLY |
| | WITH 1997 SMC CHAPTER 11 AND ASHRAE 15. |
| | |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE |
| | CONTACT PATTY KRAUSS AT 659-8096 |
| | EXT. 8388. |