| 2001-12-24 00:00:00 | *************BUILDING UNSAT************* |
| | |
| | 1) IMPACT FEES MUST BE PAID TO PALM |
| | BEACH COUNTY, PLANS STAMPED BY THEM AND |
| | COPY OF RECEIPT SUBMITTED TO CITY OF |
| | WEST PALM BEACH BUILDING DEPARTMENT, |
| | BEFORE A BUILDING PERMIT CAN BE ISSUED. |
| | |
| | 2) PROVIDE OVERFLOW SCUPPERS PER 97SBC |
| | SEC. 1517.6.4. |
| | |
| | 3) INDICATE THE EXTERIOR WINDOW AND DOOR |
| | SIZES AND TYPES ON THE PLANS. |
| | |
| | 4) PROVIDE (2) CURRENT AND COMPLETE |
| | COPIES OF SBCCI OR METRO-DADE PRODUCT |
| | APPROVALS FOR: |
| | - ARCHED FIXED GLASS WINDOWS |
| | - STRUCTURAL MULLIONS |
| | - SINGLE FRENCH DOOR (THE APPROVAL THAT |
| | WAS SUBMITTED IS FOR SINGLE UNIT |
| | APPLICATION OF A PAIR OF DOORS AND A |
| | SINGLE DOOR WITH SIDELITE ONLY) |
| | THE FRENCH DOOR PRODUCT APPROVALS WERE |
| | ALSO MISSING THE APPROVED DRAWINGS. |
| | |
| | 5) PROVIDE A BATHROOM WITH A DOOR HAVING |
| | A 29" CLEAR OPENING PER FL ACCESSIBILITY |
| | CODE. |
| | |
| | 6) PROVIDE ENERGY CALCULATIONS AND |
| | EQUIPMENT SIZING CALCULATIONS (MANUAL J) |
| | AS REQUIRED BY THE 1997 FLORIDA ENERGY |
| | EFFICIENCY CODE FOR BUILDING |
| | CONSTRUCTION. |
| | |
| | 7) PROVIDE PRODUCT APPROVALS FOR ROOFING |
| | MATERIALS UNDER A SEPARATE PERMIT. |
| | |
| | 8) INDICATE HOW THE FOYER WALLS WILL BE |
| | ATTACHED TO THE EXISTING STRUCTURE AND |
| | NEW BLOCK STRUCTURE. |
| | |
| | 9) INDICATE THE TRUSS TO DOUBLE PLATE |
| | AND DOUBLE PLATE TO (3) 2X 10 BEAM |
| | CONNECTIONS REQUIRED FOR A CONTINOUS |
| | LOAD PATH. |
| | |
| | 10) THE ROOF SHEATHING NAILING SPECIFIED |
| | ON SHEET 4 IS INCORRECT. THE CITY OF WPB |
| | AMENDMENTS TO THE 97SBC SEC. 2306 |
| | REQUIRE 6"O.C. AT EDGES AND 6" O.C. |
| | INTERMEDIATE IN ROOF ZONES 1 & 2. |
| | |
| | 11) INDICATE COMPLIANCE WITH CITY OF WPB |
| | AMENDMENTS TO 97 SBC SEC. 2304.2.5. |
| | WHERE LATH AND STUCCO FINISH IS APPLIED |
| | OVER THE EXTERIOR OF WOOD FRAME |
| | CONSTRUCTION, AN APPROVED WEEP SCREED |
| | (STUCCO STOP) PLACED NOT LESS THAN 6" |
| | ABOVE FINISHED GRADE SHALL BE USED TO |
| | TERMINATE THE STUCCO AT THE BASE OF THE |
| | WALL. |
| | |
| | 12)PROVIDE FIRE BLOCKING AT INTERSECTION |
| | OF WALL AND CEILING PER 97SBC SEC.2305.1 |
| | |
| | 13) PROVIDE FIRECUTS WHERE TRUSSES |
| | TERMINATE IN MASONRY WALLS PER 97 SBC |
| | SEC. 2305.4. |
| | |
| | 14) INDICATE WALL FURRING MATERIAL THAT |
| | WILL BE USED ON WALL SECTION. |
| | |
| | 15) INDICATE ATTIC VENTILATION AS |
| | REQUIRED BY 97 SBC SEC. 2309.7. |
| | |
| | 16) PROVIDE ARCHITECT'S TITLE BLOCK ON |
| | SHEETS 2 AND 3 OF PLANS. |
| | |
| | 17) PROVIDE A DESIGN CERTIFICATION FORM |
| | OR PROVIDE ALL THE REQUIRED INFORMATION |
| | ON THE PLANS (MEAN ROOF HEIGHT, DESIGN |
| | PRESSURE, IMPORTANCE FACTOR, ETC.). SEE |
| | ATTACHED. |
| | |
| | 18) STORM PANELS WILL BE REQUIRED ON ALL |
| | GLAZING THAT IS NOT IMPACT RESISTANT. |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)659-8096 EXT.8202 |