| 2001-08-06 00:00:00 | REVIEW FOR SMOKE CONTROL SYSTEM FOR |
| | ATRIUM |
| | ***************DENIED******************* |
| | 1. PLEASE CLARIFY MAXIMUM ATRIUM HEIGHT |
| | AS WE HAVE TWO DIFFERENT STATEMENTS AS |
| | TO HEIGHT. |
| | 2. PROVIDE SEQUENCE OF OPERATION FOR |
| | DOOR OPENINGS AND ATRIUM SMOKE CONTROL |
| | 3. DURING THE ORIGINAL MEETING ON SMOKE |
| | CONTROL THE BUILDING OFFICIAL REQUESTED |
| | IF YOU WERE USING AN ALTERNATIVE METHOD |
| | TO THE SBC USE THE 10 FOOT ABOVE THE |
| | SECOND FLOOR NOT THE 6 FOOT AS SHOWN IN |
| | THE REPORT. |
| | 4. ALL ELEVATIONS OPENING TO THE ATRIUM |
| | ARE NOT INDICATED AS REQUESTED IN THE |
| | FIRST SET OF COMMENTS. PROVIDE |
| | INFORMATION ON THE ELEVATIONS INVOLVED, |
| | I,E. AREAS SHOWN AS OPEN TO BEYOND BY |
| | BALLROOM CONCOURSE BETWEEN COLUMNS U |
| | AND K. |
| | 5. ARE ALL RESTROMS, THE ADMINISTRATIVE |
| | ASSISTANT (1N-49), RECEPTION AREA |
| | (1N-50) AND ANY OTHER AREA NOT |
| | SEPARATED BY RATED WALLS INCLUDED IN |
| | THE ATRIUM SIZE CALCULATION? |
| | 6. AS PART OF THE SEQUENCE OF OPERATION, |
| | PROVIDE INFORMATION ON ALL DEVICES THAT |
| | WILL INITIATE THE SMOKE CONTROL SYSTEM. |
| | 7. INDICATE IN THE SEQUENCE OF OPERATION |
| | HOW THE DIFFERENT FANS AND DOORS IN THE |
| | DIFFERENT ZONES WILL OPERATE. WILL ALL |
| | DOORS OPEN AND ALL FANS COME ON AR ONLY |
| | THOSE IN EFFECTED AREAS? |
| | 8.SHOW FIREMANS OVERRIDE PANEL AND |
| | EXPLAIN FUNCTION. |
| | 9. ON SHEET M5.103 SEQUENCE OF OPERATION |
| | SAYS THAT OPERATOR WILL BE ABLE TO |
| | OVERRIDE THE SYSTEM AT ANY TIME. DEFINE |
| | OPERATOR IN THIS STATEMENT. |
| | 10. IF FANS OPERATE PRIOR TO DOOR |
| | OPENING, PROVIDE INFORMATION ON DOOR |
| | PRESURE. PROVIDE MAXIMUM DOOR PULL |
| | PRESSURES FOR ALL EXIT DOORS NOT OPENED |
| | AS PART OF THE SMOKE CONTROL SYSTEM. |