| 2001-07-30 00:00:00 | FAILED |
| | REFERENCE SPC-94 SGC-97 |
| | |
| | 1) PAGE M-1 PLUMBING NOTES. |
| | #11 AIR CHAMBERS TO BE INSTALLED IN |
| | ACCORDANCE WITH SPC-94 SECT. 607.8.2 & |
| | 607.8.3. WATER HAMMER ARRESTORS TO BE |
| | INSTALLED IN ACCORDANCE TO MANUFACTURES |
| | INSTALLATION INSTRUCTIONS. |
| | #14 HOT WATER CIRCULATING SYSTEM TO |
| | BE INSULATED PER ENERGY CODE. |
| | #16 GAS TO BE PERMITTED SEPARATELY. |
| | SEE ATTACHED GAS PERMIT APPLICATION RE- |
| | QUIREMENTS SHEET. ALL INFORMATION ON |
| | THAT SHEET THAT IS APPLICABLE MUST BE |
| | RETURNED WITH GAS PERMIT APPLICATION. |
| | |
| | PAGE M-1 SANITARY RISER DIAGRAM. |
| | POWDER ROOM W/C IS NOT VENTED PROPERLY. |
| | BATH #3 BATHTUB IS NOT VENTED PROPERLY. |
| | RISER DIAGRAM TO REFLECT FLOOR PLAN, BAR |
| | SINK SHALL BE TAKEN OFF BUILDING DRAIN |
| | BEFORE CABANA BATH. |
| | W/M SHALL BE TAKEN OFF THE STACK LOWER |
| | THAN LAUNDRY SINK ON BOTH LAUNDRY STACKS |
| | DRIP HANG TRAP NOT VENTED PROPERLY. |
| | 1/2 BATH AT WORKSHOP ON FAR SIDE OF |
| | GARAGE NOT SHOWN ON SANITARY RISER DIA- |
| | GRAM. |
| | BIDET NOT VENTED PROPERLY IN MASTER |
| | BATH. |
| | |
| | BACKFLOW REQUIRED ON WATER SERVICE IF |
| | A SWIMMING POOL IN INSTALLED. |
| | |
| | REVIEW BY KEN STEVENS |