| Date |
Text |
| 2001-06-12 00:00:00 | ******************* UNSAT ************ |
| | |
| | 1)NOTE: PLEASE NOTE THAT OUTLET SPACING |
| | NEEDS TO MEET LOCAL CODE PER ART 210-50 |
| | STORAGE AREAS/ EVERY 20' OF |
| | UNENCUMBEREDWALL SPACE AND OFFICE AREAS |
| | EVERY 12" |
| | THE AREAS WHERE PATRONS/PUBLIC LOOKS TO |
| | BE AREA IN QUESTION. PLEASE NOTE EVERY |
| | 20' AND PLACE BRANCH CIRCUIT #`S ON |
| | PLANS THAT CORRELATE WITH PANEL SCHEDULE |
| | |
| | |
| | 2)NOTE: PLEASE NOTE THAT PANEL"C" PANEL |
| | SCHEDULE SHOWS MLO AND RISER SHOWS MCB. |
| | PLEASE CALRIFY. |
| | |
| | 3)NOTE: PLEASE NOTE THAT GROUNDING FOR |
| | TRANSFORMER NEEDS TO BE CLARIFIED. PER |
| | 450-5 AND 450-10 |
| | |
| | 4)NOTE: PLEASE NOTE 450-13 FOR ACESS. |
| | PLEASE SHOW TRANSFORMER LOCATION ON |
| | PLANS.PLANS NOTE TRANSFORMER HANGING |
| | FROM CEILING BUT NOT WHERE. |
| | PLEASE ALSO NOTE THAT ART 450-21B FOR |
| | TRANSFORMERS OVER 112.5 KVA NEED TO BE |
| | INSTALLED IN A TRANSFORMER VAULT. |
| | |
| | 5)NOTE: PLEASE NOTE WIRE SIZE SHOWN FOR |
| | PANEL "B" ON E-5AS 4-1/0`S FOR 200A. |
| | PLEASE CORRECT. |
| | |
| | 6)NOTE: PLEASE NOTE ACCESSABLITY FOR |
| | ALL DISCONNECTS AND CLEARENCES PER |
| | 11-26. PLEASE CLARIFICATION FOR DISCO- |
| | -NNECTS FOR TRANSFORMER// LINE AND LOAD. |
| | |
| | 7)NOTE: PLEASE SUBMIT AIC RATINGS FOR |
| | ALL NEW EQUIPMENT BEING INSTALLED. |
| | MAINS/PANELS/BREAKERS MUST BE RATED FOR |
| | THE AVAILABLE FAULT CURRENT PER 110-9. |
| | PLEASE NOTE THAT AIC RATING WAS |
| | SUBMITTED FOR PANELS, BUT NOT FOR MAIN |
| | OR DISC. |
| | |
| | 8)NOTE: PLEASE FEILD VERIFY SIZE OF |
| | EXSITING CONDUCTORS SHOWN FOR MAIN. |
| | PLEASE CLARIFY FOR ART 240-3B |
| | |
| | PLEASE SUBMIT ALL THE ABOVE INFORMATION |
| | FOR REVIEW. IF THERE ARE ANY QUESTIONS, |
| | PLEASE CALL. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-659-8096 EXT 8372 |