Plan Review Notes For Permit 00061369
Permit Number 00061369
Review Stop P
Sequence Number 3
Notes
Date Text
2001-01-08 00:00:001)THE LAYOUT OF THE RESTROOMS ON THE
 LIFE SAFETY PLANS DOESN'T CORRELATE WITH
 THE OTHER SHEETS.COUNTYWIDE AMENDMENTS
 TO SPC SEC.104.2.1.
  
 2)WATER HEATERS SHALL BE READILY ACCESS-
 IBLE PER SPC SEC.501.7.SUPPLY FIXED
 LADDER AND PLATFORM OR RELOCATE WATER
 HEATER TO FLOOR.
  
 3)A UNION SHALL BE INSTALLED DOWNSTREAM
 OF THE MANUAL SHUTOFF VALVE BY THE
 SOLENOID VALVE ON THE GAS SYSTEM PER
 NFPA 54 SEC.5.5.4.(S.O.V.IS SHOWN AS
 SOLENOID VALVE.CLARIFY.)
  
 4)THE MIN.SIZE GAS LINE TO ITEMS P-14,
 P-16,P-17 SHALL BE 1 1/4" PER SGC TABLE
 305.4(A).
  
 5)THE SANITARY SYSTEM REQUIRES ONE MAIN
 VENT STACK OR STACK VENT THROUGH THE
 ROOF(MIN.3").SPC 904.3.1.
  
 6)DESIGN OF DRAINAGE SYSTEM FOR GREASY
 WASTE SHALL COMPLY W/SPC SEC.921 FOR
 HORIZONTAL COMBINATION WASTE AND VENT
 SYSTEM.
  
 7)AN OVERFLOW IS REQD.ON THE CONDENSATE
 SYSTEM PRIOR TO THE CONNECTION WITH
 THE STORM DRAINAGE SYSTEM OR CONNECTION
 SHALL BE INDIRECT.SPC 804.3,806.
  
 CALL 561-569-8096,EXT.8377 IF YOU HAVE
 ANY QUESTIONS.
 TIMOTHY LARGE
 PLUMBING PLANS EXAMINER.