2001-01-08 00:00:00PROVIDE WATER AND SEWER PLAN SHOWING
 THE FOLLOWING ITEMS:
 CONNECTIONS OF WATER SERVICE WILL BE
 THRU DIRECT TAPS ONLY. PROVIDE SIZE
 (NO TAPPING SADDLES WILL BE ALLOWED)
 SHOW EXIST. METER LOCATION AND NOTE
 METER TO BE SHUT OFF, CUT AND PLUGGED.
  
 NEW METER LOCATION MUST BE JUST OUT SIDE
 OF RIGHT OF WAY ON THE SIDEWALK WITH
 LOCKING METER BOX LID AND TOUCH READ
 HOLE.THE DOUBLE CHECK DETECTOR ASSEMBL
 Y MUST JUST INSIDE PROPERTY LINE/R.O.W.
 LINE.
  
 SHOW EXISTING WATER AND SEWER LINE
 LOCATIONS ALONG SAQUOIA DRIVE.
 FOR LOCATION OF THESE LINE YOU MAY
 CONTACT OUR CAD DEPARTMENT AT 659-8040
 EXT. 2303
 FOR SEWER CONNECTION YOU MAY CONNECT TO
 EXISTING SANITARY SEWER SERVICE LINE IF
 IT IS 6" OR HIGHER, THIS WOULD COST
 EFFECTIVE TO THE PROPERTY OWNER.
  
 AN 18" MINIMUM SEPARATION IS REQUIRED
 BETWEEN ALL WATER AND SEWER.
  
 A 6" MINIMUM SEPERATION WILL BE REQUIRED
 BETWEEN SANITARY AND STORM.
  
 WHEN CONNECTION NEW SEWER SERVICE TO
 NEW PARISH HALL THE BATHROOMS CONNECTION
 S MUST BE CONNECTED AFTER THE GREASE
 TRAP.A CLEAN OUT WILL BE REQUIRED AT
 EVERY TURN OR EVER 100 L.F. OF STRAIGHT
 RUN. A CLEAN OUT IS REQUIRED JUST INSIDE
 OF PROPERTY LINE.
 NO STORM PLAN HAS BEEN SUBMITTED.
 SEE ATTACHED OUR STORM WATER UTILITY
 REQUIREMENTS.
  
 SINCE THERE IS A MINIMAL AMOUNT OF STORM
 YOU MAY INCLUDE IT IN WATER AND SEWER
 PLAN.
  
 YOU MUST ALSO PROVIDE THE CITY'S
 STANDARD DETAILS THAT MAY APPLY. EITHER
 CREATE A NEW SHEET OR YOU MAY INCLUDE
 THEM ON THIS SHEET IF THEY FIT.
  
 ONCE PLANS HAVE BEEN APPROVED THE
 CONTRACTOR MUST SUPPLY SHOP DRAWINGS
 FOR APPROVAL BY CITY OF WEST PALM BEACH
 PUBLIC UTILITIES ENGINEERING DEPARTMENT
 ATTENTION MANNY GONZALEZ, PROJECT SPECIA
 LIST. LOCATION: 1000 45TH ST. SUITE 9
 WEST PALM BEACH, FL 33407 (561) 659-8040
 EXT. 2306
  
 ALL PAVEMENT CUT TO INSTALL SERVICES
 MUST BE NOTED AND REFERENCED TO THE
 OUR STANDARD PAVEMENT REPLACEMENT DETAIL
  
 THE WATER SEWER AND DRAINAGE MUST BE
 DESIGNED, SIGNED AND SEALED BY A FLORIDA
 REGISTERED CIVIL ENGINEER.