Plan Review Details - Permit 99100118
Plan Review Stops For Permit 99100118
Review Stop E ELECTRICAL
Rev No 1 Status P Date 1999-10-19 Cont ID  
Sent By dpalmer Date 1999-10-19 Time 06:43 Rev Time 0.00
Received By dpalmer Date 1999-10-19 Time 06:43 Sent To  
Notes
2001-01-08 00:00:00**************PROVISO******************
  
 1)NOTE:AS PER ARTS:110-9/215-5 NEED TO
 SUBMIT AIC RATING OF EQUIPMENT/MAINS/
 BREAKERS. AIC RATING IS FIGURED FROM
 FAULT CURRENT CALCULATIONS.
 2)NOTE:AS PER ART:210-8-A-6 ALL OUTLETS
 SERVING KITCHEN COUNTERSPACE ARE TO BE
 GFI/GFI PROTECTED.
 3)NOTE:AS PER 1996 NFPA-72 2-2.1.1.1
 SMOKE DETECTORS ARE REQ`D INSIDE AND
 OUTSIDE ALL SLEEPING ROOMS OF NEW
 CONSTRUCTION OF RESIDENTIAL DWELLINGS.
 4)NOTE:PLEASE NOTE THAT ON PANEL SCHED.
 AS PER ART;210-52D BATH RECEPTS. ARE TO
 BE ON A SEPARATE 20AMP. CIRCURT.
  
 NED TO HAVE ALL THE ABOVE SUBMITTED FOR
 REVIEW AND APPROVAL BEFORE FIRST ROUGH
 ELECTRICAL INSPECTION IS CALLED IN.

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 1999-10-12 Cont ID  
Sent By jleech Date 1999-10-12 Time 13:59 Rev Time 0.50
Received By jleech Date 1999-10-12 Time 13:59 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 1999-10-06 Cont ID  
Sent By tlarge Date 1999-10-06 Time 16:23 Rev Time 0.33
Received By tlarge Date 1999-10-06 Time 16:23 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 2 Status P Date 1999-11-09 Cont ID  
Sent By jgomez Date 1999-11-09 Time 13:16 Rev Time 1.50
Received By jgomez Date 1999-11-09 Time 13:16 Sent To  
Notes
2001-01-08 00:00:00APPROVED WITH PROVISO:
 1-FLOOD ZONE "A-8". PROVIDE ELEVATION
 CERTIFICATE.
 2-PLEASE REVISE ALL ORIGINAL DRAWINGS
 SHOWING ALL CORRECTIONS REQUESTED ON
 PLANS.
 3-PROVIDE PRODUCT APPROVAL FOR: ENTRY
 DOORS WITH SIDELITES ASSEMBLY, WINDOW
 AND DOOR MULLIONS, ROOF TILE, GARAGE
 DOOR.
 NOTE:
 NORANDEX PRODUCTS SUBMITTAL ARE NOT
 ACCEPTED UNLESS THEY PROVIDE SITE
 SPECIFIC COMPLETE ENGINEERING CALCS
 AND SPECIFICATIONS OR APPROVED PRODUCT
 APPROVAL.
 4-STORM PANELS:
 -INSTALLATION SCHEDULE, KEY PLAN AND
 ENGINEER PLANS DON'T MATCH.
 -PROVIDE COMPLETE INSTALLATION
 SCHEDULE AS PER CITY SAMPLE, ATTACHED.
 5-PROVIDE SAFETY GLASS AS REQUIRED. SEE
 PLANS FOR COMMENTS.
 6-UPDATE ALL ENGINEERED TRUSSES:
 -REVISE MEAN ROOF HEIGHT.
 -DESIGN CRITERIA ACCEPTED BY THIS
 OFFICE IS SBC 1997 OR ASCE 7-95 ONLY.
 7-PROVIDE COMPLETE BUCK DETAILS FOR ALL
 EXTERIOR WINDOW TYPES, DOOR TYPES AND
 GARAGE DOOR.SEC 104.2.2 CITY AMENDMENT
 8-PROVIDE COMPLETE SPECIFICATIONS/DETAIL
 FOR CONSTRUCTION AT CEILING OF REAR
 AND FRONT PORCH. SEC 2504 SBC 1997.
  
 NOTE:
 ALL ITEMS ON PROVISO MUST BE ADDRESSED
 PRIOR TO INSTALLATION.

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status F Date 1999-11-05 Cont ID  
Sent By jgomez Date 1999-11-05 Time 10:54 Rev Time 2.00
Received By jgomez Date 1999-11-05 Time 10:54 Sent To  
Notes
2001-01-08 00:00:00CHECKLIST:
 1- PAY IMPACT FEES.
 2-REVISE ENERGY CALCULATIONS.
 3-PAY RADON FEES
 4-SEE COMMENTS ON PLANS
 5-PRODUCT APPROVALS
 6-UPDATE TRUSS DRAWINGS
 7-REVISE ALL ORIGINAL DRAWINGS
 8-STORM PANELS.
 9-SAFETY GLASS
 10-FLOOD ZONE.
 11-CEILING CONSTRUCTION AT PORCH
 12-BUCK DETAILS
 13-

Review Stop Z ZONING
Rev No 1 Status P Date 1999-11-09 Cont ID  
Sent By jgomez Date 1999-11-09 Time 13:35 Rev Time 0.25
Received By jgomez Date   Time   Sent To  
Notes
2001-01-08 00:00:00APPROVED BY GRACE J. 10/5/99.


Account Summary | Usage Policy | Privacy Policy