Plan Review Details - Permit 23031912
Plan Review Stops For Permit 23031912
Review Stop AD ADDRESSING
Rev No 1 Status P Date 2023-04-18 Cont ID  
Sent By cpuell Date 2023-04-18 Time 12:22 Rev Time 0.00
Received By cpuell Date 2023-04-18 Time 12:22 Sent To  
Notes
2023-04-18 12:23:14ADDRESS APPROPRIATE FOR PROJECT.

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status P Date 2023-06-14 Cont ID  
Sent By lbond Date 2023-06-14 Time 11:07 Rev Time 0.00
Received By lbond Date 2023-06-14 Time 11:07 Sent To  
Notes
***NONE***

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2023-04-12 Cont ID  
Sent By lbond Date 2023-04-12 Time 09:20 Rev Time 0.00
Received By lbond Date 2023-04-12 Time 09:20 Sent To  
Notes
2023-04-12 09:36:43BUILDING REVIEW COMMENTS:
  
 W.P.B. PERMIT: 23031912
  
 REVIEWED: APRIL 12, 2023
  
 FLORIDA BUILDING CODE,7TH EDITION (2020)
 FBC[AMENDED] = 2017 CHAPTER 1 WPB AMENDMENTS (SEE LINK
 BELOW)
 HTTPS://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/
 BUILDING-PERMIT-FORMS
 FBC BUILDING
 FBC EXISTING BUILDING
  
 COMMENTS:
  
 ASBESTOS REVIEW:
 FAILED PLAN REVIEW:
  
 PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING ASBESTOS
 REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE:
  
 HTTPS://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVIC
 ES/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION
 -RENOVATION.HTML
  
 IF YOU HAVE ANY QUESTIONS OR CONCERNS, PLEASE DO NOT
 HESITATE TO CONTACT ME
  
 LOUIS BOND, AIA
 BUILDING PLANS EXAMINER II
 DEVELOPMENT SERVICES DEPT.
 BUILDING DIVISION
 401 CLEMATIS STREET
 WEST PALM BEACH, FLORIDA 33401
 PH: 561-805-6729
 FX: 561-805-6676
 EMAIL: [email protected]
  
  
 NOTES:
 PLEASE PROVIDE COMMENT RESPONSE SHEET TO EXPLAIN HOW
 EACH COMMENT IS BEING ADDRESSED.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2023-07-18 Cont ID  
Sent By pvalenti Date 2023-07-18 Time 07:10 Rev Time 0.00
Received By pvalenti Date 2023-07-18 Time 07:02 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2023-07-07 Cont ID  
Sent By pvalenti Date 2023-07-07 Time 15:37 Rev Time 0.00
Received By pvalenti Date 2023-07-07 Time 15:35 Sent To  
Notes
2023-07-07 15:39:29PETER E VALENTI
 BUILDING PLANS EXAMINER II/INSPECTOR
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING
 CODE, BUILDING 3303:
  
  
 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER
 DEPARTMENT, REQUEST FOR METER PULL, ON
 THEIR FORM "DEMOLITION APPLICATION"
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2023-04-14 Cont ID  
Sent By pvalenti Date 2023-04-14 Time 08:33 Rev Time 0.00
Received By pvalenti Date 2023-04-14 Time 07:47 Sent To  
Notes
2023-04-14 08:44:43PETER E VALENTI
 BUILDING PLANS EXAMINER II/INSPECTOR
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING
 CODE, BUILDING 3303:
  
  
 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER
 DEPARTMENT, REQUEST FOR METER PULL, ON
 THEIR FORM "DEMOLITION APPLICATION"
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
 WATERDOWN METHOD:
 IT APPEARS THAT A BACKFLOW PREVENTER PERMIT HAS BEEN
 APPLIED FOR (PERMIT #23040160). PLEASE NOTIFY ME WHEN
 THIS PERMIT HAS BEEN APPROVED ALONG WITH FINAL APPROVED
 FIELD PLUMBING INSPECTION.
  
 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED. IT APPEARS
 THAT A PERMIT FOR THE SEWER LATERAL CAPPING HAS BEEN
 OBTAINED (PERMIT #23040125). PLEASE NOTIFY ME WHEN THIS
 PERMIT HAS HAD AN APPROVED PLUMBING FINAL FIELD
 INSPECTION.
  
 9. PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING
 ASBESTOS REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE:
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2023-07-12 Cont ID  
Sent By lquinone Date 2023-07-12 Time 10:48 Rev Time 0.00
Received By lquinone Date 2023-07-12 Time 10:48 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2023-04-20 Cont ID  
Sent By lquinone Date 2023-04-20 Time 13:10 Rev Time 0.00
Received By lquinone Date 2023-04-20 Time 13:10 Sent To  
Notes
2023-04-20 13:10:54PLEASE PROVIDE STORMWATER POLLUTION PREVENTION PLAN
 SHOWN ON COPY OF PROPERTY SURVEY - SILT FENCE AROUND
 PROPERTY TO PREVENT DEBRIS RUNOFF; PROTECT ROADWAY FROM
 TRACKING OF DIRT FROM TRUCKS HAULING DEBRIS; PROTECT
 ANY STORM DRAIN INLETS IN VICINITY USING BEST
 MANAGEMENT PRACTICES (FILTER FABRIC, ETC.)
  
 THERE ARE WATER AND SEWER LINES IN THE VICINITY OF THIS
 PROJECT. PER CHAPTER 556 OF THE FLORIDA STATE STATUTES,
 YOU MUST CALL 811 FOR UTILITY LOCATES AT LEAST TWO FULL
 BUSINESS DAYS IN ADVANCE OF ANY CONSTRUCTION OR
 DEMOLITION WORK. INFORMATION CAN BE FOUND HERE:
 HTTP://WWW.SUNSHINE811.COM/
  
 PROVIDE ALL REQUIRED ASSOCIATED DOCUMENTS AS REQUIRED
 BY BUILDING DEPT. - STORMWATER POLLUTION PREVENTION
 PLAN, AND UTILITY SIGNOFFS - WATER/SEWER, PEST, FPL,
 FPU, ASBESTOS ETC.
  
 TO RESUBMIT, YOU MUST FIRST WAIT TILL ALL THE PLAN
 REVIEWS ARE COMPLETE. EVEN IF YOU FAILED ONE TRADE AND
 WANT TO ADDRESS THE COMMENTS IMMEDIATELY, YOU MUST WAIT
 FOR ALL OTHER TRADES TO REVIEW YOUR PLAN. RESUBMITTING
 BEFORE PLAN REVIEW IS COMPLETE WILL DELAY YOUR PLAN
 REVIEW TIME.
  
 ONCE ALL PLAN REVIEWS ARE COMPLETE, IF YOU DONT
 UNDERSTAND THE FAILED PLAN REVIEW COMMENTS, AS A BEST
 PRACTICE YOU SHOULD CALL OR EMAIL YOUR PLAN REVIEWER TO
 DISCUSS. EVERY PLAN REVIEWER INCLUDES THEIR NAME, PHONE
 AND EMAIL ADDRESS IN THE COMMENTS. TO VIEW YOUR PLAN
 REVIEW COMMENTS ONLINE, GO TO THE DEVELOPMENT SERVICES
 WEBSITE AT HTTPS://WWW.WPB.ORG/GOVERNMENT/DEVELOPMENT-S
 ERVICES/PERMITS AND SEE WHERE CAN I FIND MY PLAN REVIEW
 COMMENTS ONLINE? FOR INSTRUCTIONS.
  
 FOR QUESTIONS ABOUT HOW TO RESUBMIT, SEE INFO ON
 WEBSITE OR EMAIL [email protected] AND A BUILDING DIVISION
 TEAM MEMBER WILL HELP YOU.
  
 THANKS,
 LINDA M. QUINONES-CINTRON, PROJECT COORDINATOR,
 ENGINEERING SERVICES DEPARTMENT (561) 494-1085
 [email protected]
 FOR 24-HOUR EMERGENCY RESPONSE SERVICES TO PUBLIC
 UTILITIES, PUBLIC WORKS, PARKS, ETC. 561-822-2210
  
  

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2023-04-26 Cont ID  
Sent By amhamilt Date 2023-04-26 Time 12:11 Rev Time 0.00
Received By amhamilt Date 2023-04-26 Time 12:11 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2023-07-18 Cont ID  
Sent By pvalenti Date 2023-07-18 Time 07:10 Rev Time 0.00
Received By pvalenti Date 2023-07-13 Time 17:22 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2023-07-13 Cont ID  
Sent By aoliver Date 2023-07-13 Time 07:09 Rev Time 0.00
Received By aoliver Date 2023-07-03 Time 10:51 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2023-04-27 Cont ID  
Sent By aoliver Date 2023-04-27 Time 07:54 Rev Time 0.00
Received By aoliver Date 2023-04-11 Time 16:32 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status N Date 2023-06-14 Cont ID  
Sent By lbond Date 2023-04-12 Time 09:19 Rev Time 0.00
Received By lbond Date 2023-06-14 Time 11:09 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2023-04-26 Cont ID  
Sent By amhamilt Date 2023-04-26 Time 12:18 Rev Time 0.00
Received By amhamilt Date 2023-04-26 Time 12:18 Sent To  
Notes
***NONE***