Plan Review Details - Permit 23021244
Plan Review Stops For Permit 23021244
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2023-04-25 Cont ID  
Sent By lbond Date 2023-04-25 Time 09:48 Rev Time 0.00
Received By lbond Date 2023-04-25 Time 09:48 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2023-03-31 Cont ID  
Sent By lbond Date 2023-03-31 Time 08:12 Rev Time 0.00
Received By lbond Date 2023-03-31 Time 08:12 Sent To  
Notes
2023-03-31 08:14:31PROVISO - PLEASE COMPLY TO LATEST THRESHOLD COMMENT
 DATED MARCH 22 2023 VERY IMPORTANT. UPLOAD DOCUMENT TO
 PROJECTDOX
 THANK YOU

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2023-02-27 Cont ID  
Sent By lbond Date 2023-02-27 Time 14:34 Rev Time 0.00
Received By lbond Date 2023-02-27 Time 14:34 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2023-04-25 Cont ID  
Sent By lbond Date 2023-04-25 Time 09:49 Rev Time 0.00
Received By lbond Date 2023-04-19 Time 17:23 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2023-03-31 Cont ID  
Sent By lbond Date 2023-03-31 Time 08:15 Rev Time 0.00
Received By lbond Date 2023-03-08 Time 15:13 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2023-02-27 Cont ID  
Sent By lbond Date 2023-02-27 Time 14:34 Rev Time 0.00
Received By lbond Date 2023-02-27 Time 12:19 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2023-02-27 Cont ID  
Sent By lbond Date 2023-02-27 Time 14:09 Rev Time 0.00
Received By lbond Date 2023-02-27 Time 14:09 Sent To  
Notes
***NONE***

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 3 Status P Date 2023-04-25 Cont ID  
Sent By lbond Date 2023-04-25 Time 09:48 Rev Time 0.00
Received By lbond Date 2023-04-25 Time 09:48 Sent To  
Notes
***NONE***

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 2 Status F Date 2023-03-22 Cont ID  
Sent By dbattles Date 2023-03-22 Time 16:11 Rev Time 0.00
Received By dbattles Date 2023-03-22 Time 16:11 Sent To  
Notes
2023-03-22 16:14:29PLEASE PROVIDE PAGE 8 OF THE SPECIAL INSPECTOR
 AGREEMENT.
 THAT IS THE PAGE WHERE THE CONTRACTOR AND OWNER SIGN.
  
 THIS CAN BE EMAIL TO [email protected] OR UPLOAD IT TO
 PROJECTDOX SUPPORTING.
 YOU CAN REPLACE THE ONE PAGE DOCUMENT WITH THE NEW TWO
 PAGE DOCUMENT TO INCLUDE CONTRACTOR AND OWNERS
 SIGNATURE.
  
 DYLAN BATTLES
 561-805-6718
 [email protected]
  

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 1 Status F Date 2023-02-27 Cont ID  
Sent By lbond Date 2023-02-27 Time 14:28 Rev Time 0.00
Received By lbond Date 2023-02-27 Time 14:28 Sent To  
Notes
2023-02-27 14:30:05BUILDING REVIEW COMMENTS:
  
 W.P.B. PERMIT: 23021244
  
 REVIEWED: FEBRUARY 27, 2023
  
 FLORIDA BUILDING CODE,7TH EDITION (2020)
 FBC[AMENDED] = 2017 CHAPTER 1 WPB AMENDMENTS (SEE LINK
 BELOW)
 HTTPS://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/
 BUILDING-PERMIT-FORMS
 FBC BUILDING
 FBC EXISTING BUILDING
  
 COMMENTS:
 1) COMPLETE THE THRESHOLD / SPECIAL INSPECTOR AGREEMENT
 OF UNDERSTANDING; IF PDF OF AGREEMENT IS NEEDED PLEASE
 CONTACT THE BUILDING PLAN REVIEWER AND THEY WILL
 PROVIDE VIA E-MAIL.
 2) PROVIDE RESUMES AND COPIES OF LICENSES FOR ALL
 PROPOSED INSPECTORS. PLEASE INCLUDE AS MANY ADDITIONAL
 INSPECTORS AS POSSIBLE BECAUSE THESE ARE THE ONLY
 PEOPLE THAT THE CHIEF BUILDING INSPECTOR WILL ALLOW TO
 BE ON-SITE.
  
  
 IF YOU HAVE ANY QUESTIONS OR CONCERNS, PLEASE DO NOT
 HESITATE TO CONTACT ME
  
 LOUIS BOND, AIA
 BUILDING PLANS EXAMINER II
 DEVELOPMENT SERVICES DEPT.
 BUILDING DIVISION
 401 CLEMATIS STREET
 WEST PALM BEACH, FLORIDA 33401
 PH: 561-805-6729
 FX: 561-805-6676
 EMAIL: [email protected]
  
  
 NOTES:
 PLEASE PROVIDE COMMENT RESPONSE SHEET TO EXPLAIN HOW
 EACH COMMENT IS BEING ADDRESSED.
  


Account Summary | Usage Policy | Privacy Policy