| Plan Review Stops For Permit 23020478 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
F |
Date |
2023-06-30 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-06-30 |
Time |
11:02 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-06-30 |
Time |
11:02 |
Sent To |
|
|
| Notes |
| 2023-06-30 11:02:42 | REVISION | | | REVIEWED BY ROGER MCPHERSON | | | 561-805-6716 | | | [email protected] | | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | | AMENDMENT | | | | | | CORRECTIONS NEEDED - FBC 107.2.1 | | | | | | 1) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE | | | INSTALLATION INSTRUCTIONS) FOR THE EXTERIOR DOORS, | | | WINDOW SYSTEMS, ROOFING SYSTEMS AND EXTERIOR SYSTEMS | | | LISTED ON THE DRAWINGS. | | | | | | 2) I DO NOT SEE A LIST OF DEFERRED ITEMS ON DRAWING G | | | 101 AS NOTED IN THE CORRECTIONS LETTER - - EXTERIOR | | | WINDOW, DOOR, ROOFING SYSTEM AND EXTERIOR WALL CLADDING | | | SYSTEMS MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS TO | | | BE DEFERRED ON THE CONSTRUCTION DOCUMENTS - FBC WPB | | | 107.3.4.1 | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
F |
Date |
2023-06-01 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-06-01 |
Time |
13:05 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-06-01 |
Time |
13:05 |
Sent To |
|
|
| Notes |
| 2023-06-01 13:07:50 | REVISION | | | REVIEWED BY ROGER MCPHERSON | | | 561-805-6716 | | | [email protected] | | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | | AMENDMENT | | | | | | CORRECTIONS NEEDED - FBC 107.2.1 | | | | | | 1) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE | | | INSTALLATION INSTRUCTIONS) FOR THE EXTERIOR DOORS, | | | WINDOW SYSTEMS, ROOFING SYSTEMS AND EXTERIOR SYSTEMS | | | LISTED ON THE DRAWINGS. | | | | | | 2) I DO NOT SEE A LIST OF DEFERRED ITEMS ON DRAWING G | | | 101 AS NOTED IN THE CORRECTIONS LETTER - - EXTERIOR | | | WINDOW, DOOR, ROOFING SYSTEM AND EXTERIOR WALL CLADDING | | | SYSTEMS MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS TO | | | BE DEFERRED ON THE CONSTRUCTION DOCUMENTS - FBC WPB | | | 107.3.4.1 | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2023-04-19 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-04-19 |
Time |
11:46 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-04-19 |
Time |
11:38 |
Sent To |
|
|
| Notes |
| 2023-04-19 11:43:32 | REVISION | | | REVIEWED BY ROGER MCPHERSON | | | 561-805-6716 | | | [email protected] | | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | | AMENDMENT | | | | | | CORRECTIONS NEEDED - FBC 107.2.1 | | | | | | 1) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE | | | INSTALLATION INSTRUCTIONS) FOR THE EXTERIOR DOORS, | | | WINDOW SYSTEMS AND ROOFING SYSTEMS LISTED ON THE | | | DRAWINGS. | | | | | | 2) PLEASE SHOW EXTERIOR WALL CLADDING ATTACHMENTS TO | | | THE STEEL FRAMING (ATTACHMENT TYPE, SIZE AND ON CENTER | | | SPACING) OR PROVIDE A PRODUCT APPROVAL FOR THE WALL | | | CLADDING SYSTEM - FBC WPB 107.2.1 | | | | | | 3) WINDOW, DOOR, ROOFING SYSTEM AND EXTERIOR WALL | | | CLADDING SYSTEMS MAY BE DEFERRED SUBMITTALS BY LISTING | | | ITEMS TO BE DEFERRED ON THE CONSTRUCTION DOCUMENTS - | | | FBC WPB 107.3.4.1 | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2023-02-24 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-02-24 |
Time |
10:32 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-02-24 |
Time |
09:57 |
Sent To |
|
|
| Notes |
| 2023-02-24 10:32:29 | REVISION | | | REVIEWED BY ROGER MCPHERSON | | | 561-805-6716 | | | [email protected] | | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | | AMENDMENT | | | | | | CORRECTIONS NEEDED - FBC 107.2.1 | | | | | | 1) PLEASE PROVIDE THE DETAILS FOR THE "6" LIGHT GAUGE | | | FRAMING WITH EXTERIOR STO STUCCO SYSTEM". | | | | | | 2) PLEASE PROVIDE DETAILS FOR THE "POWDER COATED ALUM. | | | STOREFRONT SYSTEM WITH FROSTED GLAZING" | | | | | | 3) PLEASE PROVIDE THE ROOFING SYSTEM PRODUCT APPROVALS. | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2023-07-11 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2023-07-11 |
Time |
16:38 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2023-07-11 |
Time |
16:33 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2023-03-10 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2023-03-10 |
Time |
18:11 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2023-03-10 |
Time |
18:06 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2023-02-24 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2023-02-24 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2023-02-24 |
Time |
12:01 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2023-07-11 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2023-07-11 |
Time |
16:38 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2023-06-29 |
Time |
16:14 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2023-06-01 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-06-01 |
Time |
13:13 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-05-31 |
Time |
10:21 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2023-04-19 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-04-19 |
Time |
11:53 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-04-18 |
Time |
09:53 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2023-03-24 |
|
|
Cont ID |
|
| Sent By |
avolcy |
Date |
2023-03-24 |
Time |
08:24 |
Rev Time |
0.00 |
| Received By |
avolcy |
Date |
2023-02-23 |
Time |
14:10 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
4 |
Status |
P |
Date |
2023-06-30 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-06-30 |
Time |
11:06 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-06-30 |
Time |
11:06 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
3 |
Status |
F |
Date |
2023-06-01 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-06-01 |
Time |
13:13 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-06-01 |
Time |
13:13 |
Sent To |
|
|
| Notes |
| 2023-06-01 13:13:42 | SIGNATURE REVIEW | | | | | | CORRECTIONS NEEDED - | | | | | | 1) DRAWINGS E-PB01 AND E-PB02 DO NOT SHOW AS DIGITALLY | | | SIGNED IN ADOBE READER - | | | | | | SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE | | | DIGITALLY/ELECTRONICALLY SIGNED TO BE USED IN | | | ELECTRONIC PLAN REVIEW. (A CERTIFICATE-BASED DIGITAL | | | SIGNATURE (OFTEN JUST CALLED A DIGITAL SIGNATURE) IS A | | | SPECIFIC TYPE OF E-SIGNATURE). | | | |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
F |
Date |
2023-04-19 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-04-19 |
Time |
11:49 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-04-19 |
Time |
11:49 |
Sent To |
|
|
| Notes |
| 2023-04-19 11:53:49 | SIGNATURE REVIEW | | | | | | CORRECTIONS NEEDED - | | | | | | 1) DRAWINGS E-PB01 AND E-PB02 DO NOT SHOW AS DIGITALLY | | | SIGNED IN ADOBE READER - | | | | | | SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE | | | DIGITALLY/ELECTRONICALLY SIGNED TO BE USED IN | | | ELECTRONIC PLAN REVIEW. (A CERTIFICATE-BASED DIGITAL | | | SIGNATURE (OFTEN JUST CALLED A DIGITAL SIGNATURE) IS A | | | SPECIFIC TYPE OF E-SIGNATURE). | | | |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2023-02-24 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2023-02-24 |
Time |
10:33 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2023-02-24 |
Time |
10:33 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2023-03-24 |
|
|
Cont ID |
|
| Sent By |
AVolcy |
Date |
2023-03-24 |
Time |
08:21 |
Rev Time |
0.00 |
| Received By |
avolcy |
Date |
2023-03-24 |
Time |
08:21 |
Sent To |
|
|
| Notes |
| 2023-03-24 08:23:54 | THIS REVIEW IS LIMITED TO THE ELEVATOR AND ENCLOSURE | | | ONLY | | | | | | THE PROJECT IS SUBJECT TO ALL DEVELOPMENT ORDER | | | CONDITIONS, AS OUTLINED IN RESOLUTION NO. 81-20, AS | | | APPROVED BY THE CITY COMMISSION AND AS MAY BE AMENDED. |
|
|