Review Stop AD ADDRESSING
Rev No 2 Status P Date 2023-01-27 Cont ID  
Sent By cpuell Date 2023-01-27 Time 15:16 Rev Time 0.00
Received By cpuell Date 2023-01-27 Time 15:16 Sent To  
Notes
2023-01-27 15:17:56ADDRESS APPROPRIATE FOR PROJECT. A MORE COMPLETE
 ADDRESS REVIEW WILL BE DONE UNDER 22120880

Review Stop AD ADDRESSING
Rev No 1 Status F Date 2023-01-09 Cont ID  
Sent By cpuell Date 2023-01-09 Time 16:15 Rev Time 0.00
Received By cpuell Date 2023-01-09 Time 16:15 Sent To  
Notes
2023-01-09 16:22:33A NEW ADDRESS NEEDS TO BE ESTABLISHED FOR THE PROJECT,
 PER ROBERT BROWNS PPRC COMMENTS:
  
 17. BUILDING ADDRESS. EACH SEPARATE BUILDING, AND UNIT
 WITH AN INDEPENDENT ENTRANCE FROM THE STREET, SHALL
 HAVE A SEPARATE ADDRESS ASSIGNED BASED ON THE LOCATION
 OF THE BUILDING ENTRANCE. FOR STREET ADDRESSING,
 CONTACT CAROLINE PUELL, ADDRESSING COORDINATOR, AT
 (561) 805 6659, OR BY EMAIL: [email protected] RESPONSE
 NOTED.
  
 FOR THE FOUNDATION PERMIT A PRIMARY ADDRESS NEEDS TO BE
 ASSIGNED BASED ON THE PRIMARY ENTRANCE AND THE CITY'S
 ROAD CENTERLINE, PLEASE PROVIDE A SITE PLAN SHOWING THE
 PRIMARY LOCATION OF THE PRIMARY ENTRANCE TO
 [email protected] OR CALL 561-805-6659
  

Review Stop AFFIDAVIT PRIVATE PROVIDER AFFIDAVIT
Rev No 3 Status P Date 2023-03-31 Cont ID  
Sent By lbond Date 2023-03-31 Time 15:17 Rev Time 0.00
Received By lbond Date 2023-03-31 Time 15:17 Sent To  
Notes
2023-03-31 14:25:13MECHANICAL AFFIDAVIT IS NOT REQUIRED ON THIS FOUNDATION
 ONLY AFFIDAVIT. THE MECHANICAL DRAWINGS SUBMITTED HAVE
 BEEN LOCKED SO THEY WILL NOT BE PRINTED. ME
2023-03-31 14:20:043/31/23 ELECTRIC AFFIDAVIT PASSED. MP
 3/31/23 PLUMBING AFFIDAVIT PASSED. MP
2023-03-31 14:18:35BUILIDNG AFFIDAVIT PASSED 3-31-2023
 STRUCTURAL AFFIDAVIT; PASSED 3-31-2023

Review Stop AFFIDAVIT PRIVATE PROVIDER AFFIDAVIT
Rev No 2 Status F Date 2023-03-30 Cont ID  
Sent By lbond Date 2023-03-30 Time 09:57 Rev Time 0.00
Received By lbond Date 2023-03-30 Time 09:57 Sent To  
Notes
2023-03-30 09:44:22STRUCTURAL AFFIDAVIT FAILED-DATES ON DRAWINGS SIGNED
 AND SEALED DOUCMENTS ARE NOT 11.29.22 PLEASE UPDATED
 ACCORDINGLY
 GEOTECHNINCAL REPORT UPDATED RECENTLY FOLLOWING
 BUILDING COMMENT- SEE NARRATIVE MUST BE PART OF THE
 STRUCTURAL AFFIDAVIT.
  
  
2023-03-29 13:46:38PLUMBING AFFIDAVIT REVIEW FAILED.
 1) THE AFFIDAVIT LISTS ALL CIVIL (C) SHEETS DATES-
 11/29/22. CIVIL SHEETS UPLOADED FOR REVIEW HAVE DEC.
 2022 DATES.
 2) THE AFFIDAVIT LISTS ALL PLUMBING (P) SHEETS DATES-
 11/29/22.
 SHEETS P-001, P-101, P-102, P-601, & P-603 UPLOADED FOR
 REVIEW ARE DATED 3/24/23.
 3) SHEETS P-101, P-102, & P-603 ARE NOT LISTED IN THE
 AFFIDAVIT. PLEASE NOTE THESE SHEETS ARE ALSO NOT LISTED
 IN THE INDEX ON SHEET G-100.
  
2023-03-29 11:40:13 
 ELECTRIC AFFIDAVIT REVIEW PASSED. MP
2023-03-29 09:37:31THE AFFIDAVIT FOR THE MECHANICAL PLAN REVIEW INDICATES
 THAT SHEETS M-001, M-002, M-101A, M-101B. THE AFFIDAVIT
 DOES NOT INDICATE THAT THE FOLLOWING SHEETS THAT WERE
 SUBMITTED IN THE DRAWING PACKAGE HAVE BEEN REVIEWED AS
 THEY ARE NOT LISTED IN THE MECHANICAL AFFIDAVIT. SHEET
 M-605A AND M-605B. THE MECHANICAL AFFIDAVIT HAS FAILED.
 ME
2023-03-29 09:03:29BUILDING AFFIDAVIT : FAILED
 LATEST BUILDING AFFIDAVIT SHEETS DATES SHOULD REFLECT
 LATEST VERSION. EXAMPLE G-100 WAS UPLOADED 03.22.2023
 AND YOUR AFFIDAVIT SAYS SHEETS IS DATED 11.29.2022
 PLEASE UPDATED ACCORDINGLY FOR ALL LATEST SHEETS PART
 OF THE AFFIDAVIT.

Review Stop AFFIDAVIT PRIVATE PROVIDER AFFIDAVIT
Rev No 1 Status P Date 2023-03-09 Cont ID  
Sent By lbond Date 2023-03-09 Time 11:16 Rev Time 0.00
Received By lbond Date 2023-03-09 Time 11:16 Sent To  
Notes
2023-03-09 12:21:42MECHANICAL AFFIDAVIT APPROVED. ME
2023-03-09 10:46:59BUILDING AND STRUCTURE AFFIDAVIT PASSED LOUIS BOND, AIA
  
  
2023-03-08 14:27:17PLUMBING AFFIDAVIT PASSED.
2023-03-08 13:08:203/8/23 ALL ELECTRIC AND FIRE ALRM PLANS PASSED
 AFFIDAVIT REVIEW. M PETERSON

Review Stop AIPP ART IN PUBLIC PLACES
Rev No 1 Status P Date 2023-03-07 Cont ID  
Sent By swelter Date 2023-02-22 Time 11:50 Rev Time 0.00
Received By swelter Date 2023-03-07 Time 09:32 Sent To  
Notes
2023-02-22 11:54:04 
 ART ASSESSMENT COMPLETED AND RECEIVED 3.7.2023 OPTION
 #2 PUBLIC ART CONTRIBUTION - FOUNDATION PERMIT ONLY -
 OPTION 2 IS DUE AT TIME OF BUILDING PERMIT FEES -
 MASTER PERMIT 22120881
  
 CONTACT SYBILLE WELTER AT [email protected] X1521 ASAP
 FOR PUBLIC ART ASSESSMENT APPLICATION; DUE NOW AT TIME
 OF PERMITTING WITH EVIDENCE OF ESCROW.

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status N Date   Cont ID  
Sent By   Date 2022-12-27 Time   Rev Time 0.00
Received By   Date 2022-12-27 Time   Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2023-03-31 Cont ID  
Sent By lbond Date 2023-03-31 Time 15:16 Rev Time 0.00
Received By lbond Date 2023-03-31 Time 15:16 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2023-03-09 Cont ID  
Sent By lbond Date 2023-03-09 Time 11:04 Rev Time 0.00
Received By lbond Date 2023-03-09 Time 11:04 Sent To  
Notes
2023-03-09 11:13:56BUILDING REVIEW COMMENTS:
  
 W.P.B. PERMIT: 22120881
  
 REVIEWED: MARCH 9, 2023
  
 FLORIDA BUILDING CODE,7TH EDITION (2020)
 FBC[AMENDED] = 2017 CHAPTER 1 WPB AMENDMENTS (SEE LINK
 BELOW)
 HTTPS://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/
 BUILDING-PERMIT-FORMS
 FBC BUILDING
 FBC EXISTING BUILDING
  
 COMMENTS:
  
 SECTION 107.2.1 WPB
 INCLUDE GEOTECHNICAL REPORT IN SUPPORTING DOCUMENTS.
 SHEET G-100 DATE FOR SHEET LS-101, 102, 103 SHOULD SAY
 7/27/22
  
  
 IF YOU HAVE ANY QUESTIONS OR CONCERNS, PLEASE DO NOT
 HESITATE TO CONTACT ME
  
 LOUIS BOND, AIA
 BUILDING PLANS EXAMINER II
 DEVELOPMENT SERVICES DEPT.
 BUILDING DIVISION
 401 CLEMATIS STREET
 WEST PALM BEACH, FLORIDA 33401
 PH: 561-805-6729
 FX: 561-805-6676
 EMAIL: [email protected]
  
  
 NOTES:
 PLEASE PROVIDE COMMENT RESPONSE SHEET TO EXPLAIN HOW
 EACH COMMENT IS BEING ADDRESSED.
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2023-03-09 Cont ID  
Sent By mpeterso Date 2023-03-09 Time 15:18 Rev Time 0.00
Received By mpeterso Date 2023-03-08 Time 12:55 Sent To  
Notes
2023-03-09 15:19:25AUDIT OF ELECTRICAL PLANS PASSED.MP

Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2023-03-01 Cont ID  
Sent By vnoel Date 2023-03-01 Time 13:18 Rev Time 0.00
Received By vnoel Date 2023-03-01 Time   Sent To  
Notes
2023-03-01 13:22:08PASSED WITH PROVISO:
  
 1. NO ENGINEERING PLANS HAVE BEEN APPROVED. DEVELOPER
 ASSUMES ALL RISK AND LIABILITY OF FOUNDATION APPROVAL
 WITHOUT APPROVED ENGINEERING PLANS.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2023-01-17 Cont ID  
Sent By rrossano Date 2023-01-17 Time   Rev Time  
Received By rrossano Date 2023-01-17 Time   Sent To  
Notes
2023-01-17 12:12:09PROJECT IS STILL UNDER FORMAL SITE PLAN REVIEW.

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2023-03-28 Cont ID  
Sent By pleduc Date 2023-03-28 Time   Rev Time 0.00
Received By pleduc Date 2023-03-28 Time 11:59 Sent To  
Notes
2023-03-28 12:01:18FIRE PROVISO:
  
 SHOULD THERE BE ANY FIRE LINE UNDERGROUND WORK
 ASSOCIATED
 WITH THIS FOUNDATION PERMIT IT SHALL BE INSTALLED UNDER
 A SEPARATE
 PERMIT & SHOP DRAWINGS.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2023-01-10 Cont ID  
Sent By pleduc Date 2023-01-10 Time   Rev Time 0.00
Received By pleduc Date 2023-01-09 Time 10:22 Sent To  
Notes
2023-01-09 12:45:54FIRE PROVISO:
  
 SHOULD THERE BE ANY FIRE LINE UNDERGROUND WORK
 ASSOCIATED
 WITH THIS FOUNDATION PERMIT IT SHALL BE INSTALLED UNDER
 A SEPARATE
 PERMIT & SHOP DRAWINGS.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2023-03-31 Cont ID  
Sent By lbond Date 2023-03-31 Time 15:16 Rev Time 0.00
Received By lbond Date 2023-03-31 Time 15:16 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2023-03-30 Cont ID  
Sent By lbond Date 2023-03-30 Time 09:57 Rev Time 0.00
Received By lbond Date 2023-03-28 Time 07:28 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2023-03-29 Cont ID  
Sent By shill Date 2023-03-28 Time 07:28 Rev Time 0.00
Received By shill Date 2023-03-27 Time 08:16 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date   Cont ID  
Sent By   Date 2023-03-15 Time   Rev Time 0.00
Received By shill Date 2023-03-07 Time 14:39 Sent To  
Notes
2023-03-13 14:40:51TO AUDIT
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date   Cont ID  
Sent By   Date 2023-03-07 Time   Rev Time 0.00
Received By lmarchan Date 2023-03-06 Time 16:00 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2023-01-24 Cont ID  
Sent By aoliver Date 2023-01-24 Time 16:03 Rev Time 0.00
Received By aoliver Date 2023-01-06 Time 15:55 Sent To  
Notes
***NONE***

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status N Date 2023-02-16 Cont ID  
Sent By rbrown Date 2023-02-16 Time 11:04 Rev Time 0.00
Received By rbrown Date 2023-02-16 Time 11:03 Sent To  
Notes
2023-02-16 11:04:44IMPACT FEES WILL BE PAID PRIOR TO ISSUANCE OF BUILDING
 PERMIT # 22120880

Review Stop M MECHANICAL (A/C)
Rev No 2 Status N Date 2023-03-31 Cont ID  
Sent By medwards Date 2023-03-31 Time 14:10 Rev Time 0.00
Received By medwards Date 2023-03-31 Time 14:10 Sent To  
Notes
2023-03-31 14:11:57THIS IS FOR THE FOUNDATION ONLY. THE NARRATIVE STATES
 THE MECHANICAL DRAWINGS WERE REMOVED. THEY WERE NOT
 REMOVED BUT I DID LOCK THEM SO THEY WILL NOT BE PRINTED
 AND MISTAKEN AS APPROVED. ME

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2023-03-09 Cont ID  
Sent By medwards Date 2023-03-09 Time 12:54 Rev Time 0.00
Received By medwards Date 2023-03-09 Time 12:54 Sent To  
Notes
2023-03-09 12:55:37THE PERMIT APPLICATION IS FOR FOUNDATION ONLY. REMOVE
 ALL MECHANICAL SHHETS THAT DO NOT PERTAIN TO THE
 FOUNDATION OF THIS PROJECT.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop P PLUMBING
Rev No 2 Status P Date 2023-03-31 Cont ID  
Sent By rwbrown Date 2023-03-31 Time 15:21 Rev Time 0.00
Received By rwbrown Date 2023-03-31 Time 15:21 Sent To  
Notes
2023-03-31 15:22:43AUDIT ONLY

Review Stop P PLUMBING
Rev No 1 Status F Date 2023-03-15 Cont ID  
Sent By ccole Date 2023-03-15 Time 10:34 Rev Time 0.00
Received By ccole Date 2023-03-15 Time 07:41 Sent To  
Notes
2023-03-15 10:34:521ST REVIEW FBC-2020 PLUMBING
 PERMIT- 22120881
 3/15/23
  
 CODES IN EFFECT:
 FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC
  
 PLUMBING AUDIT RESULTS.
  
 1) SHEETS P101A & P101B: SEPARATE PERMIT APPLICATIONS
 AND PLAN SUBMITTALS ARE REQUIRED AT THIS TIME FOR THE
 POTABLE WATER BACKFLOW PREVENTERS AND THE GREASE
 INTERCEPTORS. IF YOU DO NOT CURRENTLY HAVE CONTRACTORS
 SELECTED AND PLANS FINALIZED FOR THESE ITEMS, YOU CAN
 SUBMIT APPLICATIONS- TBD (TO BE DETERMINED) BY EMAILING
 COMPLETED PERMIT APPLICATIONS TO
 [email protected]. YOU WILL RECEIVE INSTRUCTIONS
 TO PAY FEES AND UPLOAD PLANS. YOU MAY UPLOAD PLANS AND
 PAY FEES AT A FUTURE DATE, BUT THE APPLICATIONS ARE
 REQUIRED AT THIS TIME. WE RECOMMEND THAT YOU PAY FEES
 AND UPLOAD PLANS AT THE SAME TIME. AFTER YOU HAVE THE
 PERMIT(S) GENERATED, NOTIFY ME VIA EMAIL AND I WILL
 CHANGE THE AUDIT STATUS TO PASS.
  
 PLEASE NOTE YOU HAVE THE OPTION OF SUBMITTING ONE
 APPLICATION FOR BOTH THE CONDO TOWER AND RENTAL TOWER
 BACKFLOW PREVENTERS, OR TWO IF PREFERRED. IT MAY BE A
 BETTER OPTION TO SUBMIT SEPARATE APPLICATIONS FOR THE
 CAFE INTERCEPTORS AND THE FUTURE TENANT INTERCEPTORS
 SINCE THE WORK MAY PROCEED ON DIFFERENT TIMELINES.
 CONCERNING THE INTERCEPTORS PLEASE REVIEW THE FOLLOWING
 DEFERRED SUBMITTAL REQUIREMENTS.
 A) MANUFACTURER'S SPECIFICATIONS AND INSTALLATION
 GUIDELINES WITH APPROVAL STAMP BY THE ENGINEER OF
 RECORD- SEC.1003.3. FBC P.
 B) EQUIPMENT SCHEDULE INDICATING THE MAKES AND MODELS
 AND CAPACITIES OF THE INTERCEPTORS.
 C) SIZING CALCULATIONS IN ACCORDANCE WITH ASME
 A112.14.3, ASME A112.14.4, ASME A112.14.6, CSA B481.3,
 OR PDI G101- SEC. 1003.3.5 FBC P.
 D) ENLARGED PIPING DIAGRAM OR ISOMETRIC DRAWING SHOWING
 LOCATIONS AND SIZES OF INLETS, OUTLETS, VENTS, AND
 CLEANOUTS. PLEASE NOTE THE CITY OF WPB UTILITIES DEPT.
 REQUIRES A TWO-WAY CLEANOUT FOR USE AS A SAMPLING PORT.
 PLEASE PROVIDE A CLEANOUT DETAIL ON THE PLANS.
 E) ACCESS LID DETAILS INDICATING THE LIDS WILL BE HEAVY
 DUTY TRAFFIC RATED AND WILL BE EQUIPPED WITH ACCESS
 RESTRICTORS. HEAVY DUTY LIDS ARE ALSO REQUIRED FOR THE
 CLEANOUTS.
  
 2) P101A & P101B: THE PLANS DO NOT SHOW THE BELOW SLAB
 SANITARY PIPING FOR THE BATHROOM FIXTURES, WASTE
 PIPING, LOCATIONS OF FLOOR DRAINS OR OTHER INDIRECT
 WASTE FIXTURES TO BE INSTALLED TYPICALLY IN THE PUMP
 ROOMS AND TRASH ROOMS; AND ELEVATOR SUMP PUMP PITS AND
 DISCHARGE PIPING RUNS AND DISPOSAL LOCATIONS- SEC.
 107.2.1 WPB.
 A) CONCERNING THE FLOOR DRAINS, IF TRAP PRIMERS ARE TO
 BE INSTALLED PLEASE SHOW THE WATER PIPING CONNECTION
 LOCATIONS- SEC. 1002.4.1.1. FBC P.
  
 3) P101A & P101B: PROVIDE A SANITARY DRAINAGE AND VENT
 ISOMETRIC DRAWING FOR THE BELOW FLOOR SLAB PLUMBING
 INCLUDING THE GREASE WASTE PIPING SYSTEM- SECS. 107.2.1
 WPB & 107.3.5.1.3 WPB.
  
 4) P101A: PLEASE SHOW THE GREASE WASTE AND SANITARY
 PIPE SIZES ON THE DRAWINGS- TABLE 710.1(1) FBC P.
  
 5) P-101.1A: THE PLAN SHOWS UNIDENTIFIED PIPING RUNNING
 BETWEEN THE DPR PUMP ROOM AND THE BUILDING EXTERIOR.
 PLEASE LABEL THE TYPES AND SIZES OF PIPING- SEC.
 107.2.1 WPB. CLARIFY IF ANY OF THE PIPING IS BELOW THE
 SLAB. CONCERNING THE ABOVE CEILING GAS PIPING ON THE
 EAST SIDE OF THE BUILDING, SEE COMMENT #6 BELOW.
  
 6) SHEET P-101.1B IS NOT NECESSARY FOR THIS FOUNDATION
 ONLY PERMIT BECAUSE IT SHOWS GAS METERS AND GAS PIPING
 RUNS ABOVE THE FIRST FLOOR CEILINGS. NO WORK SHOWN ON
 THE PLANS WILL BE PERMITTED UNDER THIS FOUNDATION ONLY
 PERMIT, AND THE PLAN WILL BE LOCKED OUT AT TIME OF
 PLUMBING PLAN APPROVAL- SEC. 107.2.1 WPB.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 1 Status P Date 2023-03-14 Cont ID  
Sent By jbaker Date 2023-03-14 Time 08:07 Rev Time 0.00
Received By jbaker Date 2023-03-08 Time 12:30 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date   Cont ID  
Sent By   Date 2023-03-09 Time   Rev Time 0.00
Received By lbond Date 2023-03-09 Time 10:29 Sent To  
Notes
2023-03-09 12:56:29MECHANICAL DIGITAL SIGNATURES APPROVED ME
2023-03-09 10:32:08ARCHITECT SIGNATURE PASSED
 BUILDING AFFIDAVIT ENGINEER SIGNATURE PASSD

Review Stop Z ZONING
Rev No 2 Status P Date 2023-03-07 Cont ID  
Sent By llouie Date 2023-03-07 Time   Rev Time 0.00
Received By llouie Date 2023-03-07 Time   Sent To  
Notes
2023-03-07 09:37:49ZONING APPROVED WITH THEE FOLLOWING PROVISO(S):
  
 1.) THIS APPROVAL IS FOR THE FOUNDATION PERMIT ONLY.
  
 2.) VERTICAL CONSTRUCTION OF THE PROJECT (PERMIT
 #22120880) IS SUBJECT TO THE CONDITIONS PROVIDED IN
 FORMAL SITE PLAN APPROVAL LETTER FSPR 22-11 (ISSUED ON
 02.28.2023).
  
 3.) MINOR SITE PLAN AMENDMENT REQUIRED FOR THE AS-BUILT
 PRIOR TO THE ISSUANCE OF A FINAL CERTIFICATE OF
 OCCUPANCY (C.O.).
  
 (REFERENCE: FSPR CASE NO. 22-11, RESOLUTION NO. 18-23)
  

Review Stop Z ZONING
Rev No 1 Status F Date 2023-01-24 Cont ID  
Sent By LLouie Date 2023-01-24 Time   Rev Time  
Received By llouie Date 2023-01-24 Time   Sent To  
Notes
2023-01-24 15:24:57** FAILED **
  
 PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE
 COMMENTS IN WRITING AND/OR ON THE PLANS WHERE
 APPLICABLE:
  
 1.) FINAL SITE PLAN APPROVAL MUST BE ISSUED BEFORE
 ZONING CAN SIGN-OFF ON THE FOUNDATION PERMIT. AT THIS
 TIME, FINAL SITE PLAN APPROVAL IS STILL PENDING WITH
 THE PLANNING DIVISION (AWAITING RESUBMITTAL FROM THE
 APPLICANT ADDRESSING ALL COMMENTS REQUIRED PRIOR TO
 FINAL SITE PLAN APPROVAL).
  
  
 NOTES:
  
 * ANY REVISIONS MAY RESULT IN ADDITIONAL COMMENTS.
  
 * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE
 QUESTIONS.
  
 * ZONE: CMUD (OLARA PROJECT)
  
 * REFERENCE: FSPR 22-11
  