Review Stop AD ADDRESSING
Rev No 3 Status P Date 2022-12-16 Cont ID  
Sent By cpuell Date 2022-12-16 Time 11:33 Rev Time 0.00
Received By cpuell Date 2022-12-16 Time 11:33 Sent To  
Notes
2022-12-16 11:33:46SEPARATE PERMIT SAPPLIED FOR THE DEMOS. THIS PERMIT IS
 FOR PARCE 74434309050530040L 2501 PINEWOOD AVE ONLY

Review Stop AD ADDRESSING
Rev No 2 Status F Date 2022-11-19 Cont ID  
Sent By cpuell Date 2022-11-19 Time 09:55 Rev Time 0.00
Received By cpuell Date 2022-11-19 Time 09:54 Sent To  
Notes
2022-11-19 09:55:10PLANS INDICATE THAT THE DEMOLITION ARE FOR TWO SEPARATE
 PARCELS, PARCEL 74434309050520500 HAS TWO STRUCTURES
 WHICH HAVE THE ADDRESSES OF 550 NORTHWOOD RD AND 602
 NORTHWOOD RD, THE SECOND PARCEL 74434309050480050 HAS
 ONE STRUCTURE WITH THE ADDRESS OF 610 25TH ST. TWO
 PERMITS WILL BE REQUIRED, ONE FOR EACH PARCEL, PLEASE
 LET ME KNOW WHICH PARCEL YOU WOULD LIKE THIS PERMIT
 22080666 TO BE FOR AND ALSO PLEASE LET ME KNOW WHAT THE
 SECOND PERMIT NUMBER IS FOR THE SECONDARY PARCEL.
 PLEASE CONTACT [email protected] TO APPLY FOR THE
 SECOND PERMIT. CONTACT [email protected] OR CALL
 561-805-6659 FOR THE ADDRESSING RESPONSES.

Review Stop AD ADDRESSING
Rev No 1 Status F Date 2022-09-27 Cont ID  
Sent By cpuell Date 2022-09-27 Time 17:08 Rev Time 0.00
Received By cpuell Date 2022-09-27 Time 17:08 Sent To  
Notes
2022-09-27 17:09:20PLEASE PROVIDE A SITE PLAN OR AERIAL MAP SHOWING THE
 EXACT BUILDINGS TO BE DEMOLISHED. PLEASE EMAIL RESPONSE
 TO [email protected] OR CALL 561-805-6659

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2023-03-22 Cont ID  
Sent By pvalenti Date 2023-03-22 Time 08:42 Rev Time 0.00
Received By pvalenti Date 2023-03-21 Time 10:22 Sent To  
Notes
2023-03-22 08:57:31PETER E VALENTI
 BUILDING PLANS EXAMINER II/INSPECTOR
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW APPROVED WITH PROVISO:
  
 1.) PRIOR TO ANY PHASE OF DEMO WORK THE STATE LICENSED
 ELECTRICAL CONTRACTOR IS REQUIRED TO PROVIDE A
 CONFIRMATION LETTER STATING THAT ALL ELECTRIC IN AREA
 OF WORK HAS BEEN DISCONNECTED AND AREA IS SAFE FOR
 WORK.
  
 2.) THE PLUMBING CONTRACTOR IS REQUIRED TO CAP SEWER
 LATERAL IN ALL PHASES OF DEMOLITION. THE CONTRACTOR IS
 RESPONSIBLE FOR SCHEDULING CITY PLUMBING INSPECTIONS
 FOR THE CAPPING OF LINES PRIOR TO CONCEALING/COVERING
 UP AREAS OF WORK.
  
 3.) A HYDRANT METER PERMIT HAS BEEN OBTAINED THROUGH
 THE UTILITIES DEPARTMENT FOR WATERING DOWN SITE DURING
 DEMOLITION AS NEEDED.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2023-01-30 Cont ID  
Sent By pvalenti Date 2023-01-30 Time 10:49 Rev Time 0.00
Received By pvalenti Date 2023-01-30 Time 08:35 Sent To  
Notes
2023-01-30 10:51:28PETER E VALENTI
 BUILDING PLANS EXAMINER II
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW DENIED:
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING
 CODE, BUILDING 3303:
  
 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC)
 RELEASE OF SERVICE CONFIRMATION.
 PLEASE PROVIDE ELECTRIC PERMIT INFORMATION FOR THE
 REMOVAL OF POWER POLES AND SAFE DISCONNECTING OF
 ELECTRIC.
  
 3. WATERDOWN METHOD:
 SINCE A BACKFLOW PREVENTER DEVICE HAS BEEN SELECTED AS
 THE METHOD OF WATERING DOWN SITE DURING DEMOLITION,
 PLEASE INFORM ME WHEN THE PLUMBING FINAL INSPECTION
 #703 HAS BEEN APPROVED. BEFORE SCHEDULING THE #703
 PLUMBING FINAL INSPECTION, THE BACKFLOW DEVICE NEEDS TO
 BE TESTED AND CERTIFIED BY THE CITY PUBLIC UTILITIES
 DEPARTMENT, 561 822 2244. FAX THE COMPLETED "DEMOLITION
 APPLICATION" FORM TO
 561-822-2183.
  
 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED (SUBMIT
 APPLICATION TO BUILDING DIVISION);
 SCHEDULE A FINAL PLUMBING #703 INSPECTION AND INFORM ME
 WHEN THE PLUMBING FINAL INSPECTION #703 HAS BEEN
 APPROVED.
  
  
 PETER E VALENTI
 BUILDING PLANS EXAMINER II
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW DENIED:
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING
 CODE, BUILDING 3303:
  
 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC)
 RELEASE OF SERVICE CONFIRMATION.
 PLEASE PROVIDE ELECTRIC PERMIT INFORMATION FOR THE
 REMOVAL OF POWER POLES AND SAFE DISCONNECTING OF
 ELECTRIC.
  
 3. WATERDOWN METHOD:
 SINCE A BACKFLOW PREVENTER DEVICE HAS BEEN SELECTED AS
 THE METHOD OF WATERING DOWN SITE DURING DEMOLITION,
 PLEASE INFORM ME WHEN THE PLUMBING FINAL INSPECTION
 #703 HAS BEEN APPROVED. BEFORE SCHEDULING THE #703
 PLUMBING FINAL INSPECTION, THE BACKFLOW DEVICE NEEDS TO
 BE TESTED AND CERTIFIED BY THE CITY PUBLIC UTILITIES
 DEPARTMENT, 561 822 2244. FAX THE COMPLETED "DEMOLITION
 APPLICATION" FORM TO
 561-822-2183.
  
 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED (SUBMIT
 APPLICATION TO BUILDING DIVISION);
 SCHEDULE A FINAL PLUMBING #703 INSPECTION AND INFORM ME
 WHEN THE PLUMBING FINAL INSPECTION #703 HAS BEEN
 APPROVED.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2022-12-06 Cont ID  
Sent By pvalenti Date 2022-12-06 Time 16:45 Rev Time 0.00
Received By pvalenti Date 2022-12-06 Time 16:01 Sent To  
Notes
2022-12-06 16:09:20PETER E VALENTI
 BUILDING PLANS EXAMINER II
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW DENIED:
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING
 CODE, BUILDING 3303:
  
 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC)
 RELEASE OF SERVICE CONFIRMATION.
 PLEASE PROVIDE ELECTRIC PERMIT INFORMATION FOR THE
 REMOVAL OF POWER POLES AND SAFE DISCONNECTING OF
 ELECTRIC.
  
 3. WATERDOWN METHOD:
 SINCE A BACKFLOW PREVENTER DEVICE HAS BEEN SELECTED AS
 THE METHOD OF WATERING DOWN SITE DURING DEMOLITION,
 PLEASE INFORM ME WHEN THE PLUMBING FINAL INSPECTION
 #703 HAS BEEN APPROVED. BEFORE SCHEDULING THE #703
 PLUMBING FINAL INSPECTION, THE BACKFLOW DEVICE NEEDS TO
 BE TESTED AND CERTIFIED BY THE CITY PUBLIC UTILITIES
 DEPARTMENT, 561 822 2244. FAX THE COMPLETED "DEMOLITION
 APPLICATION" FORM TO
 561-822-2183.
  
 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED (SUBMIT
 APPLICATION TO BUILDING DIVISION);
 SCHEDULE A FINAL PLUMBING #703 INSPECTION AND INFORM ME
 WHEN THE PLUMBING FINAL INSPECTION #703 HAS BEEN
 APPROVED.
  
  
 7. SEPARATE PERMITS ARE REQUIRED (ONE FOR EACH PARCEL)
 THAT INVOLVES WORK AS SUBMITTED FOR.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2022-10-03 Cont ID  
Sent By pvalenti Date 2022-10-03 Time 11:10 Rev Time 0.00
Received By pvalenti Date 2022-10-03 Time 11:10 Sent To  
Notes
2022-10-03 11:24:07PETER E VALENTI
 BUILDING PLANS EXAMINER II
 [email protected]
 561 805 6673
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW DENIED:
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING
 CODE, BUILDING 3303:
  
 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC)
 RELEASE OF SERVICE CONFIRMATION
  
 2. UTILITY RELEASE - FLORIDA PUBLIC UTILITIES (GAS)
 RELEASE OF SERVICE CONFIRMATION
  
 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER
 DEPARTMENT, REQUEST FOR METER PULL, ON
 THEIR FORM "DEMOLITION APPLICATION"
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
 WATERDOWN METHOD:
 IF A WATER TRUCK IS DESIRED, PROVIDE DETAILED
 INFPRMATION OF THE WATER TRUCK SUCH AS: THE
 GALLON CAPACITY OF THE WATER TANK AND A LETTER
 INCLUDING A STATEMENT THAT THE WATER
 USED WILL BE POTABLE AND FROM AN OFF-SITE LOCATION ONLY
 AND WILL BE ON-SITE AT ALL TIMES
 DURING DEMOLITION.
 IF A HYDRANT METER OR BACKFLOW PREVENTER IS DESIRED,
 THEN A PARTIAL RELEASE WILL BE NOTED
 ON THEIR FORM. IF THE BACKFLOW PREVENTER DEVICE IS
 SELECTED, A PLUMBING PERMIT IS REQUIRED. BEFORE
 SCHEDULING THE 703(PLUMBING FINAL INSPECTION), THE
 BACKFLOW DEVICE NEEDS TO BE TESTED AND CERTIFIED BY
 THE CITY???S UTILITIES DEPT, 561-822-2244. FAX THE
 COMPLETED "DEMOLITION APPLICATION" FORM TO
 561-822-2183.
  
 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED (SUBMIT
 APPLICATION TO BUILDING DIVISION);
 SCHEDULE A FINAL PLUMBING #703.
  
 6. COMPLETE THE DEMO DEBRIS FORM: HTTP://WPB.ORG/DEPART
 MENTS/DEVELOPMENT-SERVICES/FORMS/BUILDING-PERMIT-FORMS
 IF THE FORM IS NOT AVAILABLE ONLINE, SEND A REQUEST FOR
 THE FORM TO [email protected].
  
 7. SEPARATE PERMITS ARE REQUIRED (ONE FOR EACH PARCEL)
 THAT INVOLVES WORK AS SUBMITTED FOR.
  
  

Review Stop ENG ENGINEERING CSD
Rev No 3 Status P Date 2023-01-17 Cont ID  
Sent By rrossano Date 2023-01-17 Time   Rev Time 0.00
Received By rrossano Date 2023-01-17 Time   Sent To  
Notes
2023-01-17 11:01:42DEMO PROVISOS
  
 APPROVAL IS FOR SITE WORK ONLY (NO RIGHT OF WAY).
  
 THERE ARE WATER AND SEWER LINES IN THE VICINITY OF THIS
 PROJECT. PER CHAPTER 556 OF THE FLORIDA STATE STATUTES,
 YOU MUST CALL 811 FOR UTILITY LOCATES AT LEAST TWO FULL
 BUSINESS DAYS IN ADVANCE OF ANY CONSTRUCTION OR
 DEMOLITION WORK. INFORMATION CAN BE FOUND HERE:
 HTTP://WWW.SUNSHINE811.COM/
  
 THANKS,
 RICK ROSSANO, SENIOR PROJECT COORD., WPB ENG. SERVICES
 DEPT., 561-494-1098, FAX: 561-494-1116 [email protected]
 FOR 24-HOUR EMERGENCY RESPONSE SERVICES TO PUBLIC
 UTILITIES, PUBLIC WORKS, PARKS, ETC. 561-822-2210
  
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2022-11-21 Cont ID  
Sent By rrossano Date 2022-11-21 Time   Rev Time 0.00
Received By rrossano Date 2022-11-21 Time   Sent To  
Notes
2022-11-21 10:18:07PROJECT IS STILL UNDER SITE PLAN REVIEW.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-09-27 Cont ID  
Sent By rrossano Date 2022-09-27 Time   Rev Time  
Received By rrossano Date 2022-09-27 Time   Sent To  
Notes
2022-09-27 10:59:54PROJECT IS STILL UNDER SITE PLAN REVIEW.

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2022-10-06 Cont ID  
Sent By amhamilt Date 2022-10-06 Time 16:33 Rev Time 0.00
Received By amhamilt Date 2022-10-06 Time 16:33 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2023-03-22 Cont ID  
Sent By pvalenti Date 2023-03-22 Time 09:10 Rev Time 0.00
Received By pvalenti Date 2023-03-17 Time 12:39 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2023-01-30 Cont ID  
Sent By pvalenti Date 2023-01-30 Time 10:51 Rev Time 0.00
Received By pvalenti Date 2023-01-12 Time 09:39 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-12-07 Cont ID  
Sent By pvalenti Date 2022-12-07 Time 08:03 Rev Time 0.00
Received By pvalenti Date 2022-11-18 Time 07:21 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-10-07 Cont ID  
Sent By pvalenti Date 2022-10-07 Time 06:27 Rev Time 0.00
Received By pvalenti Date 2022-09-27 Time 05:31 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2023-03-22 Cont ID  
Sent By pvalenti Date 2023-03-22 Time 09:03 Rev Time 0.00
Received By pvalenti Date 2023-03-22 Time 09:00 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-12-07 Cont ID  
Sent By pvalenti Date 2022-12-07 Time 08:03 Rev Time 0.00
Received By pvalenti Date 2022-12-06 Time 16:01 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-10-03 Cont ID  
Sent By pvalenti Date 2022-10-03 Time 11:09 Rev Time 0.00
Received By pvalenti Date 2022-10-03 Time 11:09 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2022-10-11 Cont ID  
Sent By amhamilt Date 2022-10-11 Time 16:26 Rev Time 0.00
Received By amhamilt Date 2022-10-11 Time 16:26 Sent To  
Notes
2023-01-06 10:23:17*****THIS PERMIT NUMBER ONLY APPLIES TO THE DEMO ON
 2501 PINEWOOD.*****
  
 NOT ALL PERMITS LISTED ON THE FRONT SCREEN HAVE PASSED
 AND COVERED BY THE FEES/PLANS ARE APPROVED.
  
 CONTACT ERIC SCHNEIDER @ 561-822-1446
 [email protected]
  
2022-10-11 16:26:15AS THERE IS NO EXISTING STRUCTURE ON THE SITE, PERMIT
 HAS PASSED CONDITIONALLY: NO TREES IN THE RIGHT OF WAY
 WILL BE ALTERED WITHOUT A SEPARATE PERMIT
  
 ANNE HAMILTON
 HISTORIC PRESERVATION PLANNER
 [email protected]
 561.822.1428
  

Review Stop Z ZONING
Rev No 1 Status F Date 2022-10-06 Cont ID  
Sent By amhamilt Date 2022-10-06 Time 16:34 Rev Time 0.00
Received By amhamilt Date 2022-10-06 Time 16:33 Sent To  
Notes
2022-10-06 16:35:01THE PERMIT HAS FAILED FOR THE FOLLOWING REASON(S)
  
 SEC 94-210 (D)(5)
 "EXISTING BUILDINGS MAY NOT BE DESTROYED OR REMOVED
 UNTIL A BUILDING PERMIT HAS BEEN ISSUED FOR A
 REPLACEMENT BUILDING WHICH COMPLIES WITH THE NMUD
 REGULATIONS"
  
 ANNE HAMILTON
 HISTORIC PRESERVATION PLANNER
 [email protected]
 561.822.1428
  


Account Summary | Usage Policy | Privacy Policy