Plan Review Details - Permit 22080422
Plan Review Stops For Permit 22080422
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2022-10-07 Cont ID  
Sent By cthroop Date 2022-10-07 Time 13:32 Rev Time 0.00
Received By cthroop Date 2022-10-07 Time 12:50 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2022-09-14 Cont ID  
Sent By cthroop Date 2022-09-14 Time 12:50 Rev Time 0.00
Received By cthroop Date 2022-09-13 Time 10:06 Sent To  
Notes
2022-09-14 12:56:06PLAN REVIEW BUILDING
  
 CHRISTOPHER S. THROOP, C.B.O., CFM
 PLANS EXAMINER II PX3169/SFP306
 BU1635 BN4338
 ASFPM CFM US-21-11935
 CITY OF WEST PALM BEACH
 (561) 805-6726
 [email protected]
  
 CODES IN EFFECT:
 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST
 PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE,
 CHAPTER 1 ADMINISTRATION
 NFPA 70 2017 EDITION NEC 2017
  
 1ST REVIEW
  
 RESULTS: DENIED
 ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT
  
 1.PROVIDE A COPY OF THE MOST RECENT BOUNDARY LINE
 SURVEY.
 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS
 SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH
 107.2.5.
  
 2. PROVIDE A SITE PLAN....
 107.2.5 SITE PLAN. THE CONSTRUCTION DOCUMENTS SUBMITTED
 WITH THE APPLICATION FOR PERMIT SHALL BE ACCOMPANIED BY
 A SITE PLAN SHOWING TO SCALE THE SIZE AND LOCATION OF
 NEW CONSTRUCTION AND EXISTING STRUCTURES ON THE SITE,
 AND IT SHALL BE DRAWN IN ACCORDANCE WITH AN ACCURATE
 AND INCLUDED BOUNDARY LINE SURVEY.
  
 3. PROVIDE A SITE DRAINAGE PLAN PER FBC R401.3
 IT SHALL BE DRAWN IN ACCORDANCE WITH AN ACCURATE AND
 INCLUDED BOUNDARY LINE SURVEY.
 FBC R401.3 SITE DRAINAGE
 SURFACE DRAINAGE SHALL BE DIVERTED TO A STORM SEWER
 CONVEYANCE OR OTHER APPROVED POINT OF COLLECTION THAT
 DOES NOT CREATE A HAZARD.
 LOTS SHALL BE GRADED TO DRAIN SURFACE WATER AWAY FROM
 FOUNDATION WALLS. THE GRADE SHALL FALL A MINIMUM OF 6
 INCHES WITHIN THE FIRST 10 FEET.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
  
 WHEN RESUBMITING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-08-23 Cont ID  
Sent By fgiaquin Date 2022-08-23 Time 22:40 Rev Time 0.00
Received By fgiaquin Date 2022-08-23 Time 20:06 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-10-07 Cont ID  
Sent By cthroop Date 2022-10-07 Time 13:32 Rev Time 0.00
Received By cthroop Date 2022-09-19 Time 08:16 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-09-14 Cont ID  
Sent By shill Date 2022-09-14 Time 14:00 Rev Time 0.00
Received By shill Date 2022-08-17 Time 09:21 Sent To  
Notes
***NONE***

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 2 Status P Date 2022-10-17 Cont ID  
Sent By lmarchan Date 2022-10-17 Time 11:38 Rev Time 0.00
Received By lmarchan Date 2022-10-11 Time 07:26 Sent To  
Notes
2022-10-17 11:38:33NO FEES DUE PER IMPACT OFFICE. LEM
2022-10-11 07:26:5410/11/2022 EMAILED IMPACT FOR REVIEW-AO

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status F Date 2022-09-14 Cont ID  
Sent By cthroop Date 2022-09-14 Time 12:48 Rev Time 0.00
Received By cthroop Date 2022-09-14 Time 12:48 Sent To  
Notes
2022-09-14 12:50:01IMPACT FEES
 PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE
 DIGITALLY VIA PROJECT DOX UPON NOTIFICATION BY THIS
 OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST
 FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE
 OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL
 IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME
 THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM
 CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS
 TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF UPON
 APPROVAL AND FEE PAYMENT (IF ANY), PLEASE UPLOAD THE
 RECEIPT TO YOUR PROJECT OR EMAIL IT TO
 [email protected] .
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2022-08-22 Cont ID  
Sent By medwards Date 2022-08-22 Time 15:27 Rev Time 0.00
Received By medwards Date 2022-08-22 Time 15:27 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2022-08-23 Cont ID  
Sent By ccole Date 2022-08-23 Time 12:17 Rev Time 0.00
Received By ccole Date 2022-08-22 Time 15:40 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status N Date 2022-09-14 Cont ID  
Sent By cthroop Date 2022-09-14 Time 10:14 Rev Time 0.00
Received By cthroop Date 2022-09-14 Time 10:14 Sent To  
Notes
2022-09-14 10:15:51PROVISO ON PLAN PAGE A-004: A SEPERATE ROOFING PERMIT
 IS REQUIRED. CT

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-10-07 Cont ID  
Sent By cthroop Date 2022-10-07 Time 13:32 Rev Time 0.00
Received By cthroop Date 2022-10-07 Time 12:50 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-09-14 Cont ID  
Sent By cthroop Date 2022-09-14 Time 12:48 Rev Time 0.00
Received By cthroop Date 2022-09-13 Time 10:06 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2022-09-29 Cont ID  
Sent By vbroglia Date 2022-09-29 Time 10:25 Rev Time 0.00
Received By vbroglia Date 2022-09-29 Time 10:24 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2022-08-29 Cont ID  
Sent By vbroglia Date 2022-08-29 Time 12:19 Rev Time 0.00
Received By vbroglia Date 2022-08-29 Time 12:19 Sent To  
Notes
2022-08-29 12:21:598/29/2022 FAILED
  
 PLEASE PROVIDE A SURVEY OR SITE PLAN THAT SHOW THE
 SETBACKS OF THE STRUCTURE TO THE PROPERTY LINES
  
  
 **** FAILED ****