| 2022-09-22 14:47:33 | NEW CONCESSION AND RESTROOM BUILDINGS |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) PLEASE SHOW THE WALL FINISHES SURROUNDING THE |
| | MOP/SERVICE SINK TO COMPLY WITH FBC 1210.2.2 WALLS AND |
| | PARTITIONS. |
| | WALLS AND PARTITIONS WITHIN 2 FEET (610 MM) OF SERVICE |
| | SINKS, URINALS AND WATER CLOSETS SHALL HAVE A SMOOTH, |
| | HARD, NONABSORBENT SURFACE, TO A HEIGHT OF NOT LESS |
| | THAN 4 FEET (1219 MM) ABOVE THE FLOOR - (DRYWALL IS NOT |
| | CONSIDERED A HARD SURFACE) |
| | |
| | 2) PLEASE SHOW THE ATTIC ACCESS LOCATION AND SIZE PER |
| | FBC 1209.2 |
| | |
| | 3) PLEASE SHOW THE ATTIC VENTILATION PER FBC 1203.2 |
| | |
| | 4) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE |
| | INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| | PRODUCT APPROVALS FOR THE EXTERIOR WINDOWS, EXTERIOR |
| | DOORS, ROOFING SYSTEMS - ALL PRODUCT APPROVALS NEED TO |
| | BE REVIEWED AND MARKED APPROVED BY THE BUILDING |
| | DESIGNER OF RECORD - FBC WPB 107.3.4 |
| | |
| | 5) PLEASE PROVIDE SIGNED AND SEALED DETAILS FROM AN |
| | ARCHITECT OR ENGINEER FOR THE IRON SECURITY GATES |
| | ATTACHED TO THE RESTROOM BUILDING - WHICH ARE SUBJECT |
| | TO WIND LOADS PER FBC 1609 - OR PROVIDE PRODUCT |
| | APPROVALS AS NOTED IN COMMENT 4. |
| | |
| | 6) PLEASE SHOW THE BUILDING CONSTRUCTION TYPE PER FBC |
| | CHAPTER 6 |
| | |
| | 7) PLEASE PROVIDE SIGNED AND SEALED DETAILS FROM AN |
| | ARCHITECT OR ENGINEER FOR THE ALUMINUM CANOPIES - WHICH |
| | ARE SUBJECT TO WIND LOADS PER FBC 1609 - OR PROVIDE |
| | PRODUCT APPROVALS AS NOTED IN COMMENT 4. |
| | |
| | 8) PLEASE SHOW ON THE DRAWINGS THE WALL AND CEILING |
| | INSULATION IF ANY PER THE ENERGY CALCULATIONS. |
| | |
| | 9) PLEASE PROVIDE A COPY OF THE SOILS REPORT |
| | (GEOTECHNICAL REPORT) AS NOTED ON DRAWING S-3. |
| | |
| | 10) ACCESSIBLE RESTROOM = PLEASE SHOW THE DOOR |
| | MANEUVERING CLEARANCE FOR THE SECURITY GATE TO EXIT THE |
| | RESTROOM - FBC A 404.2.4 |
| | |
| | 11) ACCESSIBLE RESTROOM = PLEASE SHOW THE TOILET SEAT |
| | COVER DISPENSER ABOVE THE GRAB BAR TO COMPLY WITH THE |
| | REQUIRED CLEARANCE FBC A 609.3 THE SPACE BETWEEN THE |
| | GRAB BAR AND PROJECTING OBJECTS ABOVE SHALL BE 12 |
| | INCHES (305 MM) MINIMUM. |
| | |
| | 12) REST ROOMS = PLEASE SHOW THE STALL DIMENSIONS AND |
| | THE GRAB BAR DIMENSIONS FOR THE REQUIRED AMBULATORY |
| | ACCESSIBLE COMPARTMENT - PER FBC A 604.8.2 -- FBC A |
| | 213.3.1TOILET COMPARTMENTS. |
| | WHERE TOILET COMPARTMENTS ARE PROVIDED, AT LEAST ONE |
| | TOILET COMPARTMENT SHALL COMPLY WITH 604.8.1. IN |
| | ADDITION TO THE COMPARTMENT REQUIRED TO COMPLY WITH |
| | 604.8.1, AT LEAST ONE COMPARTMENT SHALL COMPLY WITH |
| | 604.8.2 WHERE SIX OR MORE TOILET COMPARTMENTS ARE |
| | PROVIDED, OR WHERE THE COMBINATION OF URINALS AND WATER |
| | CLOSETS TOTALS SIX OR MORE FIXTURES. |
| | |
| | 13) A SEPARATE PERMIT IS REQUIRED FOR THE EXISTING |
| | BUILDING DEMOLITION. |
| | |
| | 14) ITEMS SUCH AS ALUMINUM CANOPY DETAILS, ROOFING |
| | SYSTEMS, WINDOW AND DOOR PRODUCT APPROVALS MAY BE |
| | DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON |
| | THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED |
| | SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED |
| | SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN |
| | THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION |
| | AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| | WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL |
| | ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING |
| | OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS |
| | ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE |
| | BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL |
| | ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A |
| | NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| | DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| | CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| | BUILDING OFFICIAL. |
| | |