| 2022-08-04 10:36:36 | PLAN REVIEW COMMENTS |
| | |
| | 1ST REVIEW: FBC SIXTH EDITION (2017) |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | DENIED BY BUILDING |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) THE COSTRUCTION DOCUMENTS THAT WERE SUBMITTED FOR |
| | THE GROUND FLOOR AND GARAGE EXTERIOR GLAZING HAVE NOT |
| | BEEN REVIEWED AND APPROVED IN WRITING BY THE DESIGNER |
| | OF RECORD FOR THE PROJECT. WE REQUIRE ONE SET OF |
| | SUBMITTALS WITH THE DESIGNER OF RECORDS REVIEW STAMP |
| | AND ONE CLEAN SET FROM THE DELAGATE ENGINEER. FBC |
| | AMENDMENTS 107.3.4.1 DEFERRED SUBMITTALS. FOR THE |
| | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | |