| Plan Review Stops For Permit 22060744 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
N |
Date |
2022-10-13 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:23 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:23 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
N |
Date |
2022-09-16 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-09-16 |
Time |
15:22 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-09-16 |
Time |
14:38 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2022-08-18 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:13 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:13 |
Sent To |
|
|
| Notes |
| 2022-08-18 16:14:47 | SEE COMMENTS FOR GARAGE TYPE 1 (EAST). |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2022-07-28 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-07-28 |
Time |
10:11 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-07-28 |
Time |
09:18 |
Sent To |
|
|
| Notes |
| 2022-07-28 09:20:10 | PLAN REVIEW COMMENTS | | | 1ST REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) SUBMIT THE COMPLETE PRODUCT APPROVALS AND/OR | | | EVALUATION REPORTS FOR THE FLOOD VENT MODEL 1540-530 | | | AND TRIM AND SLEEVE KIT 1540-531-12. | | | | | | 2) SUBMIT A SIGNED AND SEALED FINAL SURVEY. NOTE: THE | | | BOOK AND PAGE NUMBER IN SECTION A3 OF THE ELEVATION | | | CERTIFICATE DID NOT MATCH THE ONE ON THE PREVIOUS | | | SURVEY DRAWINGS THAT WERE SUBMITTED. OUR RECORDS SHOW | | | THAT THE PLATS ARE RECORDED IN BOOK 130, PAGE 178. | | | PLEASE CORRECT. FBC 107.2.1 | | | | | | 3) THE BUILDING DIAGRAM NUMBER IN SECTION A7 OF THE | | | ELEVATION CERTIFICATE SHOULD BE 1A FOR THE GARAGES. | | | THEY ARE NOT RAISED SLAB ON GRADE PER NFIP ELEVATION | | | CERTIFICATE INSTRUCTIONS PAGE 7 OF 9. | | | | | | 4) THE INFORMATION THAT IS ENTERED IN SECTION A9 OF THE | | | ELEVATION CERTIFICATE SHOULD BE ENTERED IN SECTION A8. | | | THIS IS A DETACHED GARAGE AND SECTION A9 IS FOR GARAGES | | | THAT ARE ATTACHED TO ANOTHER BUILDING. IN SECTION A4 IT | | | SHOULD BE NOTED THAT THIS IS A DETACHED GARAGE. | | | | | | 5) VERIFY THAT THE SQUARE FOOTAGE OF THE GARAGE IS THE | | | MEASUREMENTS TO THE OUTSIDE WALLS AND THAT THEY | | | CORRESPOND TO THE SURVEY. NFIP ELEVATION CERTIFICATE | | | INSTRUCTIONS ITEM A8.A. | | | | | | 6) THE TOP OF BOTTOM FLOOR ENTERED IN SECTION C2. A) IS | | | 15.02 FEET. MAKE SURE THAT THE ELEVATION ON THE FINAL | | | SURVEY MATCHES THE ELEVATION CERTIFICATE. PLEASE VERIFY | | | AND MAKE NECESSARY CORRECTIONS. FBC 107.2.1 | | | | | | 7) SUBMIT PHOTOGRAPHS OF THE EXTERIOR SIDES OF THE | | | GARAGE THAT SHOWS THE FLOOD VENTS. FBC 107.2.1 |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2022-10-13 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:48 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-09-21 |
Time |
06:25 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2022-09-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-09-19 |
Time |
15:03 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-08-23 |
Time |
06:50 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2022-08-18 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:16 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-08-15 |
Time |
14:27 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2022-07-28 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-07-28 |
Time |
14:12 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-07-12 |
Time |
05:28 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
4 |
Status |
P |
Date |
2022-10-13 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:48 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:48 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
3 |
Status |
F |
Date |
2022-09-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-09-19 |
Time |
15:03 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-09-16 |
Time |
15:22 |
Sent To |
|
|
| Notes |
| 2022-09-16 15:21:44 | PLAN REVIEW COMMENTS | | | 3RD REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) SUBMIT THE COMPLETE PRODUCT APPROVALS AND/OR | | | EVALUATION REPORTS FOR THE FLOOD VENT MODEL 1540-530 | | | AND TRIM AND SLEEVE KIT 1540-531-12. FBC 107.2.1 | | | | | | 2) THE ALL PHASES S & S PDF IS NOT DIGITALLY SIGNED. | | | FBC 107.2.1 | | | | | | 3) THE INFORMATION THAT IS ENTERED IN THE COMMENT AREA | | | OF SECTION D SPECIFIES ITEM A9 WHICH SHOULD BE CHANGED | | | TO ITEM A8. ALL OF THE INFORMATION WAS MOVED FROM A9 TO | | | A8. | | | | | | 4) [THE SQUARE FOOT AREA OF GARAGE 3 IS 2083 SQFT. | | | BASED ON THE SURVEY. PLEASE REVISE ITEM A8 A). ] VERIFY | | | THAT THE SQUARE FOOTAGE OF THE GARAGE IS THE | | | MEASUREMENTS TO THE OUTSIDE WALLS AND THAT THEY | | | CORRESPOND TO THE SURVEY. NFIP ELEVATION CERTIFICATE | | | INSTRUCTIONS ITEM A8.A. FBC 107.2.1 | | | | | | 5) IN THE CAPTIONS FOR PHOTOS 7 AND 8, SPECIFTY THE | | | RIGHT OR LEFT SIDE OF THE BUILDING FOR THE LOCATION OF | | | THE FLOOD VENTS. FBC 107.2.1 | | | | | | 6) SUBMIT PHOTOGRAPHS OF THE EXTERIOR SIDES OF THE | | | GARAGE THAT SHOWS THE FLOOD VENTS. FBC 107.2.1 | | | | | | 7) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH | | | OF THE REVIEW COMMENTS HAS BEEN ADDRESSED |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
2 |
Status |
F |
Date |
2022-08-18 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:15 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:15 |
Sent To |
|
|
| Notes |
| 2022-08-18 16:16:35 | SEE BUILDING COMMENTS. |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
1 |
Status |
F |
Date |
2022-07-28 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-07-28 |
Time |
14:10 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-07-28 |
Time |
10:08 |
Sent To |
|
|
| Notes |
| 2022-07-28 10:10:26 | SEE BUILDING REVIEW. NOT RESULTED PENDING PEER REVIEW. | | | PEER REVIEW BY ROGER MCPHERSON FOUND NO OTHER ISSUES. |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
4 |
Status |
P |
Date |
2022-10-13 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:49 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-10-13 |
Time |
17:49 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
3 |
Status |
F |
Date |
2022-09-16 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-09-16 |
Time |
15:22 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-09-16 |
Time |
15:22 |
Sent To |
|
|
| Notes |
| 2022-09-16 15:23:22 | A DIGITALLY SIGNED FINAL SURVEY IS REQUIRED. |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2022-08-18 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:16 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-08-18 |
Time |
16:16 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2022-07-28 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-07-28 |
Time |
09:15 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-07-28 |
Time |
09:15 |
Sent To |
|
|
| Notes |
|
|