Plan Review Details - Permit 22051141
Plan Review Stops For Permit 22051141
Review Stop AD ADDRESSING
Rev No 1 Status P Date 2022-06-10 Cont ID  
Sent By cpuell Date 2022-06-10 Time 08:28 Rev Time 0.00
Received By cpuell Date 2022-06-10 Time 08:28 Sent To  
Notes
2022-06-10 08:29:02ADDRESS APPROPRIATE FOR PROJECT.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2023-04-19 Cont ID  
Sent By mpeterso Date 2023-04-19 Time 10:47 Rev Time 0.00
Received By mpeterso Date 2023-04-19 Time 10:47 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-07-01 Cont ID  
Sent By mpeterso Date 2022-07-01 Time 14:36 Rev Time 0.00
Received By mpeterso Date 2022-07-01 Time 14:32 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 1 Status N Date 2022-07-27 Cont ID  
Sent By eschneid Date 2022-07-27 Time 12:10 Rev Time 0.00
Received By eschneid Date 2022-07-27 Time 12:10 Sent To  
Notes
2022-07-27 12:11:44ENGINEERING REVIEW DONE UNDER PERMIT 21120571 WCF ROW.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2023-04-19 Cont ID  
Sent By mpeterso Date 2023-04-19 Time 10:52 Rev Time 0.00
Received By mpeterso Date 2023-04-13 Time 17:51 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-07-28 Cont ID  
Sent By aoliver Date 2022-07-28 Time 08:54 Rev Time 0.00
Received By aoliver Date 2022-06-10 Time 05:23 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2023-04-19 Cont ID  
Sent By mpeterso Date 2023-04-19 Time 10:52 Rev Time 0.00
Received By mpeterso Date 2023-04-19 Time 10:52 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-07-01 Cont ID  
Sent By mpeterso Date 2022-07-01 Time 14:36 Rev Time 0.00
Received By mpeterso Date 2022-07-01 Time 14:36 Sent To  
Notes
2022-07-01 14:36:51ALL PLANS PASSED SIGNATURE. MP

Review Stop Z ZONING
Rev No 2 Status P Date 2023-04-14 Cont ID  
Sent By eschneid Date 2023-04-14 Time 15:26 Rev Time 0.25
Received By eschneid Date 2023-04-14 Time 15:26 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2022-07-27 Cont ID  
Sent By eschneid Date 2022-07-27 Time 14:02 Rev Time 0.25
Received By eschneid Date 2022-07-27 Time 12:07 Sent To  
Notes
2022-07-27 14:02:52FAILED
  
 1) THE SUBMITTED COMMUNICATION FACILITY PLACEMENT
 PERMIT - CITY RIGHTS-OF-WAY (21120571) MUST BE APPROVED
 PRIOR TO THIS PERMIT BEING APPROVED. THIS SUBMITTED
 PERMIT CONTAINS THE SAME PLANS AS THE WCF ROW PERMIT.
 THE COMMENTS BELOW WERE ALSO PROVIDED ON THE WCF ROW
 PERMIT. PLEASE ENSURE THAT FUTURE SUBMITTALS FOR BOTH
 PERMITS CONTAIN THE SAME INFORMATION.
  
 2) THE BORE PIT AND HANDHOLE NOTES ON SHEET P-1 STATE
 THAT THE SIDEWALK WILL BE RESTORED; HOWEVER, THESE ARE
 ALSO LOCATED WITHIN THE PARKWAY WHICH WILL NEED
 RESTORATION. PLEASE UPDATE THE NOTATIONS ACCORDINGLY.
  
 3) PROVIDE A CROSS SECTION OF THE UNDERGROUND ELECTRIC
 WHICH VERIFIES THAT THERE ARE NO CONFLICTS WITH
 EXISTING UTILITIES AND TREE ROOTS.
  
 4) THE PLANS SHOW THE BORE PITS, HANDHOLE AND THE POLE
 INSTALL IN DIRECT OVERLAP OF ELECTRIC LINES AND WITHIN
 2 FEET OF A GAS LINE. IN ORDER TO VERIFY THAT THE
 INSTALLATION WILL NOT INTERFERE WITH THE EXISTING
 FACILITIES, PROVIDE A PUBLIC UTILITY LETTER OF NO
 OBJECTION FROM FPL AND FPU REGARDING THE INSTALLATION.
  
 5) THE EXCAVATION FOR THE HANDHOLE AT THE POWER POLE IS
 SHOWN CROSSING ONTO PRIVATE PROPERTY, WHICH IS NOT
 PERMITTED UNLESS THE SURVEY CLEARLY SHOWS A UTILITY
 EASEMENT AT THIS LOCATION.
  
 6) THE POLE STYLE AND HEIGHT MEET CITY REQUIREMENTS.
 THE POLE COLOR AT THIS LOCATION SHALL BE RAL/RAYCAP
 7042 TRAFFIC GREY A.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446
 [email protected]
  