Plan Review Details - Permit 22041213
Plan Review Stops For Permit 22041213
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2022-08-08 Cont ID  
Sent By shill Date 2022-08-08 Time 07:04 Rev Time 0.00
Received By shill Date 2022-08-08 Time 07:04 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2022-07-13 Cont ID  
Sent By jbrooks Date 2022-07-13 Time 11:58 Rev Time 0.00
Received By jbrooks Date 2022-07-13 Time 11:58 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2022-06-01 Cont ID  
Sent By jbrooks Date 2022-06-01 Time 10:23 Rev Time 0.00
Received By jbrooks Date 2022-06-01 Time 10:23 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-08-08 Cont ID  
Sent By shill Date 2022-08-08 Time 07:05 Rev Time 0.00
Received By shill Date 2022-07-14 Time 07:46 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-07-13 Cont ID  
Sent By jbrooks Date 2022-07-13 Time 11:58 Rev Time 0.00
Received By jbrooks Date 2022-06-03 Time 08:28 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-06-01 Cont ID  
Sent By jbrooks Date 2022-06-01 Time 10:23 Rev Time 0.00
Received By jbrooks Date 2022-05-09 Time 06:24 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status N Date 2022-08-08 Cont ID  
Sent By shill Date 2022-08-08 Time 07:05 Rev Time 0.00
Received By shill Date 2022-08-08 Time 07:05 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-06-01 Cont ID  
Sent By jbrooks Date 2022-06-01 Time 10:23 Rev Time 0.00
Received By jbrooks Date 2022-06-01 Time 10:23 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 3 Status P Date 2022-07-14 Cont ID  
Sent By kdefranc Date 2022-07-14 Time 12:30 Rev Time 0.00
Received By kdefranc Date 2022-07-14 Time 12:28 Sent To  
Notes
2022-07-14 12:30:237/14/22 ? PASSED
  
 PREVIOUS REVIEW COMMENT TO BE ADDRESSED:
 1. PLEASE PROVIDE AN ILLUSTRATION (PREFERABLY
 ARCHITECTURAL EXTERIOR ELEVATION(S)/DRAWING(S)) OF THE
 BUILDING FA?ADE(S) BEING IMPACTED BY THE PROPOSED WORK
 IDENTIFYING/INDICATING/DEMONSTRATING THE STOREFRONT
 WINDOW(S) AND DOOR(S) BEING REPLACED AND THE
 DIMENSIONAL DETAILS. [SATISFIED]
  
 ADDITIONAL REVIEW COMMENT TO BE ADDRESSED:
 1. THE ILLUSTRATION NEEDS TO
 IDENTIFY/INDICATE/DEMONSTRATE THE EXISTING BUILDING
 FA?ADE WITH THE BUILDING HEIGHT AND WIDTH (DIMENSIONAL
 UNITS ? FEET OR INCHES) ALONG WITH THE PROPOSED
 STOREFRONT OPENING WITH THE WINDOWS/DOOR HEIGHT AND
 WIDTH (DIMENSIONAL UNITS ? FEET OR INCHES). [SATISFIED]
  
  
 KEVIE DEFRANC
 PLANNER - PLANNING DIVISION
 [email protected]
 561-822-1449
  

Review Stop Z ZONING
Rev No 2 Status F Date 2022-06-17 Cont ID  
Sent By kdefranc Date 2022-06-17 Time 11:04 Rev Time 0.00
Received By kdefranc Date 2022-06-17 Time 11:02 Sent To  
Notes
2022-06-17 11:03:306/17/22 ? FAILED
  
 PREVIOUS REVIEW COMMENT TO BE ADDRESSED:
 1. PLEASE PROVIDE AN ILLUSTRATION (PREFERABLY
 ARCHITECTURAL EXTERIOR ELEVATION(S)/DRAWING(S)) OF THE
 BUILDING FA?ADE(S) BEING IMPACTED BY THE PROPOSED WORK
 IDENTIFYING/INDICATING/DEMONSTRATING THE STOREFRONT
 WINDOW(S) AND DOOR(S) BEING REPLACED AND THE
 DIMENSIONAL DETAILS. [PARTIALLY SATISFIED]
  
 ADDITIONAL REVIEW COMMENT TO BE ADDRESSED:
 1. THE ILLUSTRATION NEEDS TO
 IDENTIFY/INDICATE/DEMONSTRATE THE EXISTING BUILDING
 FA?ADE WITH THE BUILDING HEIGHT AND WIDTH (DIMENSIONAL
 UNITS ? FEET OR INCHES) ALONG WITH THE PROPOSED
 STOREFRONT OPENING WITH THE WINDOWS/DOOR HEIGHT AND
 WIDTH (DIMENSIONAL UNITS ? FEET OR INCHES).
  
  
 KEVIE DEFRANC
 PLANNER - PLANNING DIVISION
 [email protected]
 561-822-1449
  

Review Stop Z ZONING
Rev No 1 Status F Date 2022-05-17 Cont ID  
Sent By kdefranc Date 2022-05-17 Time 12:13 Rev Time 0.00
Received By kdefranc Date 2022-05-17 Time 12:12 Sent To  
Notes
2022-05-17 12:13:265/17/22 ? FAILED
  
 REVIEW COMMENT TO BE ADDRESSED:
 1. PLEASE PROVIDE AN ILLUSTRATION (PREFERABLY
 ARCHITECTURAL EXTERIOR ELEVATION(S)/DRAWING(S)) OF THE
 BUILDING FA?ADE(S) BEING IMPACTED BY THE PROPOSED WORK
 IDENTIFYING/INDICATING/DEMONSTRATING THE STOREFRONT
 WINDOW(S) AND DOOR(S) BEING REPLACED AND THE
 DIMENSIONAL DETAILS.
  
  
 KEVIE DEFRANC
 PLANNER - PLANNING DIVISION
 [email protected]
 561-822-1449
  