Plan Review Details - Permit 22041068
Plan Review Stops For Permit 22041068
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2022-05-16 Cont ID  
Sent By rmcdouga Date 2022-05-16 Time 14:32 Rev Time 0.00
Received By rmcdouga Date 2022-05-16 Time 14:32 Sent To  
Notes
2022-05-16 14:35:33FBC-R4501.19 FINAL INSPECTION. FINAL ELECTRICAL AND
 BARRIER CODE INSPECTION SHALL BE COMPLETED PRIOR TO
 FILLING THE POOL WITH WATER.
  
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-05-05 Cont ID  
Sent By ppetty Date 2022-05-05 Time 09:07 Rev Time 0.00
Received By ppetty Date 2022-05-05 Time 08:45 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2022-04-27 Cont ID  
Sent By lcrespo Date 2022-04-27 Time 10:45 Rev Time 0.00
Received By lcrespo Date 2022-04-27 Time 10:45 Sent To  
Notes
2022-04-27 10:46:54GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE, AND A GAS PLAN REVIEW HAS NOT
 BEEN PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND
 PLANS WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR
 FOR THE SCOPE OF WORK PER THE WPB AMENDMENT TO THE FBC
 SEC. 105.1.
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-06-01 Cont ID  
Sent By rwbrown Date 2022-06-01 Time 09:25 Rev Time 0.00
Received By rwbrown Date 2022-05-25 Time 12:19 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-05-16 Cont ID  
Sent By rmcdouga Date 2022-05-16 Time 14:35 Rev Time 0.00
Received By rmcdouga Date 2022-04-21 Time 08:56 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2022-06-01 Cont ID  
Sent By rwbrown Date 2022-06-01 Time 09:25 Rev Time 0.00
Received By rwbrown Date 2022-06-01 Time 09:15 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2022-04-27 Cont ID  
Sent By lcrespo Date 2022-04-27 Time 10:46 Rev Time 0.00
Received By lcrespo Date 2022-04-27 Time 10:46 Sent To  
Notes
2022-04-27 10:55:0404/27/22 1ST POOL PLUMBING REVIEW**DENIED** WITH
 COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. ON THE PREVIOUS VERSION, THE WAS NO GAS HEATER, AND
 NOW ONE IS PRESENT; THIS WILL REQUIRE THE TOTAL DYNAMIC
 HEAD TO BE RECALCULATED AND A GAS PERMIT FOR THAT AS A
 SEPARATE PERMIT ON A LATER DATE.
  
 2. WOULD YOU PLEASE SUBMIT TOTAL DYNAMIC HEAD
 CALCULATIONS FOR THE MAXIMUM SYSTEM FLOW? THE PUMP'S
 MAXIMUM FLOW FROM ITS PUMP CURVE IS NO LONGER ALLOWED
 TO BE USED IN DETERMINING THE MAXIMUM SYSTEM FLOW RATE
 PER ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE
 2013 EDITION ADDRESSES THE FLOW RATE IN GALLONS PER
 MINUTE (GPM). IT REQUIRES THAT THE MAXIMUM SYSTEM FLOW
 RATE DOES NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF
 THE SUCTION OUTLET FITTING ASSEMBLY (DRAIN COVER). THE
 TDH CALCULATIONS MUST INCLUDE ALL THE SYSTEM
 COMPONENTS, INCLUDING SUCTION AND RETURN PIPING,
 FITTINGS, VALVES, GAS HEATER, AND FILTER. ALL SYSTEM
 COMPONENTS EXCEPT THE PUMP.
  
 3. WOULD YOU PLEASE SUBMIT THE POOL PUMP CURVE AND
 IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS SPECIFIC
 TO THE PUMP BEING INSTALLED ON THIS POOL. THIS IS
 NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE TDH
 CALCULATIONS PER THE ANSI/APSP/ICC 7 - 2015 SECS.
 4.4.9, 4.4.9.1.
  
 4. WOULD YOU PLEASE PROVIDE THE SPECIFICATION FOR THE
 GAS HEATER PER THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES.
 A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGES CAN BE FOUND, WILL HELP EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 WEST PALM BEACH AMENDMENTS 2017 FBC CHAPTER; UPON
 REQUEST.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-05-16 Cont ID  
Sent By rmcdouga Date 2022-05-16 Time 14:28 Rev Time 0.00
Received By rmcdouga Date 2022-05-16 Time 14:28 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2022-04-27 Cont ID  
Sent By asangele Date 2022-04-27 Time 14:56 Rev Time 0.00
Received By asangele Date 2022-04-27 Time 14:56 Sent To  
Notes
***NONE***