Plan Review Details - Permit 22020552
Plan Review Stops For Permit 22020552
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2022-10-14 Cont ID  
Sent By rmcdouga Date 2022-10-14 Time 09:33 Rev Time 0.00
Received By rmcdouga Date 2022-10-14 Time 08:50 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2022-05-04 Cont ID  
Sent By rmcdouga Date 2022-05-04 Time 15:56 Rev Time 0.00
Received By rmcdouga Date 2022-05-04 Time 15:56 Sent To  
Notes
2022-05-04 15:01:01PLAN
 REVIEW COMMENTS
  
 2ND REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) RESOLVED. CIRCLE OR HI-LITE THE MODEL AND THE WIND
 PRESSURES OF THE 22" TCC SKYLIGHT LISTED IN THE PRODUCT
 APPROVAL THAT WILL BE INSTALLED. FBC AMENDMENTS 107.2.1
  
 2) NOT RESOLVED [ THE WIND SPEED IS 170 MPH VULT. NOT
 -54. ] SPECIFY THE WIND DATA (WINDSPEED, EXPOSURE
 CATEGORY, MEAN ROOF HEIGHT) ON THE DRAWING.
 FBC-R301.2.1
  
 3) NOT RESOLVED. [ THE -54.0 THAT IS CIRCLED IN THE
 SIMPLIFIED UPLIFT CHART IS COMPONENT AND CLADDING
 PRESSURE FOR A HIP ROOF WITH A SLOPE BETWEEN 4:12 AND
 6:12 FOR ROOF ZONE 1. THE ISSUES THAT I HAVE ARE THAT
 THE EXPOSURE CATEGORY C IS NOT SPECIFIED FOR THIS TABLE
 AND THE PRODUCT APPROVAL HAS A DESIGN PRESSURE OF +/-
 50 PSF FOR THE IMPACT RATED SKYLIGHT WHICH IS LESS THAN
 -54 PSF.] SPECIFY THE TYPE OF ROOF (GABLE OR HIP), THE
 ROOFING MATERIAL, THE ROOF SLOPE AND THE ROOF COMPONENT
 AND CLADDING PRESSURE ZONE FOR THE SKYLIGHT
 INSTALLATION. THE DESIGN PRESSURES FOR THE SKYLIGHT
 ASSEMBLY HAVE TO BE GREATER THAN THE REQUIRED
 PRESSURES. FBC-R301
  
 4) RESOLVED.PROVIDE A CLEAR AND DETAILED ROOF DIAGRAM
 THAT SHOWS THE PROPOSED LOCATION OF THE SKYLIGHT. THE
 ONE THAT WAS SUBMITTED IS NOT CLEAR OR DETAILED ENOUGH.
 FBC 107.2.1
  
 5) NOT RESOLVED. [ IT IS NOT CLEAR HOW THE CURB WILL BE
 ATTACHED TO THE ROOF. IS IT JUST SCREWED TO THE PLYWOOD
 SHEATHING OR WILL IT ATTACH TO FRAMING UNDER THE
 SHEATHING? BASED ON THE INSTALLATION INSTRUCTIONS
 FRAMING IS REQUIRED. SPECIFY THE NUMBER AND LOCATIONS
 OF THE SCREWS THAT WILL ATTACH THE CURB TO THE ROOF?
 WHAT MATERIAL WILL BE USED TO BUILD THE CURB? PROVIDE A
 DETAILED DRAWING SIGNED AND SEALED BY A FLORIDA
 LICENSED ARCHITECT OR ENGINEER. THE NEXT TWO SENTANCES
 ARE FROM THE INSTALLATION INSTRUCTIONS: BUILD CURB
 ACCORDING TO MEASUREMENTS IN THE CHART. CURB HEIGHT AND
 ATTACHMENT SHOULD COMPLY WITH BUILDING CODES AND
 REGULATIONS AND BE SECURE ENOUGH TO TRANSFER THE SUN
 TUNNEL LOADS TO THE FRAMING MEMBERS.] IF YOU ARE USING
 A CURB TO RAISE THE SKYLIGHT ABOVE A CONCRETE TILE
 ROOF, PROVIDE A DETAIL FOR HOW THE CURB FRAMING WILL BE
 SUPPORTED AND ANCHORED TO THE ROOF. FBC-R301
  
 6) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH
 OF THE REVIEW COMMENTS HAS BEEN ADDRESSED.
  
  
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2022-03-25 Cont ID  
Sent By rmcdouga Date 2022-03-25 Time 09:04 Rev Time 0.00
Received By rmcdouga Date 2022-03-25 Time 09:04 Sent To  
Notes
2022-03-25 09:58:07PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) CIRCLE OR HI-LITE THE MODEL AND THE WIND PRESSURES
 OF THE 22" TCC SKYLIGHT LISTED IN THE PRODUCT APPROVAL
 THAT WILL BE INSTALLED. FBC AMENDMENTS 107.2.1
  
 2) SPECIFY THE WIND DATA (WINDSPEED, EXPOSURE CATEGORY,
 MEAN ROOF HEIGHT) ON THE DRAWING. FBC-R301.2.1
  
 3) SPECIFY THE TYPE OF ROOF (GABLE OR HIP), THE ROOFING
 MATERIAL, THE ROOF SLOPE AND THE ROOF COMPONENT AND
 CLADDING PRESSURE ZONE FOR THE SKYLIGHT INSTALLATION.
 THE DESIGN PRESSURES FOR THE SKYLIGHT ASSEMBLY HAVE TO
 BE GREATER THAN THE REQUIRED PRESSURES. FBC-R301
  
 4) PROVIDE A CLEAR AND DETAILED ROOF DIAGRAM THAT SHOWS
 THE PROPOSED LOCATION OF THE SKYLIGHT. THE ONE THAT WAS
 SUBMITTED IS NOT CLEAR OR DETAILED ENOUGH. FBC 107.2.1
  
 5) IF YOU ARE USING A CURB TO RAISE THE SKYLIGHT ABOVE
 A CONCRETE TILE ROOF, PROVIDE A DETAIL FOR HOW THE CURB
 FRAMING WILL BE SUPPORTED AND ANCHORED TO THE ROOF.
 FBC-R301
  
 6) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH
 OF THE REVIEW COMMENTS HAS BEEN ADDRESSED.
  
  
  
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-10-14 Cont ID  
Sent By rmcdouga Date 2022-10-14 Time 09:34 Rev Time 0.00
Received By rmcdouga Date 2022-09-22 Time 08:18 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-05-04 Cont ID  
Sent By rmcdouga Date 2022-05-04 Time 15:56 Rev Time 0.00
Received By rmcdouga Date 2022-04-20 Time 16:15 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-03-25 Cont ID  
Sent By rmcdouga Date 2022-03-25 Time 09:58 Rev Time 0.00
Received By rmcdouga Date 2022-02-09 Time 11:49 Sent To  
Notes
***NONE***