Plan Review Details - Permit 22020145
Plan Review Stops For Permit 22020145
Review Stop B BUILDING (STRUCTURAL)
Rev No 5 Status P Date 2023-07-12 Cont ID  
Sent By rmcdouga Date 2023-07-12 Time 16:25 Rev Time 0.00
Received By rmcdouga Date 2023-07-12 Time 16:25 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2023-06-28 Cont ID  
Sent By rmcdouga Date 2023-06-28 Time 08:32 Rev Time 0.00
Received By rmcdouga Date 2023-06-28 Time 08:32 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2022-05-03 Cont ID  
Sent By rmcdouga Date 2022-05-03 Time 10:24 Rev Time 0.00
Received By rmcdouga Date 2022-05-03 Time 10:24 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2022-03-29 Cont ID  
Sent By rmcdouga Date 2022-03-29 Time 11:20 Rev Time 0.00
Received By rmcdouga Date 2022-03-29 Time 11:16 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2022-03-14 Cont ID  
Sent By rmcdouga Date 2022-03-14 Time 14:08 Rev Time 0.00
Received By rmcdouga Date 2022-03-14 Time 14:08 Sent To  
Notes
2022-02-24 09:44:17 
  

Review Stop I INCOMING/PROCESSING
Rev No 7 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By amcgrego Date 2023-06-29 Time 08:53 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2023-06-28 Cont ID  
Sent By rmcdouga Date 2023-06-28 Time 08:35 Rev Time 0.00
Received By rmcdouga Date 2023-06-06 Time 12:19 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2023-06-06 Cont ID  
Sent By lmarchan Date 2023-06-06 Time 07:41 Rev Time 0.00
Received By lmarchan Date 2023-05-25 Time 08:29 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2023-05-22 Cont ID  
Sent By asangele Date 2023-05-22 Time 11:12 Rev Time 0.00
Received By asangele Date 2023-05-22 Time 11:12 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-05-03 Cont ID  
Sent By rmcdouga Date 2022-05-03 Time 10:25 Rev Time 0.00
Received By rmcdouga Date 2022-04-06 Time 14:48 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-04-04 Cont ID  
Sent By asangele Date 2022-04-04 Time 16:27 Rev Time 0.00
Received By asangele Date 2022-04-04 Time 16:27 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-03-14 Cont ID  
Sent By rmcdouga Date 2022-03-14 Time 14:12 Rev Time 0.00
Received By rmcdouga Date 2022-02-04 Time 09:51 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status P Date 2023-07-12 Cont ID  
Sent By rmcdouga Date 2023-07-12 Time 16:22 Rev Time 0.00
Received By rmcdouga Date 2023-07-12 Time 16:22 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2022-04-07 Cont ID  
Sent By lcrespo Date 2022-04-07 Time 10:46 Rev Time 0.00
Received By lcrespo Date 2022-04-07 Time 10:46 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-03-29 Cont ID  
Sent By rmcdouga Date 2022-03-29 Time 11:21 Rev Time 0.00
Received By rmcdouga Date 2022-03-29 Time 11:16 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2022-03-14 Cont ID  
Sent By rmcdouga Date 2022-03-14 Time 14:08 Rev Time 0.00
Received By rmcdouga Date 2022-03-14 Time 14:08 Sent To  
Notes
2022-03-14 14:11:46THE ENGINEER'S DIGITAL SIGNATURES ON THE THREE DRAWINGS
 AND THE FINAL INSPECTION LETTER COULD NOT BE VERIFIED.
 ELECTRONICALLY SUBMITTED DRAWINGS ARE REQUIRED TO HAVE
 THE ARCHITECT OR ENGINEER'S DIGITAL SIGNATURE ON THEM.
 YOU ALSO HAVE THE OPTION TO SUBMIT THE SIGNED AND
 SEALED PAPER VERSION OF DRAWINGS. AFTER THE ELECTRONIC
 PLANS HAVE BEEN APPROVED, YOU CAN SUBMIT THE
 CORRESPONDING PAPER DRAWINGS AT THE BUILDING DEPARTMENT
 TO BE VERIFIED. THE ARCHITECT OR ENGINEER'S ORIGINAL
 HANDWRITTEN SIGNATURE AND SEAL IS REQUIRED TO BE ON THE
 DRAWINGS. NO PHOTOCOPY OR OTHER FACSIMILES OF THE
 SIGNATURE ARE ACCEPTABLE. FS 481 & FAC 61G1 OR FS 471 &
 FAC 61G15

Review Stop Z ZONING
Rev No 7 Status   Date   Cont ID  
Sent By ecolon Date   Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 6 Status F Date 2023-06-12 Cont ID  
Sent By kdefranc Date 2023-06-12 Time 11:40 Rev Time 0.00
Received By kdefranc Date 2023-06-12 Time 11:38 Sent To  
Notes
2023-06-12 11:40:346/12/23 ??? FAILED
  
 REVIEW COMMENT TO BE ADDRESSED:
 1. PROVIDE THE LATEST PLANS, AS INDICATED IN SECTION 8
 OF RESOLUTION NO. 84-23 (CLASS A SPECIAL USE PERMIT),
 UPDATED ACCORDINGLY WITH THE LOCATION OF
 WATER-RESISTANT REFLECTIVE NUMERALS CORRESPONDING TO
 THE STREET ADDRESS OF THE UPLAND PROPERTY (222)
 IDENTIFIED/INDICATED/DEMONSTRATED. [PARTIALLY
 SATISFIED]
  
  
 KEVIE DEFRANC
 SENIOR PLANNER - PLANNING DIVISION
 [email protected]
 561-822-1449
  

Review Stop Z ZONING
Rev No 5 Status F Date 2023-06-05 Cont ID  
Sent By kdefranc Date 2023-06-05 Time 16:53 Rev Time 0.00
Received By kdefranc Date 2023-06-05 Time 16:47 Sent To  
Notes
2023-06-05 16:53:466/5/23 ??? FAILED
  
 REVIEW COMMENT TO BE ADDRESSED:
 1. PROVIDE THE LATEST PLANS, AS INDICATED IN SECTION 8
 OF RESOLUTION NO. 84-23 (CLASS A SPECIAL USE PERMIT),
 UPDATED ACCORDINGLY WITH THE LOCATION OF
 WATER-RESISTANT REFLECTIVE NUMERALS CORRESPONDING TO
 THE STREET ADDRESS OF THE UPLAND PROPERTY (222)
 IDENTIFIED/INDICATED/DEMONSTRATED.
  
  
 KEVIE DEFRANC
 SENIOR PLANNER - PLANNING DIVISION
 [email protected]
 561-822-1449
  

Review Stop Z ZONING
Rev No 4 Status F Date 2023-05-22 Cont ID  
Sent By asangele Date 2023-05-22 Time 11:12 Rev Time 0.00
Received By asangele Date 2023-05-22 Time 11:12 Sent To  
Notes
2023-05-22 11:29:26FAILED
 5/22/2023
  
  
 PROPSED TURBIDITY CURTAIN CANNOT BE LOCATED OUTSIDE THE
 MIDDLE ONE THIRD
  
 ARTICLE X. SECTION 94-313
  
 LOCATION AND SETBACKS. DOCKS, "TEES," DOLPHINS,
 PILINGS, BOATLIFTS, AND OTHER MOORING-RELATED
 FACILITIES SHALL BE CONSTRUCTED WITHIN THE MIDDLE
 ONE-THIRD OF THE LOT ON WHICH A DOCK IS CONSTRUCTED, AS
 EXTENDED INTO THE WATERWAY. NO WATERCRAFT SHALL BE
 DOCKED OR ANCHORED IN A POSITION, OR BE OF SUCH LENGTH,
 THAT CAUSES IT TO EXTEND BEYOND THE SIDE SETBACK LINES
 REQUIRED FOR PRINCIPAL STRUCTURES ON SUCH PROPERTY, AS
 EXTENDED INTO THE WATERWAY.
  
  
  
 ALEXIS SANGELEER
 PLANNER
 [email protected]

Review Stop Z ZONING
Rev No 3 Status F Date 2022-04-13 Cont ID  
Sent By asangele Date 2022-04-13 Time 14:52 Rev Time 0.00
Received By asangele Date 2022-04-13 Time 14:52 Sent To  
Notes
2022-04-13 15:00:084/13/2022
 FAIL
 THE BOATLIFT ITSELF IS FINE SINCE IT ALREADY GOT
 APPROVED BY A PREVIOUS PERMIT HOWEVER THE FINGER PIER
 WAS BUILT WITHOUT A PERMIT. YOU DO HAVE THE OPTION OF
 APPLYING FOR A CLASS A SPECIAL USE PERMIT.
  
  
  
 ALEXIS SANGELEER
 ASSOCIATE PLANNER
 [email protected]

Review Stop Z ZONING
Rev No 2 Status F Date 2022-04-04 Cont ID  
Sent By asangele Date 2022-04-04 Time 16:25 Rev Time 0.00
Received By asangele Date 2022-04-04 Time 16:25 Sent To  
Notes
2022-04-04 16:26:464/4/2022
 FAILED
 PLEASE ADDRESS PREVIOUS ZONING COMMENTS.
  
 ALEXIS SANGELEER
 ASSOCIATE PLANNER
 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status F Date   Cont ID  
Sent By asangele Date 2022-02-24 Time   Rev Time  
Received By   Date 2022-02-24 Time   Sent To  
Notes
2022-02-24 09:46:532/24/2022
 FAILED
 PLEASE PROVIDE A SURVEY WITH THE LOT SPLIT INTO ONE
 THIRDS
 MORE INFORMATION NEEDS TO BE PROVIDED ONE THE EXISTING
 DOCK
 BOAT LIFT HAS TO BE LOCATED IN THE MIDDLE ONE THIRD OF
 THE PROPERTY AS STATED IN SECTION 94-313 OF THE CITY OF
 WEST PALM BEACH ZONING AND LAND DEVELOPMENT
 REGULATIONS.
  
 ALEXIS SANGELEER
 ASSOCIATE PLANNER
 [email protected]
  