Plan Review Details - Permit 22020131
Plan Review Stops For Permit 22020131
Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2022-08-29 Cont ID  
Sent By rrossano Date 2022-08-29 Time   Rev Time 0.00
Received By rrossano Date 2022-08-29 Time   Sent To I
Notes
2022-08-29 10:33:03PASSED WITH PROVISOS:
  
 DO NOT CONSTRUCT DRIVEWAY ON TOP OF WATER METERS,
 SANITARY CLEANOUTS, STORMWATER INLETS ETC.
  
 CONSTRUCT DRIVEWAY APRON IN COMPLIANCE WITH WPB
 CONSTRUCTION STANDARD DETAIL GC-5 (WHEN DISTANCE
 BETWEEN CURB OR EDGE OF PAVEMENT IS 10 FT. OR GREATER),
 OR STANDARD DETAIL GC-6 (WHEN DISTANCE BETWEEN CURB OR
 EDGE OF PAVEMENT IS LESS THAN 10 FT.) CITY STANDARD
 DETAIL IS REQUIRED, SEE LINK BELOW: HTTPS://WWW.WPB.ORG
 /GOVERNMENT/ENGINEERING/ENGINEERING-STANDARDS-DETAILS
  
 CALL 811 FOR UTILITY LOCATES 48 HRS. IN ADVANCE OF
 CONSTRUCTION.
  
 THANKS,
 RICK ROSSANO, SENIOR PROJECT COORDINATOR, CITY OF WPB
 ENGINEERING SERVICES DEPARTMENT
 (561) 494-1098, FAX: (561) 494-1116 EMAIL:
 [email protected]
 CENTRAL OPERATIONS CENTER (DISPATCH):
 24-HOUR EMERGENCY RESPONSE SERVICES TO PUBLIC
 UTILITIES, PUBLIC WORKS, PARKS, ETC. 561-822-2210
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-08-02 Cont ID  
Sent By rrossano Date 2022-08-02 Time   Rev Time  
Received By rrossano Date 2022-08-02 Time   Sent To  
Notes
2022-08-02 16:17:34INDICATE AREAS OF PROPOSED DRIVEWAY CONSTRUCTION ON A
 COPY OF THE PROPERTY SURVEY. SHOW ANY WATER METERS,
 SANITARY CLEANOUTS, STORM INLETS ETC. IN VICINITY OF
 PROPOSED DRIVEWAY. DO NOT CONSTRUCT DRIVEWAY ON TOP OF
 WATER METERS, SANITARY CLEANOUTS, STORMWATER INLETS
 ETC.
  
 SHOW PROPOSED DRIVEWAY APRON. CONSTRUCT DRIVEWAY APRON
 IN COMPLIANCE WITH WPB CONSTRUCTION STANDARD DETAIL
 GC-5 (WHEN DISTANCE BETWEEN CURB OR EDGE OF PAVEMENT IS
 10 FT. OR GREATER), OR STANDARD DETAIL GC-6 (WHEN
 DISTANCE BETWEEN CURB OR EDGE OF PAVEMENT IS LESS THAN
 10 FT.) CITY STANDARD DETAIL IS REQUIRED, SEE LINK
 BELOW: HTTPS://WWW.WPB.ORG
 /GOVERNMENT/ENGINEERING/ENGINEERING-STANDARDS-DETAILS
  
 THE PAVER DRIVEWAY AGREEMENT IS ONLY A REQUIREMENT IF
 PAVERS ARE USED IN THE RIGHT OF WAY PORTION OF THE
 DRIVEWAY. ARE PAVERS PROPOSED IN THE RIGHT OF WAY?
  
 THANKS,
 RICK ROSSANO, SENIOR PROJECT COORDINATOR,
 CITY OF WPB ENGINEERING SERVICES DEPARTMENT
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected]
 HTTPS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-
 STANDARDS-DETAILS
 CENTRAL OPERATIONS CENTER (DISPATCH):
 24-HOUR EMERGENCY RESPONSE SERVICES TO PUBLIC
 UTILITIES, PUBLIC WORKS, PARKS, ETC. 561-822-2210
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-08-30 Cont ID  
Sent By aoliver Date 2022-08-30 Time 09:41 Rev Time 0.00
Received By aoliver Date 2022-08-24 Time 17:07 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-08-12 Cont ID  
Sent By lmarchan Date 2022-08-12 Time 16:47 Rev Time 0.00
Received By lmarchan Date 2022-07-29 Time 14:04 Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 1 Status P Date 2022-08-12 Cont ID  
Sent By lmarchan Date 2022-08-12 Time 16:47 Rev Time 0.00
Received By lmarchan Date 2022-08-12 Time 16:47 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2022-08-26 Cont ID  
Sent By afowlkes Date 2022-08-26 Time 13:05 Rev Time 0.00
Received By afowlkes Date 2022-08-26 Time 13:05 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2022-08-04 Cont ID  
Sent By afowlkes Date 2022-08-04 Time 16:06 Rev Time 0.00
Received By afowlkes Date 2022-08-04 Time 16:06 Sent To  
Notes
***NONE***