Plan Review Details - Permit 22011000
Plan Review Stops For Permit 22011000
Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2022-03-14 Cont ID  
Sent By RROSSANO Date 2022-03-14 Time   Rev Time 0.00
Received By rrossano Date 2022-03-14 Time   Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-02-14 Cont ID  
Sent By rrossano Date 2022-02-14 Time   Rev Time  
Received By rrossano Date 2022-02-14 Time   Sent To  
Notes
2022-02-14 08:41:41UNDER FORMAL ENGINEERING PERMIT MODIFICATION REVIEW.
  
 RICK ROSSANO, SENIOR PROJECT COORDINATOR,
 CITY OF WPB ENGINEERING SERVICES DEPARTMENT
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected]
 HTTPS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-
 STANDARDS-DETAILS
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2022-03-14 Cont ID  
Sent By   Date 2022-03-14 Time   Rev Time 0.00
Received By bdolan Date 2022-03-14 Time 12:45 Sent To  
Notes
2022-03-14 12:48:531) INSTALL, TEST AND INSPECT PER NFPA? 24 STANDARD FOR
 THE INSTALLATION OF PRIVATE FIRE SERVICE MAINS AND
 THEIR APPURTENANCES, 2013 EDITION
  
 2) DO NOT COVER/BACKFILL OVER ANY JOINTS PRIOR TO
 INSPECTION.
  
 PER CITY CODES, ALL WORK IS SUBJECT TO FIELD
 INSPECTIONS AND APPROVAL.
  
 LT. BRIAN DOLAN
 DIVISION OF FIRE PREVENTION
 561-804-4752
 [email protected]
  
  
  
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2022-02-03 Cont ID  
Sent By   Date 2022-02-03 Time   Rev Time 0.00
Received By jcclark Date 2022-02-03 Time 09:23 Sent To  
Notes
2022-02-03 09:47:26ALL UNDERGROUND WATER SUPPLY LINES ARE REQUIRED TO BE
 TIGHTENED PER MANUFACTURER SPECIFICATIONS AND INSPECTED
 PRIOR TO BEING BURIED PER NFPA 13 10.8 PER CITY CODES,
 ALL WORK IS SUBJECT TO FIELD INSPECTIONS AND APPROVAL.
 JOSEPH CLARK
 OFFICE OF THE FIRE MARSHAL
 561-804-4748
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-03-15 Cont ID  
Sent By mpeterso Date 2022-03-15 Time 13:10 Rev Time 0.00
Received By mpeterso Date 2022-03-10 Time 09:43 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-02-15 Cont ID  
Sent By cthroop Date 2022-02-15 Time 11:28 Rev Time 0.00
Received By cthroop Date 2022-02-01 Time 10:37 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-03-15 Cont ID  
Sent By mpeterso Date 2022-03-15 Time 13:10 Rev Time 0.00
Received By mpeterso Date 2022-03-15 Time 13:10 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-02-15 Cont ID  
Sent By cthroop Date 2022-02-15 Time 11:28 Rev Time 0.00
Received By cthroop Date 2022-02-15 Time 10:53 Sent To  
Notes
***NONE***