Plan Review Details - Permit 22010759
Plan Review Stops For Permit 22010759
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2022-04-13 Cont ID  
Sent By rmcdouga Date 2022-04-13 Time 13:17 Rev Time 0.00
Received By rmcdouga Date 2022-04-13 Time 13:17 Sent To  
Notes
2022-04-13 13:09:51FBC-R4501.19 FINAL INSPECTION. FINAL ELECTRICAL AND
 BARRIER CODE INSPECTION SHALL BE COMPLETED PRIOR TO
 FILLING THE POOL WITH WATER.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2022-03-15 Cont ID  
Sent By rmcdouga Date 2022-03-15 Time 17:49 Rev Time 0.00
Received By rmcdouga Date 2022-03-15 Time 17:50 Sent To  
Notes
2022-03-15 17:55:27PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE POOL DEPTH IS SPECIFIED AS MORE THAN 5 FEET
 WHICH REQUIRES A LADDER, STEPS, BENCH OR SWIMOUT IN THE
 DEEP END. R4501.18 LADDERS AND STEPS. ALL POOLS WHETHER
 PUBLIC OR PRIVATE SHALL BE PROVIDED WITH A LADDER OR
 STEPS IN THE SHALLOW END WHERE WATER DEPTH EXCEEDS 24
 INCHES (610 MM). IN PRIVATE POOLS WHERE WATER DEPTH
 EXCEEDS 5 FEET (1524 MM), THERE SHALL BE LADDERS,
 STAIRS OR UNDERWATER BENCHES/SWIMOUTS IN THE DEEP END.
 WHERE MANUFACTURED DIVING EQUIPMENT IS TO BE USED,
 BENCHES OR SWIMOUTS SHALL BE RECESSED OR LOCATED IN A
 CORNER.
 EXCEPTION: IN PRIVATE POOLS HAVING MORE THAN ONE
 SHALLOW END, ONLY ONE SET OF STEPS ARE REQUIRED. A
 BENCH, SWIM-OUT OR LADDER MAY BE USED AT ALL ADDITIONAL
 SHALLOW ENDS IN LIEU OF AN ADDITIONAL SET OF STEPS.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-02-05 Cont ID  
Sent By fgiaquin Date 2022-02-05 Time 18:44 Rev Time 0.00
Received By fgiaquin Date 2022-02-05 Time 18:23 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2022-01-31 Cont ID  
Sent By lcrespo Date 2022-01-31 Time 10:49 Rev Time 0.00
Received By lcrespo Date 2022-01-31 Time 10:49 Sent To  
Notes
2022-01-31 10:49:53GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE, AND A GAS PLAN REVIEW HAS NOT
 BEEN PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND
 PLANS WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR
 FOR THE SCOPE OF WORK PER THE WPB AMENDMENT TO THE FBC
 SEC. 105.1.
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-04-13 Cont ID  
Sent By rmcdouga Date 2022-04-13 Time 13:18 Rev Time 0.00
Received By rmcdouga Date 2022-03-22 Time 07:11 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-03-15 Cont ID  
Sent By rmcdouga Date 2022-03-15 Time 17:55 Rev Time 0.00
Received By rmcdouga Date 2022-01-24 Time 08:24 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2022-01-31 Cont ID  
Sent By lcrespo Date 2022-01-31 Time 10:49 Rev Time 0.00
Received By lcrespo Date 2022-01-31 Time 10:49 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-04-13 Cont ID  
Sent By rmcdouga Date 2022-04-13 Time 13:17 Rev Time 0.00
Received By rmcdouga Date 2022-04-13 Time 13:17 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-03-15 Cont ID  
Sent By rmcdouga Date 2022-03-15 Time 17:49 Rev Time 0.00
Received By rmcdouga Date 2022-03-15 Time 17:49 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2022-02-01 Cont ID  
Sent By asangele Date 2022-02-01 Time 12:33 Rev Time 0.00
Received By asangele Date 2022-02-01 Time 12:33 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved