| Plan Review Stops For Permit 22010219 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2022-07-19 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2022-07-19 |
Time |
18:41 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2022-07-19 |
Time |
18:36 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2022-06-24 |
|
|
Cont ID |
|
| Sent By |
fgiaquin |
Date |
2022-06-24 |
Time |
19:41 |
Rev Time |
0.00 |
| Received By |
fgiaquin |
Date |
2022-06-24 |
Time |
18:54 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
N |
Date |
2022-07-20 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2022-07-20 |
Time |
07:41 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2022-07-20 |
Time |
07:35 |
Sent To |
|
|
| Notes |
| 2022-07-20 07:42:01 | A SEPARATE PERMIT IS REQUIRED FOR GAS PIPING AND | | | APPLIANCE INSTALLATIONS. |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
1 |
Status |
P |
Date |
2022-07-13 |
|
|
Cont ID |
|
| Sent By |
amhamilt |
Date |
2022-07-13 |
Time |
10:21 |
Rev Time |
0.00 |
| Received By |
amhamilt |
Date |
2022-07-13 |
Time |
10:21 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2022-07-29 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-07-29 |
Time |
13:55 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-07-29 |
Time |
08:44 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2022-07-27 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-07-27 |
Time |
07:46 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-07-26 |
Time |
12:32 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
2022-07-20 |
Time |
|
Rev Time |
0.00 |
| Received By |
cdecoeur |
Date |
2022-06-17 |
Time |
10:41 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
3 |
Status |
P |
Date |
2022-07-29 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-07-29 |
Time |
13:54 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-07-29 |
Time |
13:54 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
F |
Date |
2022-07-27 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-07-27 |
Time |
07:20 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-07-27 |
Time |
07:20 |
Sent To |
|
|
| Notes |
| 2022-07-27 07:46:39 | AS THE DRAWINGS SUBMITTED ARE MECHANICAL DRAWINGS I SEE | | | NO REASON TO SHOW THE ELECTRICAL SYMBOLS ON THE | | | MECHANICAL DRAWINGS. THE RESPONSE LETTER INDICATES THE | | | SCOPE OF WORK TO BE ON SHEET M0.1, I DO NOT SEE A SCOPE | | | OF WORK ON SHEET M0.1. PLEASE PROVIDE A SCOPE OF WORK. | | | I DO SEE GENERAL NOTES AND DETAIL DRAWINGS THAT DO NOT | | | SEEM TO APPLY TO THIS PROJECT AS I SEE A NOTE 4 IN THE | | | LAUNDRY ROOM AND THE DRYER EXHAUST DUCT IN THE LAUNDRY | | | ROOM ON SHEET M1.1. IS THIS THE ONLY SCOPE OF WORK FOR | | | THIS PROJECT? IF SO PLEASE REMOVE THE NOTES THAT DO NOT | | | APPLY TO THIS PROJECT. FBC 107.2.1 | | | | | | MICHAEL EDWARDS | | | MECHANICAL EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL. 33401 | | | 561-805-6728 | | | [email protected] | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2022-06-21 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-06-21 |
Time |
07:19 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-06-21 |
Time |
07:19 |
Sent To |
|
|
| Notes |
| 2022-06-21 07:27:40 | PROVIDE A MECHANICAL SCOPE OF WORK, PROVIDE DRAWINGS | | | WITH ALL WORK TO BE COMPLETED UNDER THIS PERMIT. IS THE | | | MECHANICAL SYSTEM BEING REPLACED? IS ALL THE DUCTWORK | | | BEING REPLACED? WHAT ARE THE CIRCLES ON THE DRAWINGS? | | | WHAT DOES THE LETTER J INDICATE ON THE DRAWINGS? NOTE 1 | | | INDICATES NEW EXHAUST FAN BUT THIS NUMBER IS NOT ON THE | | | DRAWINGS. ARE ALL OF THE BATH EXHAUST FANS BEING | | | REPLACED? FBC 107.2.1 | | | | | | MICHAEL EDWARDS | | | MECHANICAL EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL. 33401 | | | 561-805-6728 | | | [email protected] | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2022-06-21 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2022-06-21 |
Time |
10:11 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2022-06-21 |
Time |
10:04 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2022-07-29 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-07-29 |
Time |
13:55 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-07-29 |
Time |
13:55 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2022-07-19 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2022-07-19 |
Time |
18:41 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2022-07-19 |
Time |
18:41 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
N |
Date |
2022-07-13 |
|
|
Cont ID |
|
| Sent By |
ahamilto |
Date |
2022-07-13 |
Time |
10:21 |
Rev Time |
0.00 |
| Received By |
amhamilt |
Date |
2022-07-13 |
Time |
10:21 |
Sent To |
|
|
| Notes |
|
|