Plan Review Details - Permit 21100999
Plan Review Stops For Permit 21100999
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 3 Status P Date 2022-03-04 Cont ID  
Sent By rmcphers Date 2022-03-04 Time 11:10 Rev Time 0.00
Received By rmcphers Date 2022-03-04 Time 11:10 Sent To  
Notes
***NONE***

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status F Date 2022-02-14 Cont ID  
Sent By rmcphers Date 2022-02-14 Time 09:50 Rev Time 0.00
Received By rmcphers Date 2022-02-14 Time 09:50 Sent To  
Notes
2022-02-14 09:51:06PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY.
  
 ADDITIONAL INFORMATION REGARDING ASBESTOS REQUIREMENTS
 CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2021-11-22 Cont ID  
Sent By rmcphers Date 2021-11-22 Time 16:02 Rev Time 0.00
Received By rmcphers Date 2021-11-22 Time 16:01 Sent To  
Notes
2021-11-22 16:02:22PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY.
  
 ADDITIONAL INFORMATION REGARDING ASBESTOS REQUIREMENTS
 CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 5 Status P Date 2022-03-28 Cont ID  
Sent By rmcphers Date 2022-03-28 Time 15:15 Rev Time 0.00
Received By rmcphers Date 2022-03-28 Time 15:15 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status F Date 2022-03-23 Cont ID  
Sent By rmcphers Date 2022-03-23 Time 09:58 Rev Time 0.00
Received By rmcphers Date 2022-03-23 Time 09:58 Sent To  
Notes
2022-03-23 10:02:52CONDO REMODEL
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED -
  
 1) A FLAME SPREAD TEST REPORT FOR THE LAMINATE FLOOR IT
 SELF IS NOT REQUIRED. PLEASE PROVIDE THE FLAME SPREAD
 TEST REPORT FOR THE LAMINATE FLOORING AND THE
 UNDERLAYMENT AS A SYSTEM - OR - A FLAME SPREAD TEST
 REPORT FOR THE UNDERLAYMENT IT SELF.
  
 FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723. (DO NOT NEED THIS REPORT IF THE PADDING IS
 ATTACHED TO THE FLOORING)
  
 2). YOU CAN EMAIL ME THE PROPOSED TEST REPORTS TO
 VERIFY THAT THEY ARE TEST REPORTS BEFORE RESUBMITTING
 TO PROJECTDOX ( [email protected] )
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2022-03-04 Cont ID  
Sent By rmcphers Date 2022-03-04 Time 11:10 Rev Time 0.00
Received By rmcphers Date 2022-03-04 Time 11:10 Sent To  
Notes
2022-03-04 11:34:37CONDO REMODEL
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED -
  
 DRAWING A-102 UNDER SCOPE OF WORK - FLOORING LAMINATE
 ON MASTER BEDROOM TO BE REPLACED - YOU HAVE SUPPLIED
 UNDERLAYMENT TEST REPORTS FOR TILE FLOORING - WHICH
 WILL NOT WORK FOR THE FLAME SPREAD REQUIREMENT
  
 "C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723. (DO NOT NEED THIS REPORT IF THE PADDING IS
 ATTACHED TO THE FLOORING)"
  
 THE FLAME SPREAD TEST REPORT WILL NEED TO BE FOR THE
 COMPLETE SYSTEM (LAMINATE FLOORING AND UNDERLAYMENT) OR
 THE UNDERLAYMENT ALONE.
  
 1) THE FOLLOWING ACUSTICAL TEST REPORTS ARE REQUIRED:
  
 MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO
 DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST
 REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE
 MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT)
  
 A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR
 BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90..
 PROVIDE A COPY OF THE TEST REPORT. (A DROP CEILING
 SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING ASSEMBLY
 DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED DROP
 CEILING DESCRIPTION)
  
 B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN
 DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC
 OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN
 IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN
 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH
 ASTM E 492. PROVIDE A COPY OF THE TEST REPORT. (A DROP
 CEILING SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING
 ASSEMBLY DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED
 DROP CEILING DESCRIPTION)
  
 C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723. (DO NOT NEED THIS REPORT IF THE PADDING IS
 ATTACHED TO THE FLOORING)
  
 2). YOU CAN EMAIL ME THE PROPOSED TEST REPORTS TO
 VERIFY THAT THEY ARE TEST REPORTS BEFORE RESUBMITTING
 TO PROJECTDOX ( [email protected] )
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2022-02-14 Cont ID  
Sent By rmcphers Date 2022-02-14 Time 09:49 Rev Time 0.00
Received By rmcphers Date 2022-02-14 Time 09:49 Sent To  
Notes
2022-02-14 09:50:26CONDO REMODEL
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 2ND REVIEW
  
 CORRECTIONS NEEDED -
  
 1) THE FOLLOWING ACUSTICAL TEST REPORTS ARE REQUIRED:
  
 MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO
 DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST
 REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE
 MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT)
  
 A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR
 BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90..
 PROVIDE A COPY OF THE TEST REPORT. (A DROP CEILING
 SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING ASSEMBLY
 DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED DROP
 CEILING DESCRIPTION)
  
 B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN
 DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC
 OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN
 IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN
 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH
 ASTM E 492. PROVIDE A COPY OF THE TEST REPORT. (A DROP
 CEILING SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING
 ASSEMBLY DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED
 DROP CEILING DESCRIPTION)
  
 C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723. (DO NOT NEED THIS REPORT IF THE PADDING IS
 ATTACHED TO THE FLOORING)
  
 2). YOU CAN EMAIL ME THE PROPOSED TEST REPORTS TO
 VERIFY THAT THEY ARE TEST REPORTS BEFORE RESUBMITTING
 TO PROJECTDOX ( [email protected] )
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-11-22 Cont ID  
Sent By rmcphers Date 2021-11-22 Time 16:02 Rev Time 0.00
Received By rmcphers Date 2021-11-22 Time 16:02 Sent To  
Notes
2021-11-22 16:03:11CONDO REMODEL
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED -
  
 1) THE FOLLOWING ACUSTICAL TEST REPORTS ARE REQUIRED:
  
 MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO
 DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST
 REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE
 MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT)
  
 A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR
 BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90..
 PROVIDE A COPY OF THE TEST REPORT. (A DROP CEILING
 SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING ASSEMBLY
 DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED DROP
 CEILING DESCRIPTION)
  
 B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN
 DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC
 OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN
 IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN
 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH
 ASTM E 492. PROVIDE A COPY OF THE TEST REPORT. (A DROP
 CEILING SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING
 ASSEMBLY DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED
 DROP CEILING DESCRIPTION)
  
 C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723. (DO NOT NEED THIS REPORT IF THE PADDING IS
 ATTACHED TO THE FLOORING)
  
 2). YOU CAN EMAIL ME THE PROPOSED TEST REPORTS TO
 VERIFY THAT THEY ARE TEST REPORTS BEFORE RESUBMITTING
 TO PROJECTDOX ( [email protected] )
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2022-02-14 Cont ID  
Sent By fgiaquin Date 2022-02-14 Time 19:01 Rev Time 0.00
Received By fgiaquin Date 2022-02-14 Time 18:20 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2021-11-17 Cont ID  
Sent By fgiaquin Date 2021-11-17 Time 22:49 Rev Time 0.00
Received By fgiaquin Date 2021-11-17 Time 22:09 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2022-02-02 Cont ID  
Sent By pleduc Date 2022-02-02 Time   Rev Time 0.00
Received By pleduc Date 2022-02-02 Time 10:41 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2021-10-26 Cont ID  
Sent By pleduc Date 2021-10-26 Time   Rev Time 0.00
Received By pleduc Date 2021-10-26 Time 15:35 Sent To  
Notes
2021-10-26 15:42:13THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) THERE ARE INDICATIONS THAT PART THE MASTER BATHROOM
 WALL IS A FIRE RATED TENANT SEPARATION WALL.
  
 ENSURE FIRE RATED TENANT SEPARATION WALLS ARE REPAIRED
 TO THE EXISTING FIRE RATED SEPARATION.
  
 PROVIDE AN APPLICABLE NOTE OF ACKNOWLEDGMENT.
  
  
  
 2) THERE ARE INDICATIONS OF FLOOR REPLACEMENT IN THE
 MASTER BEDROMM HOWEVER, THERE ARE NO SPECIFICATIONS
 SHEETS FOR THE UNDERLAYMENT AND FINISHED FLOOR, THAT
 INDICATE MEETING THE REQUIREMENTS PER NFPA'
  
 THERE IS A CORRECT INDICATION ON SHEET A-102, FOR THE
 WALL & CEILING FINSISHES; HOWEVER, PRODUCT SPEC SHEETS
 ARE NEEDED FOR THE OFFICIAL RECORD OF BOTH PRODUCTS.
  
 PLEASE REVIEW AND PROVIDE SPEC SHEETS.
  
  
  
 3) THE APPLICATION INDICATES APT. 2406 ; HOWEVER, THE
 PLAN SHEETS INDICATE APT 206.
  
 PLEASE REVIEW AND CORRECT.
  
  
  
 4) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
 5) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2022-03-23 Cont ID  
Sent By rmcphers Date 2022-03-23 Time 10:04 Rev Time 0.00
Received By rmcphers Date 2022-03-18 Time 08:50 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-03-04 Cont ID  
Sent By rmcphers Date 2022-03-04 Time 11:34 Rev Time 0.00
Received By rmcphers Date 2022-02-25 Time 08:34 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-02-14 Cont ID  
Sent By fgiaquin Date 2022-02-14 Time 19:01 Rev Time 0.00
Received By fgiaquin Date 2022-02-01 Time 15:44 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-11-22 Cont ID  
Sent By rmcphers Date 2021-11-22 Time 16:08 Rev Time 0.00
Received By rmcphers Date 2021-10-21 Time 15:45 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2022-02-08 Cont ID  
Sent By lcrespo Date 2022-02-08 Time 14:36 Rev Time 0.00
Received By lcrespo Date 2022-02-08 Time 14:36 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2021-11-02 Cont ID  
Sent By lcrespo Date 2021-11-02 Time 12:48 Rev Time 0.00
Received By lcrespo Date 2021-11-02 Time 12:48 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2022-03-23 Cont ID  
Sent By rmcphers Date 2022-03-23 Time 10:04 Rev Time 0.00
Received By rmcphers Date 2022-03-23 Time 10:04 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-02-14 Cont ID  
Sent By rmcphers Date 2022-02-14 Time 09:52 Rev Time 0.00
Received By rmcphers Date 2022-02-14 Time 09:52 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-11-22 Cont ID  
Sent By rmcphers Date 2021-11-22 Time 16:06 Rev Time 0.00
Received By rmcphers Date 2021-11-22 Time 16:06 Sent To  
Notes
2021-11-22 16:08:11SIGNATURE REVIEW
  
 ALL OF THE DRAWINGS DO NOT SHOW AS DIGITALLY SIGNED IN
 ADOBE READER -
  
 SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. (A
 CERTIFICATE-BASED DIGITAL SIGNATURE (OFTEN JUST CALLED
 A DIGITAL SIGNATURE) IS A SPECIFIC TYPE OF
 E-SIGNATURE).- OR - IF YOUR ARCHITECT OR ENGINEER DOES
 NOT HAVE AN ELECTRONIC OR DIGITAL SIGNATURE - YOU CAN
 DROP OFF THE ORIGINAL SIGNED AND SEALED
 DRAWINGS/DOCUMENTS TO THE FRONT DESK IN THE BUILDING
 DIVISION AT THE CITY HALL.
  
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
  