| Plan Review Stops For Permit 21100039 |
| Review Stop |
AD |
ADDRESSING |
| Rev No |
2 |
Status |
P |
Date |
2021-12-17 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2021-12-17 |
Time |
15:28 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2021-12-17 |
Time |
15:28 |
Sent To |
|
|
| Notes |
| 2021-12-17 15:29:29 | TITLE BLOCKS UPDATED WITH THE CORRECT ADDRESSES. THIS | | | PERMIT IS FOR THE BUILDING THAT FACES ALHAMBRA PL ONLY |
|
|
| Review Stop |
AD |
ADDRESSING |
| Rev No |
1 |
Status |
F |
Date |
2021-10-18 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2021-10-18 |
Time |
16:43 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2021-10-18 |
Time |
16:43 |
Sent To |
|
|
| Notes |
| 2021-10-18 16:48:37 | THIS PERMIT IS FOR THE HOUSE THAT FACES ALHAMBRA PL | | | ONLY, HOWEVER THE PLANS HAVE INCONSISTENT ADDRESSES IN | | | THE TITLE BLOCK, PLEASE RECTIFY THIS. THE CORRECT | | | ADDRESS SHOULD BE 266 ALHAMBRA. THIS PERMIT DOES NOT | | | INCLUDE THE GUEST HOUSE WHICH HAS BEEN ASSIGNED THE | | | ADDRESS OF 7830 S OLIVE AVE. IF YOU HAVE ANY QUESTIONS | | | PLEASE CONTACT [email protected] OR CALL 561-805-6659. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2022-02-11 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2022-02-11 |
Time |
15:54 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2022-02-11 |
Time |
11:17 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2022-01-25 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2022-01-25 |
Time |
10:58 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2022-01-25 |
Time |
10:46 |
Sent To |
|
|
| Notes |
| 2022-01-25 11:14:59 | PLAN REVIEW AUDIT |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2022-02-11 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2022-02-11 |
Time |
16:16 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2022-02-11 |
Time |
11:17 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
F |
Date |
2022-01-31 |
|
|
Cont ID |
|
| Sent By |
mpeterso |
Date |
2022-01-31 |
Time |
11:38 |
Rev Time |
0.00 |
| Received By |
mpeterso |
Date |
2022-01-31 |
Time |
11:38 |
Sent To |
|
|
| Notes |
| 2022-01-31 11:38:08 | ELECTRICAL AUDIT OF PLANS FAILED | | | 1) PANEL SCHEDULES DENOTE SEVERAL CIRCUITS SUPPLYING | | | SEPARATE STRUCTURE WHICH IS NOT IN COMPLIANCE WITH NEC | | | 225.30 | | | 2) ELECTRICAL RISER DENOTES AN EQUIPMENT GROUNDING | | | CONDUCTOR FROM METER TO MAIN DISCONNECT WHICH IS NOT IN | | | COMPLIANCE WITH NEC 250.30(A)(1) | | | | | | CODES IN EFFECT: | | | | | | FBC = FLORIDA BUILDING CODE 2017 6TH EDITION | | | WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017 | | | 6TH ED, CHAPTER 1. | | | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 | | | 6TH EDITION | | | FBC EX = FLORIDA BUILDING CODE EXISTING BUILDING 2017 | | | 6TH EDITION | | | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION | | | NEC = NFPA 70 2017 EDITION, NATIONAL ELECTRICAL CODE | | | FS = FLORIDA STATUTES | | | FAC = FLORIDA ADMINISTRATIVE CODE | | | | | | | | | MICHAEL PETERSON | | | ELECTRICAL PLANS EXAMINER | | | [email protected] | | | 561-805-6746 | | | |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
N |
Date |
2022-01-27 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2022-01-27 |
Time |
07:15 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2022-01-27 |
Time |
07:15 |
Sent To |
|
|
| Notes |
| 2022-01-27 07:16:03 | GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN | | | THIS SUBMITTAL PACKAGE, AND A GAS PLAN REVIEW HAS NOT | | | BEEN PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND | | | PLANS WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE | | | RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT | | | REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER | | | THE WPB AMENDMENTS TO FBC SEC. 107.2.1. | | | | | | A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR | | | FOR THE SCOPE OF WORK PER THE WPB AMENDMENTO THE FBC | | | SEC. 105.1. | | | | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2022-02-13 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2022-02-13 |
Time |
08:54 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2022-02-03 |
Time |
17:27 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2022-02-01 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2022-02-01 |
Time |
07:42 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2022-01-07 |
Time |
08:43 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2022-01-10 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2022-01-06 |
Time |
08:42 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2021-12-17 |
Time |
09:59 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2021-10-22 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2021-10-22 |
Time |
17:52 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2021-10-15 |
Time |
06:20 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
2 |
Status |
P |
Date |
2022-02-23 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2022-02-23 |
Time |
10:36 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2022-02-01 |
Time |
07:44 |
Sent To |
|
|
| Notes |
| 2022-02-18 15:43:51 | RECEIPT MU-2022-007266 - $1892.30 PAID | | 2022-02-01 07:44:13 | 2/1/22 EMAILED IMPACT OFFICE TO REVIEW. LEM |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
1 |
Status |
F |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
2021-10-12 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
2021-10-12 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-10-12 08:46:41 | PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE | | | DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS | | | OFFICE. NOTIFICATION WILL OCCUR WHEN PLANS ARE NEAREST | | | FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE | | | OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL | | | IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME | | | THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM | | | CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS | | | TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
P |
Date |
2022-01-25 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2022-01-25 |
Time |
08:54 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2022-01-25 |
Time |
08:54 |
Sent To |
|
|
| Notes |
| 2022-01-25 08:55:17 | AUDIT ONLY ME |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2022-01-27 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2022-01-27 |
Time |
07:11 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2022-01-27 |
Time |
07:11 |
Sent To |
|
|
| Notes |
| 2022-01-27 07:13:47 | PLUMBING AUDIT APPROVED. |
|
|
| Review Stop |
PRIVATEPRV |
PRIVATE PROVIDER DOCUMENTS |
| Rev No |
4 |
Status |
P |
Date |
2022-02-09 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2022-02-09 |
Time |
10:48 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2022-02-07 |
Time |
13:58 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
PRIVATEPRV |
PRIVATE PROVIDER DOCUMENTS |
| Rev No |
3 |
Status |
P |
Date |
2022-01-10 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2022-01-10 |
Time |
08:42 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2022-01-10 |
Time |
08:42 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
PRIVATEPRV |
PRIVATE PROVIDER DOCUMENTS |
| Rev No |
2 |
Status |
F |
Date |
2022-01-06 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2022-01-06 |
Time |
11:45 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2022-01-06 |
Time |
11:45 |
Sent To |
|
|
| Notes |
| 2022-01-06 11:46:47 | FS553.791, AFFIDAVIT DOES NOT INCLUDE THE MOST CURRENT | | | REVISION TO THE PLANS. | | | FOR INSTANCE SEE A101, DATE ON PLAN IS 10/2021 AND WAS | | | DIGITALLY SIGNED 12/13/2021, AFFIDAVIT REFERS TO | | | VERSION 1 SIGNING DATE. CHECK ALL. | | | | | | |
|
|
| Review Stop |
PRIVATEPRV |
PRIVATE PROVIDER DOCUMENTS |
| Rev No |
1 |
Status |
P |
Date |
2021-12-17 |
|
|
Cont ID |
|
| Sent By |
dbattles |
Date |
2021-12-17 |
Time |
13:18 |
Rev Time |
0.00 |
| Received By |
dbattles |
Date |
2021-12-17 |
Time |
13:18 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
R |
ROOF PLAN REVIEW |
| Rev No |
2 |
Status |
N |
Date |
2022-02-11 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2022-02-11 |
Time |
15:58 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2022-02-11 |
Time |
11:17 |
Sent To |
|
|
| Notes |
| 2022-02-11 15:59:30 | DEFERRAL ON PLAN PAGE A-501: SUBMIT A ROOFING | | | SUB-PERMIT WITH PRODUCT APPROVALS. CT |
|
|
| Review Stop |
R |
ROOF PLAN REVIEW |
| Rev No |
1 |
Status |
F |
Date |
2022-01-25 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2022-01-25 |
Time |
10:58 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2022-01-25 |
Time |
10:58 |
Sent To |
|
|
| Notes |
| 2022-01-25 11:04:07 | ROOFING SYSTEM | | | REVIEWED BY ROGER MCPHERSON | | | 561-805-6716 | | | [email protected] | | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | | AMENDMENT | | | | | | CORRECTIONS NEEDED - | | | | | | 1) PLEASE PROVIDE THE ROOFING SYSTEM DETAILS - FBC WPB | | | 107.2.1.1 | | | | | | 2) ROOFING SYSTEM DETAILS MAY BE DEFERRED SUBMITTALS BY | | | LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION | | | DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE | | | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE | | | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT | | | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE | | | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A | | | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL | | | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE | | | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE | | | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION | | | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. | | | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE | | | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN | | | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD | | | THEM TO THE BUILDING OFFICIAL WITH A NOTATION | | | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE | | | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO | | | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL | | | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED | | | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING | | | OFFICIAL. |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2022-02-09 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2022-02-09 |
Time |
10:48 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2022-02-07 |
Time |
13:58 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2022-01-25 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2022-01-25 |
Time |
11:14 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2022-01-25 |
Time |
11:14 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2022-01-06 |
|
|
Cont ID |
|
| Sent By |
avann |
Date |
2022-01-06 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
2022-01-06 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-01-06 13:27:52 | ZONING APPROVED WITH THE FOLLOWING PROVISOS: | | | | | | 1.) CUMULATIVE DRIVEWAY WIDTH OF ALL DRIVEWAYS ON THE | | | PROPERTY SHALL NOT EXCEED 20 FT. IN WIDTH. SEPARATE | | | PERMITS AND REVIEWS REQUIRED FOR DRIVEWAYS. | | | | | | 2.) SEPARATE PERMIT SUBMITTAL, REVIEW, APPROVAL AND | | | INSTALLATION REQUIRED PRIOR TO ISSUANCE OF A | | | CERTIFICATE OF OCCUPANCY (C.O.): LANDSCAPING, | | | DRIVEWAYS, FENCE, SWIMMING POOL. | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
|
|
|
Cont ID |
|
| Sent By |
awooten |
Date |
2021-11-03 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
2021-11-03 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-10-22 12:22:30 | ******ZONING PROVISO***** | | | | | | PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY, | | | THE FOLLOWING CONDITIONS SHALL BE ADDRESSED: | | | | | | 1. A LANDSCAPE PERMIT, WHICH INLUDES A LANDSCAPE PLAN, | | | SHALL BE SUBMITTED TO THE BUILDING DIVISION FOR REVIEW. | | | | | | 2. THE LANDSCAPE MATERIAL SHOWN ON THE APPROVED | | | LANDSCAPE PERMIT SHALL BE INSTALLED AND PASS A FINAL | | | LANDSCAPE INSPECTION. | | | | | | | | | THE PROPOSED DRIVEWAY, POOL, AND FENCE REQUIRE A | | | SEPARATE PERMIT. THE PROPOSED DRIVEWAY PLAN HAS A WIDTH | | | THAT EXCEEDS THE LIMITS OF CODE.**** | | | | | | THIS PERMIT IS CONNECTED TO PERMIT 21100037 (7830 S | | | OLIVE AVENUE) WHICH IS FOR THE PROPOSED GUEST HOUSE AT | | | THE REAR OF THE PROPERTY. | | | | | | ALANA WOOTEN | | | PLANNER | | | PLANNING DIVISON | | | 561-822-1449 | | | [email protected] | | | | | | | | | |
|
|