| Plan Review Stops For Permit 21081109 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
9 |
Status |
P |
Date |
2022-05-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-05-09 |
Time |
14:24 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-05-09 |
Time |
14:24 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
8 |
Status |
P |
Date |
2022-05-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-05-09 |
Time |
13:04 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-05-09 |
Time |
13:04 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
7 |
Status |
F |
Date |
2022-04-08 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-04-08 |
Time |
15:18 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-04-08 |
Time |
15:18 |
Sent To |
|
|
| Notes |
| 2022-04-08 14:47:28 | PLAN REVIEW COMMENTS | | | | | | 7 TH REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | | | | NOTE: IT IS ACKNOWLEDGED BY THE CITY BUILDING DIVISION | | | THAT THESE ROLL-UP STORM SHUTTERS PROPOSED FOR THE ROOF | | | TOP GAZEBO ARE NOT REQUIRED TO BE INSTALLED BY THE | | | FLORIDA BUILDING CODE. | | | | | | 1) NOT RESOLVED. [ SUBMIT NEW ENGINEERING FOR OPENING | | | DESIGN PRESSURES. SEE COMMENT #2. ] PROVIDE A LETTER | | | FROM A FLORIDA LICENSED ENGINEER AFFIRMING THAT THE | | | INSTALLATION OF THESE ROLL-UP STORM SHUTTERS WILL NOT | | | HAVE AN ADVERSE EFFECT ON THE HOST STRUCTURE WHEN IN | | | USE DURING A WIND EVENT. FBC 1604.2 & 107.2.1 | | | | | | 2) NOT RESOLVED. [ THE DESIGN PRESSURES IN THE LATEST | | | INSTALLATION SCHEDULE AND THE UPDATED DESIGN PRESSURES | | | FROM STORM SMART DO NOT CORRESPOND WITH THE OPENING | | | DESIGN PRESSURES FROM THE PROFESSIONAL ENGINEER | | | (ENGINEERING EXPRESS). BECAUSE THIS IS A HIGHRISE | | | BUILDING SIGNED AND SEALED ENGINEERING FROM A FLORIDA | | | LICENSED P.E. FOR THE WINDLOAD DATA AND OPENING DESIGN | | | PRESSURES IS REQUIRED. ] PLEASE HAVE THE ENGINEER | | | EXPLAIN THE SUBSTANTIAL PRESSURE DIFFERENCE BETWEEN THE | | | DESIGN PRESSURES FOR OPENING #1 AND THE OTHER OPENINGS. | | | ESPECIALLY OPENING #5 WHICH IS IN THE SAME WALL ZONE | | | AND IS 134.5 SQFT COMPARED TO 202.5 SQFT. FBC 1604.2 | | | | | | 3) RESOLVED. A NEW INSTALLATION SCHEDULE WAS SUBMITTED. | | | NOTE: THE OPENING SIZES AND DESIGN PRESSURES WILL HAVE | | | TO BE CONSISTENT WITH THE ENGINEERING. FBC AMENDMENTS | | | 107.2.1 | | | | | | 4) RESOLVED. OPENIING SIZE WAS CORRECTED. | | | | | | 5) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH | | | OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. | | | | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
6 |
Status |
F |
Date |
2022-04-04 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-04-04 |
Time |
11:27 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-04-04 |
Time |
11:27 |
Sent To |
|
|
| Notes |
| 2022-04-04 11:27:02 | PLAN REVIEW COMMENTS | | | | | | 6 TH REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | | | | NOTE: IT IS ACKNOWLEDGED BY THE CITY BUILDING DIVISION | | | THAT THESE ROLL-UP STORM SHUTTERS PROPOSED FOR THE ROOF | | | TOP GAZEBO ARE NOT REQUIRED TO BE INSTALLED BY THE | | | FLORIDA BUILDING CODE. | | | | | | 1) PROVIDE A LETTER FROM A FLORIDA LICENSED ENGINEER | | | AFFIRMING THAT THE INSTALLATION OF THESE ROLL-UP STORM | | | SHUTTERS WILL NOT HAVE AN ADVERSE EFFECT ON THE HOST | | | STRUCTURE WHEN IN USE DURING A WIND EVENT. FBC 1604.2 & | | | 107.2.1 | | | | | | 2) PLEASE HAVE THE ENGINEER EXPLAIN THE SUBSTANTIAL | | | PRESSURE DIFFERENCE BETWEEN THE DESIGN PRESSURES FOR | | | OPENING #1 AND THE OTHER OPENINGS. ESPECIALLY OPENING | | | #5 WHICH IS IN THE SAME WALL ZONE AND IS 134.5 SQFT | | | COMPARED TO 202.5 SQFT. FBC 1604.2 | | | | | | 3) SUBMIT A CORRECTED HURRICANE SHUTTER INSTALLATION | | | SCHEDULE. FBC 107.2.1 | | | | | | 4) ON SHEET 9 OF 29 OF THE MULLION PRODUCT APPROVAL | | | (FL13068-R5), THE DESIGN PRESSURE OF 105 PSF IS CIRCLED | | | FOR THE AVERAGE SPAN WIDTH OF UP TO 132" AND A MULLION | | | LENGTH UP TO 144". I BELIEVE THAT THE OPENING IN | | | QUESTION IS 197" WIDE AND 148" IN HEIGHT (BASED ON | | | INFORMATION THAT WAS PREVIOUSLY PROVIDED). THE REQUIRED | | | LENGTH FOR THE MULLION WOULD EXCEED THE 144" MULLION | | | LENGTH ALLOWED BY THE PRODUCT APPROVAL. PLEASE CLARIFY. | | | FBC 107.2.1 & 1604.2 | | | | | | 5) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH | | | OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. | | | | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
5 |
Status |
F |
Date |
2022-02-17 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-02-17 |
Time |
14:30 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-02-14 |
Time |
10:26 |
Sent To |
|
|
| Notes |
| 2022-02-14 10:48:52 | PLAN REVIEW COMMENTS | | | | | | 5 TH REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING - THE PROPOSED SCREEN FABRIC IMPACT | | | PROTECTION DEVICE HAS A MAXIMUM DESIGN PRESSURES OF +/- | | | 60 PSF WHICH IS LESS THAN THE REQUIRED OPENING | | | PRESSURES. WE ACKNOWLEDGE THAT THE ROLL UP AND FABRIC | | | SHUTTERS ARE NOT BEING INSTALLED TO PROVIDE IMPACT | | | PROTECTION. OUR CONCERN IS THAT THE DEVICES REMAIN | | | INTACT AND NOT BECOME DETACHED DURING A WIND EVENT. THE | | | ROLL UP SHUTTERS ARE DESIGNED TO BE INSTALLED ON AN | | | ENCLOSED BUILDING AND THE FABRIC PANEL WILL ALLOW THE | | | WIND INTO THE INTERIOR OF THE GAZEBO WHICH WILL | | | INCREASE THE PRESSURE ON THE INTERNAL SIDE OF THE ROLL | | | UP SHUTTERS. THE INTERNAL PRESSURE WILL BE GREATER THAN | | | THE CONFIGURATION TESTED FOR THE PRODUCT APPROVAL. YOU | | | MAY WISH TO LOOK AT OTHER OPTIONS, POSSIBLY ROLL UP | | | GARAGE DOORS. | | | | | | | | | PREVIOUS REVIEW COMMENTS BELOW FOR REFERENCE | | | PLAN REVIEW COMMENTS | | | | | | 4 TH REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | COMMENTS FROM THE 3RD REVIEW WERE NOT ADDRESSED. | | | | | | NOTE: IT IS ACKNOWLEDGED BY THE CITY BUILDING DIVISION | | | THAT THESE ROLL-UP STORM SHUTTERS PROPOSED FOR THE ROOF | | | TOP GAZEBO ARE NOT REQUIRED TO BE INSTALLED BY THE | | | FLORIDA BUILDING CODE. | | | | | | 1) PROVIDE A LETTER FROM A FLORIDA LICENSED ENGINEER | | | AFFIRMING THAT THE INSTALLATION OF THESE ROLL-UP STORM | | | SHUTTERS WILL NOT HAVE AN ADVERSE EFFECT ON THE HOST | | | STRUCTURE WHEN IN USE DURING A WIND EVENT. FBC | | | 107.2.1.2 | | | | | | 2) PLEASE HAVE THE ENGINEER EXPLAIN THE SUBSTANTIAL | | | PRESSURE DIFFERENCE BETWEEN THE DESIGN PRESSURES FOR | | | OPENING #1 AND THE OTHER OPENINGS. ESPECIALLY OPENING | | | #5 WHICH IS IN THE SAME WALL ZONE AND IS 134.5 SQFT | | | COMPARED TO 202.5 SQFT. FBC 107.2.1.2 | | | | | | 3) THE CUSTOM MOUNT DETAIL FOR OPENING #1 SHOWS ADDING | | | AN ALUMINUM ANGLE TO THE END RETENTION TRACK. I BELIEVE | | | THAT YOU INTEND THIS TO INCREASE THE DESIGN PRESSURE OF | | | THE ROLL-UP SHUTTERS. THE ENGINEER WILL NEED TO PROVIDE | | | A RATIONAL ANALYSIS THAT EXPLAINS HOW THIS WILL | | | INCREASE THE DESIGN PRESSURES OF THE PRODUCT. THE | | | ENGINEER WILL NEED TO PROVIDE A COPY OF THE TEST REPORT | | | FOR THE ROLL-UP SHUTTERS THAT INDICATES THE MODE OF | | | FAILURE. THE REPORT NEEDS TO SHOW WHICH COMPONENT OF | | | THE ROLL-UP FAILED. IF IT IS THE SLATS THAT FAILED WHEN | | | TESTED, REINFORCING THE RETENTION TRACK WILL NOT | | | INCREASE THE PRODUCT'S DESIGN PRESSURE. FBC 107.2.1 | | | | | | 4) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH | | | OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. | | | | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
F |
Date |
2021-12-01 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-12-01 |
Time |
13:18 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-12-01 |
Time |
13:18 |
Sent To |
|
|
| Notes |
| 2021-12-01 13:20:25 | PLAN | | | REVIEW COMMENTS | | | | | | 4TH REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | COMMENTS FROM THE 3RD REVIEW WERE NOT ADDRESSED. | | | | | | NOTE: IT IS ACKNOWLEDGED BY THE CITY BUILDING DIVISION | | | THAT THESE ROLL-UP STORM SHUTTERS PROPOSED FOR THE ROOF | | | TOP GAZEBO ARE NOT REQUIRED TO BE INSTALLED BY THE | | | FLORIDA BUILDING CODE. | | | | | | 1) PROVIDE A LETTER FROM A FLORIDA LICENSED ENGINEER | | | AFFIRMING THAT THE INSTALLATION OF THESE ROLL-UP STORM | | | SHUTTERS WILL NOT HAVE AN ADVERSE EFFECT ON THE HOST | | | STRUCTURE WHEN IN USE DURING A WIND EVENT. FBC | | | 107.2.1.2 | | | | | | 2) PLEASE HAVE THE ENGINEER EXPLAIN THE SUBSTANTIAL | | | PRESSURE DIFFERENCE BETWEEN THE DESIGN PRESSURES FOR | | | OPENING #1 AND THE OTHER OPENINGS. ESPECIALLY OPENING | | | #5 WHICH IS IN THE SAME WALL ZONE AND IS 134.5 SQFT | | | COMPARED TO 202.5 SQFT. FBC 107.2.1.2 | | | | | | 3) THE CUSTOM MOUNT DETAIL FOR OPENING #1 SHOWS ADDING | | | AN ALUMINUM ANGLE TO THE END RETENTION TRACK. I BELIEVE | | | THAT YOU INTEND THIS TO INCREASE THE DESIGN PRESSURE OF | | | THE ROLL-UP SHUTTERS. THE ENGINEER WILL NEED TO PROVIDE | | | A RATIONAL ANALYSIS THAT EXPLAINS HOW THIS WILL | | | INCREASE THE DESIGN PRESSURES OF THE PRODUCT. THE | | | ENGINEER WILL NEED TO PROVIDE A COPY OF THE TEST REPORT | | | FOR THE ROLL-UP SHUTTERS THAT INDICATES THE MODE OF | | | FAILURE. THE REPORT NEEDS TO SHOW WHICH COMPONENT OF | | | THE ROLL-UP FAILED. IF IT IS THE SLATS THAT FAILED WHEN | | | TESTED, REINFORCING THE RETENTION TRACK WILL NOT | | | INCREASE THE PRODUCT'S DESIGN PRESSURE. FBC 107.2.1 | | | | | | 4) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH | | | OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
F |
Date |
2021-11-10 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-11-10 |
Time |
17:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-11-10 |
Time |
17:05 |
Sent To |
|
|
| Notes |
| 2021-11-10 15:05:09 | PLAN | | | REVIEW COMMENTS | | | | | | 3RD REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | NOTE: IT IS ACKNOWLEDGED BY THE CITY BUILDING DIVISION | | | THAT THESE ROLL-UP STORM SHUTTERS PROPOSED FOR THE ROOF | | | TOP GAZEBO ARE NOT REQUIRED TO BE INSTALLED BY THE | | | FLORIDA BUILDING CODE. | | | | | | 1) PROVIDE A LETTER FROM A FLORIDA LICENSED ENGINEER | | | AFFIRMING THAT THE INSTALLATION OF THESE ROLL-UP STORM | | | SHUTTERS WILL NOT HAVE AN ADVERSE EFFECT ON THE HOST | | | STRUCTURE WHEN IN USE DURING A WIND EVENT. FBC | | | 107.2.1.2 | | | | | | 2) PLEASE HAVE THE ENGINEER EXPLAIN THE SUBSTANTIAL | | | PRESSURE DIFFERENCE BETWEEN THE DESIGN PRESSURES FOR | | | OPENING #1 AND THE OTHER OPENINGS. ESPECIALLY OPENING | | | #5 WHICH IS IN THE SAME WALL ZONE AND IS 134.5 SQFT | | | COMPARED TO 202.5 SQFT. FBC 107.2.1.2 | | | | | | 3) THE CUSTOM MOUNT DETAIL FOR OPENING #1 SHOWS ADDING | | | AN ALUMINUM ANGLE TO THE END RETENTION TRACK. I BELIEVE | | | THAT YOU INTEND THIS TO INCREASE THE DESIGN PRESSURE OF | | | THE ROLL-UP SHUTTERS. THE ENGINEER WILL NEED TO PROVIDE | | | A RATIONAL ANALYSIS THAT EXPLAINS HOW THIS WILL | | | INCREASE THE DESIGN PRESSURES OF THE PRODUCT. THE | | | ENGINEER WILL NEED TO PROVIDE A COPY OF THE TEST REPORT | | | FOR THE ROLL-UP SHUTTERS THAT INDICATES THE MODE OF | | | FAILURE. THE REPORT NEEDS TO SHOW WHICH COMPONENT OF | | | THE ROLL-UP FAILED. IF IT IS THE SLATS THAT FAILED WHEN | | | TESTED, REINFORCING THE RETENTION TRACK WILL NOT | | | INCREASE THE PRODUCT'S DESIGN PRESSURE. FBC 107.2.1 | | | | | | 4) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH | | | OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2021-10-12 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-10-12 |
Time |
11:16 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-10-12 |
Time |
11:16 |
Sent To |
|
|
| Notes |
| 2021-10-12 11:16:21 | PLAN | | | REVIEW COMMENTS | | | | | | 2ND REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) NOT RESOLVED. CIRCLE OR HI-LITE THE SPECIFIC ROOF | | | TOP STRUCTURE THAT WILL RECEIVE THE SHUTTERS ON THE | | | ELEVATION AND ROOF PLANS THAT WERE SUBMITTED. [THE | | | LOCATION OF THE PROJECT IS TOO VAGUE. SUBMIT ADDITIONAL | | | INFORMATION TO SPECIFY THE EXACT LOCATION OF WHERE THE | | | SHUTTERS WILL BE INSTALLED. PROVIDE ELEVATIONS OF THE | | | BUILDING AND A BUILDING FLOOR PLAN FOR THE LEVEL WHERE | | | THE UNIT IS LOCATED WITH THE SPECIFIC UNIT IDENTIFIED. | | | FBC AMENDMENTS 107.2.1] | | | | | | 2) NOT RESOLVED. THE ROOF TOP STRUCTURES HAVE MEAN ROOF | | | HEIGHTS OF MORE THAN 280 FEET. SUBMIT SITE SPECIFIC | | | ENGINEERING PREPARED BY A FLORIDA LICENSED ENGINEER FOR | | | THE REQUIRED COMPONENT AND CLADDING PRESSURES FOR THE | | | SHUTTERS ON THE ROOF TOP PAVILION AS PREVIOUSLY | | | REQUESTED. [THIS IS A HIGH RISE BUILDING THAT IS MORE | | | THAN 60 FEET IN HEIGHT. SUBMIT SIGNED AND SEALED DESIGN | | | PRESSURES FROM A FLORIDA LICENSED ENGINEER. SUBMIT | | | REQUIRED COMPONENT AND CLADDING DESIGN PRESSURES FOR | | | THE OPENINGS THAT HAVE BEEN PREPARED BY A FLORIDA | | | LICENSED ENGINEER. THE DOCUMENTS ARE REQUIRED TO BE | | | DIGITALLY SIGNED BY THE ENGINEER IF SUBMITTED | | | ELECTRONICALLY AND THE ENGINEER'S ORIGINAL HANDWRITTEN | | | SIGNATURE IF PAPER DOCUMENTS ARE SUBMITTED. FS 471 & | | | FAC 61G15 AND FBC AMEND. 107.1] | | | | | | 3) A THOROUGH AND COMPLETE PLAN REVIEW CANNOT BE | | | COMPLETED AT THIS TIME DUE TO LACK OF INFORMATION ON | | | THE SUBMITTED PLANS. ADDITIONAL PLAN REVIEW COMMENTS | | | MAY BE GENERATED WHEN MORE INFORMATION IS PROVIDED. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2021-09-21 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-09-21 |
Time |
16:05 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-09-21 |
Time |
16:05 |
Sent To |
|
|
| Notes |
| 2021-09-21 16:39:29 | PLAN | | | REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THE LOCATION OF THE PROJECT IS TOO VAGUE. SUBMIT | | | ADDITIONAL INFORMATION TO SPECIFY THE EXACT LOCATION OF | | | WHERE THE SHUTTERS WILL BE INSTALLED. PROVIDE | | | ELEVATIONS OF THE BUILDING AND A BUILDING FLOOR PLAN | | | FOR THE LEVEL WHERE THE UNIT IS LOCATED WITH THE | | | SPECIFIC UNIT IDENTIFIED. FBC AMENDMENTS 107.2.1 | | | | | | 2) THIS IS A HIGH RISE BUILDING THAT IS MORE THAN 60 | | | FEET IN HEIGHT. SUBMIT SIGNED AND SEALED DESIGN | | | PRESSURES FROM A FLORIDA LICENSED ENGINEER. SUBMIT | | | REQUIRED COMPONENT AND CLADDING DESIGN PRESSURES FOR | | | THE OPENINGS THAT HAVE BEEN PREPARED BY A FLORIDA | | | LICENSED ENGINEER. THE DOCUMENTS ARE REQUIRED TO BE | | | DIGITALLY SIGNED BY THE ENGINEER IF SUBMITTED | | | ELECTRONICALLY AND THE ENGINEER'S ORIGINAL HANDWRITTEN | | | SIGNATURE IF PAPER DOCUMENTS ARE SUBMITTED. FS 471 & | | | FAC 61G15 AND FBC AMEND. 107.1 | | | | | | 3) A THOROUGH AND COMPLETE PLAN REVIEW CANNOT BE | | | COMPLETED AT THIS TIME DUE TO LACK OF INFORMATION ON | | | THE SUBMITTED PLANS. ADDITIONAL PLAN REVIEW COMMENTS | | | MAY BE GENERATED WHEN MORE INFORMATION IS PROVIDED. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2021-08-31 |
|
|
Cont ID |
|
| Sent By |
fgiaquin |
Date |
2021-08-31 |
Time |
23:05 |
Rev Time |
0.00 |
| Received By |
fgiaquin |
Date |
2021-08-31 |
Time |
22:14 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
8 |
Status |
P |
Date |
2022-05-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-05-09 |
Time |
14:24 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-05-04 |
Time |
19:23 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
7 |
Status |
N |
Date |
2022-04-08 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-04-08 |
Time |
15:20 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-04-05 |
Time |
07:51 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
6 |
Status |
N |
Date |
2022-04-04 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-04-04 |
Time |
11:27 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-03-28 |
Time |
07:04 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
5 |
Status |
N |
Date |
2022-02-17 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-02-17 |
Time |
14:30 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-01-31 |
Time |
15:10 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2021-12-01 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-12-01 |
Time |
13:18 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-11-15 |
Time |
08:52 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
F |
Date |
2021-11-10 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-11-10 |
Time |
17:07 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-11-04 |
Time |
15:39 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2021-10-12 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-10-12 |
Time |
11:16 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-09-28 |
Time |
09:01 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2021-09-21 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-09-21 |
Time |
16:05 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-08-23 |
Time |
10:05 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
3 |
Status |
P |
Date |
2022-05-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-05-09 |
Time |
13:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-05-09 |
Time |
13:05 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2022-04-08 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-04-08 |
Time |
15:20 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-04-08 |
Time |
15:20 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2022-02-14 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2022-02-14 |
Time |
10:26 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2022-02-14 |
Time |
10:26 |
Sent To |
|
|
| Notes |
|
|