Plan Review Details - Permit 21080593
Plan Review Stops For Permit 21080593
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2021-09-16 Cont ID  
Sent By cthroop Date 2021-09-16 Time 16:33 Rev Time 0.00
Received By cthroop Date 2021-09-16 Time 16:33 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2021-08-28 Cont ID  
Sent By cthroop Date 2021-08-28 Time 08:48 Rev Time 0.00
Received By cthroop Date 2021-08-28 Time 07:33 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2021-08-30 Cont ID  
Sent By jleahy Date 2021-08-30 Time 13:15 Rev Time 0.00
Received By jleahy Date 2021-08-30 Time 13:08 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2021-08-30 Cont ID  
Sent By lcrespo Date 2021-08-30 Time 08:03 Rev Time 0.00
Received By lcrespo Date 2021-08-30 Time 08:03 Sent To  
Notes
2021-08-30 08:04:10GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR
 FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS TO THE FBC
 SEC. 105.1.
  

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2021-09-07 Cont ID  
Sent By fmittner Date 2021-09-07 Time 08:45 Rev Time 0.00
Received By fmittner Date 2021-09-07 Time 08:45 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-09-16 Cont ID  
Sent By cthroop Date 2021-09-16 Time 16:34 Rev Time 0.00
Received By cthroop Date 2021-09-08 Time 12:17 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-09-08 Cont ID  
Sent By lmarchan Date 2021-09-08 Time 10:04 Rev Time 0.00
Received By lmarchan Date 2021-08-20 Time 15:08 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2021-09-16 Cont ID  
Sent By cthroop Date 2021-09-16 Time 16:33 Rev Time 0.00
Received By cthroop Date 2021-09-16 Time 16:33 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-08-28 Cont ID  
Sent By cthroop Date 2021-08-28 Time 08:46 Rev Time 0.00
Received By cthroop Date 2021-08-28 Time 07:33 Sent To  
Notes
2021-08-28 08:48:51SIGNATURE REVIEW
  
 CHRISTOPHER S. THROOP, C.B.O., CFM
 PLANS EXAMINER II PX3169/RPX306
 INSPECTOR BN4338
 BUILDING OFFICIAL BU1635
 ASFPM CERTIFIED FLOODPLAIN MANAGER US-21-11935
 DEVELOPMENT SERVICES DEPARTMENT
 CITY OF WEST PALM BEACH
 (561) 805-6726
 [email protected]
  
 CODES IN EFFECT:
 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST
 PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE,
 CHAPTER 1 ADMINISTRATION
 NEC2017
  
 1ST REVIEW:
  
 RE: STRUCTURAL ENGINEER OF RECORD SHALL REVIEW AND
 APPROVE ALL STRUCTURAL PLANS.
  
 ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT
  
 1. DOCUMENTS PREPARED BY AN ARCHITECT OR ENGINEER AND
 SUBMITTED FOR PUBLIC RECORD ARE TO BE SIGNED, SEALED,
 DATED ORIGINALS.
  
 2. EITHER UPLOAD A VALID DIGITALLY SIGNED DOCUMENT OR
 DROP OFF (OR MAIL) ONE PAPER ORIGINAL WITH AN ORIGINAL
 WET SEAL AND SIGNATURE TO:
  
 BUILDING DIVISION, FIRST FLOOR
 CITY OF WEST PALM BEACH
 401 CLEMATIS ST
 WEST PALM BEACH, FL 33401
  

Review Stop Z ZONING
Rev No 1 Status P Date 2021-09-07 Cont ID  
Sent By fmittner Date 2021-09-07 Time 08:47 Rev Time 0.00
Received By fmittner Date 2021-09-07 Time 08:47 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved