Plan Review Details - Permit 21080542
Plan Review Stops For Permit 21080542
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2022-03-21 Cont ID  
Sent By rmcphers Date 2022-03-21 Time 15:07 Rev Time 0.00
Received By rmcphers Date 2022-03-21 Time 15:07 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-09-20 Cont ID  
Sent By rmcphers Date 2021-09-20 Time 10:04 Rev Time 0.00
Received By rmcphers Date 2021-09-20 Time 09:59 Sent To  
Notes
2021-09-20 10:04:53REVISION
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
  
 1) DOOR OUT SWING SHOWN IN THE CORRIDOR BETWEEN THE
 BUILDINGS ON DRAWINGS A1.1, A1.0, A1.0A AND A2.0
 APPEARS TO BLOCK EGRESS PER FBC 1005.7.1 DOORS.
 DOORS, WHEN FULLY OPENED, SHALL NOT REDUCE THE REQUIRED
 WIDTH BY MORE THAN 7 INCHES (178 MM). DOORS IN ANY
 POSITION SHALL NOT REDUCE THE REQUIRED WIDTH BY MORE
 THAN ONE-HALF.
  
 2) WALLS AROUND THE MOP SINK NEED TO COMPLY WITH FBC
 1210.2.2 WALLS AND PARTITIONS.
 WALLS AND PARTITIONS WITHIN 2 FEET (610 MM) OF SERVICE
 SINKS, URINALS AND WATER CLOSETS SHALL HAVE A SMOOTH,
 HARD, NONABSORBENT SURFACE, TO A HEIGHT OF NOT LESS
 THAN 4 FEET (1219 MM) ABOVE THE FLOOR, AND EXCEPT FOR
 STRUCTURAL ELEMENTS, THE MATERIALS USED IN SUCH WALLS
 SHALL BE OF A TYPE THAT IS NOT ADVERSELY AFFECTED BY
 MOISTURE. (DRYWALL IS NOT CONSIDERED A HARD SURFACE)
  
 3) PLEASE PROVIDE THE ENLARGED FLOOR PLAN FOR BUILDING
 "B"
  
  
  
  
  

Review Stop E ELECTRICAL
Rev No 3 Status P Date 2022-06-10 Cont ID  
Sent By jleahy Date 2022-06-10 Time 06:23 Rev Time 0.00
Received By jleahy Date 2022-06-10 Time 06:11 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2022-04-01 Cont ID  
Sent By jleahy Date 2022-04-01 Time 16:30 Rev Time 0.00
Received By jleahy Date 2022-04-01 Time 16:30 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2021-09-24 Cont ID  
Sent By jleahy Date 2021-09-24 Time 10:08 Rev Time 0.00
Received By jleahy Date 2021-09-24 Time 10:08 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2021-08-19 Cont ID  
Sent By pleduc Date 2021-08-19 Time   Rev Time 0.00
Received By pleduc Date 2021-08-19 Time 14:28 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-06-30 Cont ID  
Sent By aoliver Date 2022-06-30 Time 07:54 Rev Time 0.00
Received By aoliver Date 2022-06-02 Time 08:34 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-04-01 Cont ID  
Sent By jleahy Date 2022-04-01 Time 16:30 Rev Time 0.00
Received By jleahy Date 2022-03-08 Time 08:18 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-09-24 Cont ID  
Sent By jleahy Date 2021-09-24 Time 10:08 Rev Time 0.00
Received By jleahy Date 2021-08-18 Time 17:23 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2022-06-15 Cont ID  
Sent By medwards Date 2022-06-15 Time 08:23 Rev Time 0.00
Received By medwards Date 2022-06-15 Time 08:23 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2022-03-21 Cont ID  
Sent By medwards Date 2022-03-21 Time 07:03 Rev Time 0.00
Received By medwards Date 2022-03-21 Time 07:03 Sent To  
Notes
2022-03-21 07:07:53PLEASE REMOVE THE AHU-1 FROM THE ENERGY CALCULATIONS AS
 THIS WILL BE INSTALLED UNDER A SEPARATE PERMIT
 ACCORDING TO SHEET M301 NOTE.
 PLEASE PROVIDE THE OUTDOOR AIR CALCULATIONS FOR THIS
 TENANT SPACE.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2021-08-30 Cont ID  
Sent By medwards Date 2021-08-30 Time 08:07 Rev Time 0.00
Received By medwards Date 2021-08-30 Time 08:07 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status P Date 2022-06-29 Cont ID  
Sent By rwbrown Date 2022-06-29 Time 09:07 Rev Time 0.00
Received By rwbrown Date 2022-06-29 Time 09:07 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2022-03-15 Cont ID  
Sent By jesmith Date 2022-03-15 Time 16:57 Rev Time 0.00
Received By jesmith Date 2022-03-10 Time 14:28 Sent To  
Notes
2022-03-15 16:56:19CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2017 6TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017
 6TH ED, CHAPTER 1
 WPB CCCM=WEST PALM BEACH CROSS-CONNECTION CONTROL
 MANUAL REVISED 2017
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017
 6TH EDITION
 FBC ACC = FLORIDA ACCESSIBILITY CODE 2017 6TH EDITION
 FBC EX = FLORIDA EXISTING BUILDING CODE 2017 6TH
 EDITION
 FBC PL = FLORIDA PLUMBING CODE 2017 6TH EDITION
 FBC FG = FLORIDA FUEL GAS CODE 2017 6TH EDITION
 FAC= FLORIDA ADMINISTRATIVE CODE
 FS = FLORIDA STATUTES
  
 21080542 632 7TH ST
 MASTER PERMIT 19120513 LOT 8B REVISION
  
 2ND REVIEW
 PLUMBING COMMENTS: DENIED
  
 A REVIEW OF MINIMUM PLUMBING FIXTURE REQUIREMENTS AS
 REQUIRED BY FBC ACC IS PART OF THE PLUMBING REVIEW
 PROCESS BUT IS TYPICALLY ADDRESSED ON THE ARCHITECTURAL
 PLANS. ANY COMMENTS CONCERNING THESE REQUIREMENTS MUST
 BE SATISFACTORILY ADDRESSED PRIOR TO A PLUMBING REVIEW
 APPROVAL.
  
  
 1. SECOND REQUEST: PER FBC ACC 211.1, WHERE DRINKING
 FOUNTAINS ARE PROVIDED ON AN EXTERIOR SITE, ON A FLOOR,
 OR WITHIN A SECURED AREA THEY SHALL BE PROVIDED IN
 ACCORDANCE WITH 211. PER 211.1, NO FEWER THAN TWO
 DRINKING FOUNTAINS SHALL BE PROVIDED. ONE DRINKING
 FOUNTAIN SHALL COMPLY WITH 602.1 THROUGH 602.6 AND ONE
 DRINKING FOUNTAIN SHALL COMPLY WITH 602.7.
 EXCEPTION: WHERE A SINGLE DRINKING FOUNTAIN COMPLIES
 WITH 602.1 THROUGH 602.6 AND 602.7, IT SHALL BE
 PERMITTED TO BE SUBSTITUTED FOR TWO SEPARATE DRINKING
 FOUNTAINS.
 TO BE CLEAR, THE SUBMITTED SINGLE DRINKING FOUNTAIN
 WITH A BOTTLE FILLER DOES NOT COMPLY WITH FBC PL 602.4
 (MAXIMUM SPOUT HEIGHT 36 INCHES ABOVE THE FLOOR FOR
 WHEELCHAIR ACCESSIBILITY) AND 602.7 (MINIMUM SPOUT
 HEIGHT 38 INCHES ABOVE THE FLOOR FOR STANDING PERSONS);
 A2.0C/DETAIL 3 SHOWS SPOUT HEIGHT AT 37-1/2 INCHES
 ABOVE THE FLOOR. PER WPB FBC 107.2.1, SCHEDULE AND
 SPECIFY FOR DRINKING FOUNTAIN(S) SHOWING FULL
 COMPLIANCE WITH FBC ACC 602.1 THROUGH 602.7. PLEASE
 CONTACT ROBERT BROWN, BUILDING OFFICIAL AT 561-805-6652
 WITH ANY QUESTION OR CONCERNS.
  
 2.ORIGINAL COMMENT: PER FBC ACC 212.3, HAND SINK SHALL
 COMPLY WITH FBC ACC 606.3 WITH THE FRONT OF THE HIGHER
 OF THE RIM OR COUNTER SURFACE 34 INCHES/2 FEET 10
 INCHES MAXIMUM (NOT 35 INCHES/2 FEET 11 INCHES AS
 SHOWN, SEE PLAN SHEET A2.0C) ABOVE THE FINISH FLOOR OR
 GROUND. ADDITIONALLY SHOW TOE AND KNEE CLEARANCE AND
 CLEAR FLOOR SPACE AS REQUIRED BY FBC ACC 306.2 AND
 306.3.
 NEW COMMENT: PER WPB FBC 107.2.1, PLEASE SHOW THE
 TURNING SPACE IN THE BREAKROOM COMPLYING WITH FBC ACC
 304.3.1 OR 304.3.2. SHOW THAT THE BREAKROOM SINK AND
 CABINET AS DESIGNED WILL NOT INTERFERE WITH THE TURNING
 SPACE.
 NEW COMMENT: REGARDING THE HAND SINK; FBC ACC 804.3.1,
 REQUIRES THE CLEAR FLOOR SPACE TO BE CENTERED ON THE
 KITCHEN WORK SURFACE, WHILE THIS IS DIRECTED AT
 KITCHENS AND KITCHENETTES REQUIRING A FORWARD APPROACH,
 IT APPEARS THAT A PERSON OPERATING A WHEELCHAIR WOULD
 BE HARD PRESSED TO COMFORTABLY ACCESS THE CONTROLS OF
 THE HAND SINK. PLEASE REVIEW FBC ACC 308 AND 309.
 CONSIDER PROVIDING A FORWARD APPROACH WITH KNEE AND TOE
 CLEARANCE.
  
  
 3. SECOND REQUEST: ARCHITECT AND MEP EACH ASSIGNED
 COMMENT TO THE OTHER WITH NO RESOLUTION. PER WPB FBC
 107.2.1, PROVIDE DETAIL AND SPECIFICATION FOR RODENT
 PROOFING OF FLOOR PIPE AND OTHER PLUMBING PENETRATIONS
 THROUGH THE FLOOR. SEE FBC PL 301.1 THROUGH 304.4.
  
 4.SECOND REQUEST: PER WPB FBC 107.2.1, PROVIDE PIPE
 HANGER DETAIL SHOWING HOW PIPING WILL BE HUNG FROM
 WOODEN FLOOR JOISTS AND ROOF RAFTERS WITH A NOTE
 STATING, "HORIZONTAL PIPE SHALL BE SUPPORTED IN
 ACCORDANCE WITH FBC PL TABLE 308.5." DETAIL NOT SHOWN
 ON P7.01 AS NOTED IN RESPONSE.
  
 5.SECOND REQUEST: SEE DETAILS BELOW-WATER HEATER
 SCHEDULE & DETAIL- PROVIDE DETAIL OF WATER HEATER
 SHOWING HEATER W/STORAGE CAPACITY, PIPING INCLUDING CW,
 HW, VALVES (INCLUDING VACUUM RELIEF VALVE IF APPLICABLE
 FBC PL 504.2) , THERMAL EXPANSION CONTROL DEVICE
 (INCLUDING SIZE), T&P DISCHARGE (INCLUDING TERMINATION)
 AND WATER HEATER PAN AND DRAIN (INCLUDING TERMINATION)
 PER WPB FPC 107.2.1; COMPLY WITH FBC PL 607.3, 503.1,
 504.1, 504.4, 504.4.1, 504.5, 504.6, 504.7, 504.7.1 AND
 504.7.2. RE: P701/DETAIL 5; WATER HEATER DETAIL.
 PROVIDE THERMAL EXPANSION DEVICE COMPLYING WITH FBC PL
 607.3
 REGARDING WATER HEATER SCHEDULE AND DETAIL:
 ***A) PER 504.4.1, T&P RELIEF VALVES SHALL BE INSTALLED
 IN THE SHELL OF THE WATER HEATER TANK. TEMPERATURE
 RELIEF VALVES SHALL BE SO LOCATED IN THE TANK AS TO BE
 ACTUATED BY THE WATER IN THE TOP 6 INCHES OF THE TANK
 SERVED.
 ***B) PER WPB FBC 107.2.1, PROVIDE SIZE OF PAN DRAIN,
 AND SPECIFY MATERIAL FOR PAN DRAIN PER FBC PL 504.7.1
 AND 504.7.2. MATERIAL SHALL BE AS REQUIRED BY FBC PL
 605.4.
 ***C) PER WPB FBC 107.2.1, PLEASE AMEND NOTE A IN THE
 EXPANSION TANK SCHEDULE TO NOTE "EXPANSION TANK BE
 CONNECTED TO THE WATER HEATER COLD WATER SUPPLY PIPE AT
 A POINT THAT IS DOWNSTREAM OF ALL CHECK VALVES,
 PRESSURE REDUCING VALVES AND BACKFLOW PREVENTERS",
 COMPLYING WITH FBC PL 607.3.
 ***D) PER WPB FBC 107.2.1, SHOW LOCATION OF SCHEDULED
 EXPANSION TANK. P701/DETAIL 5; WATER HEATER DETAIL.
  
 6.SECOND REQUEST: P701/DETAIL 5; WATER HEATER DETAIL.
 DETAIL INDICATES CONCRETE ANCHORS FOR WALL MOUNTED
 WATER HEATER SUPPORT. A2.0B ENLARGED FLOOR PLANS
 INDICATE METAL FRAMED PARTITIONS, NOT CONCRETE WALLS.
 PER WPB FBC 107.2.1, CLARIFY AND CORRECT AS NECESSARY.
  
 7. NEW COMMENT: WATER HEATER SCHEDULE ON P8.01 NOTES
 DISCHARGE OF PAN DRAIN TO NEAREST FLOOR DRAIN WITH 2
 INCH AIR GAP. WATER HEATER DETAIL ON P7.01 NOTES
 DISCHARGE TO MOP SINK. PER WPB FBC 107.2.1, PLEASE
 CLARIFY AND RECONCILE THE TWO.
  
 8. NEW COMMENT: WATER HEATER SCHEDULE CALLS FOR A.O.
 SMITH MODEL DSE-30A-120V/SGL PH/6KW. PRODUCT DATA DOES
 NOT PROVIDE FOR 120 VOLT POWER CIRCUIT; ADDITIONALLY,
 30 TO 120 GALLON UNITS ARE NOT AVAILABLE WITH LESS THAN
 12.3KW. PER WPB FBC 107.2.1, PLEASE CLARIFY.
  
 9. NEW COMMENT: P601/SANITARY ISOMETRIC; PER FBC PL
 1002.1, PROVIDE A TRAP FOR THE MOP SINK.
  
 10. NEW COMMENT: SEE P401/KEYNOTE 102; PER WPB FBC
 107.2.1, PLEASE PROVIDE DETAILS AND EQUIPMENT SCHEDULE
 FOR RECIRCULATING HOT WATER INCLUDING PUMP AND REQUIRED
 CHECK VALVES, EQUIPMENT VALVES AND CONTROLS. DETAIL
 SHALL BE INTEGRATED WITH WATER HEATER PIPING.
  
 END OF COMMENTS.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS. ALL PLANS TO BE SIGNED
 AND SEALED BY THE DESIGNER AS REQUIRED BY FAC AND FS.
  
 JERALD SMITH
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
 EMAIL [email protected]
 MOBILE 561-246-0882
 PLEASE NOTE THAT I TYPICALLY WORK ON TUESDAYS AND
 THURSDAYS
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2021-09-02 Cont ID  
Sent By jesmith Date 2021-09-02 Time 13:54 Rev Time 0.00
Received By jesmith Date 2022-02-01 Time 14:43 Sent To  
Notes
2021-09-02 13:54:40CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2017 6TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017
 6TH ED, CHAPTER 1
 WPB CCCM=WEST PALM BEACH CROSS-CONNECTION CONTROL
 MANUAL REVISED 2017
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017
 6TH EDITION
 FBC ACC = FLORIDA ACCESSIBILITY CODE 2017 6TH EDITION
 FBC EX = FLORIDA EXISTING BUILDING CODE 2017 6TH
 EDITION
 FBC PL = FLORIDA PLUMBING CODE 2017 6TH EDITION
 FBC FG = FLORIDA FUEL GAS CODE 2017 6TH EDITION
 FAC= FLORIDA ADMINISTRATIVE CODE
 FS = FLORIDA STATUTES
  
 21080542 632 7TH ST
 MASTER PERMIT 19120513 LOT 8B REVISION
  
 1ST REVIEW
 PLUMBING COMMENTS: DENIED
  
  
 A REVIEW OF MINIMUM PLUMBING FIXTURE REQUIREMENTS AS
 REQUIRED BY FBC ACC IS PART OF THE PLUMBING REVIEW
 PROCESS BUT IS TYPICALLY ADDRESSED ON THE ARCHITECTURAL
 PLANS. ANY COMMENTS CONCERNING THESE REQUIREMENTS MUST
 BE SATISFACTORILY ADDRESSED PRIOR TO A PLUMBING REVIEW
 APPROVAL.
  
 1. MASTER PERMIT 19120513 IS FOR THE SHELL CONSTRUCTION
 OF SIDE B WITH FUTURE TENANT IMPROVEMENT TO BE UNDER A
 SEPARATE PERMIT. THE PROVIDED ARCHITECTURAL PLANS
 INDICATE ONLY UNIT B ON LOT 8 IS UNDER CONSIDERATION.
 THE PLUMBING PLANS ADDRESS UNITS A AND B. IF THE REVIEW
 IS TO BE FOR BOTH SIDES A AND B, THEN ARCHITECTURAL
 PAGES ADDRESSING SIDE A AS WELL AS SIDE B SHALL BE
 SUBMITTED. PER WPB FBC 107.2.1, PLEASE CLARIFY.
 TO BE CLEAR, THE FOLLOWING COMMENTS ADDRESS ONLY THE
 SINGLE TENANT SPACE (8B).
  
 2A. A0.0-8B INDICATES SINGLE TENANT OCCUPANCY TYPE B
 BUT DOES NOT PROVIDE THE SQUARE FOOTAGE OR THE
 OCCUPANCY LOAD. THIS IS REQUIRED TO BE ABLE TO
 DETERMINE THE MINIMUM REQUIRED FACILITIES IN FBC PC
 403. PER WPB FBC 107.2.1, PROVIDE THE SAME.
  
 2B. PER WPB FBC 107.2.1, PROVIDE A PLUMBING FIXTURE
 SCHEDULE FOR THE TENANT SPACE NOTING THE REQUIRED
 MINIMUM TOILET FACILITIES AS REQUIRED BY FBC PL 403.3.
  
 3. PER FBC ACC 211.1, WHERE DRINKING FOUNTAINS ARE
 PROVIDED ON AN EXTERIOR SITE, ON A FLOOR, OR WITHIN A
 SECURED AREA THEY SHALL BE PROVIDED IN ACCORDANCE WITH
 211. PER 211.1, NO FEWER THAN TWO DRINKING FOUNTAINS
 SHALL BE PROVIDED. ONE DRINKING FOUNTAIN SHALL COMPLY
 WITH 602.1 THROUGH 602.6 AND ONE DRINKING FOUNTAIN
 SHALL COMPLY WITH 602.7.
 EXCEPTION: WHERE A SINGLE DRINKING FOUNTAIN COMPLIES
 WITH 602.1 THROUGH 602.6 AND 602.7, IT SHALL BE
 PERMITTED TO BE SUBSTITUTED FOR TWO SEPARATE DRINKING
 FOUNTAINS.
 THE SUBMITTED SINGLE DRINKING FOUNTAIN WITH A BOTTLE
 FILLER DOES NOT COMPLY. PER WPB FBC 107.2.1, SCHEDULE
 AND SPECIFY FOR DRINKING FOUNTAIN(S) SHOWING FULL
 COMPLIANCE WITH FBC ACC 602.1 THROUGH 602.7
  
 4. PER FBC ACC 212.3, HAND SINK SHALL COMPLY WITH FBC
 ACC 606.3 WITH THE FRONT OF THE HIGHER OF THE RIM OR
 COUNTER SURFACE 34 INCHES/2 FEET 10 INCHES MAXIMUM (NOT
 35 INCHES/2 FEET 11 INCHES AS SHOWN, SEE PLAN SHEET
 A2.0C) ABOVE THE FINISH FLOOR OR GROUND. ADDITIONALLY
 SHOW TOE AND KNEE CLEARANCE AND CLEAR FLOOR SPACE AS
 REQUIRED BY FBC ACC 306.2 AND 306.3
  
 5. PER WPB FBC 107.2.1, SHOW PROVIDE WALL FINISH FOR
 THE MOP SINK SHOWING COMPLIANCE WITH FBC PL 310.3 AND
 FBC 1210.2.2. WALLS AND PARTITIONS WITHIN 2 FEET (610
 MM) OF SERVICE SINKS, URINALS AND WATER CLOSETS SHALL
 HAVE A SMOOTH, HARD, NONABSORBENT SURFACE, TO A HEIGHT
 OF NOT LESS THAN 4 FEET (1219 MM) ABOVE THE FLOOR, AND
 EXCEPT FOR STRUCTURAL ELEMENTS, THE MATERIALS USED IN
 SUCH WALLS SHALL BE OF A TYPE THAT IS NOT ADVERSELY
 AFFECTED BY MOISTURE. PLEASE NOTE THAT FBC 1210.2.2
 STIPULATES THAT THE MATERIAL BE "HARD." THE INTENT OF
 THIS SECTION IS THAT THE SURROUNDING MATERIAL SHOULD
 NOT BE OF A TYPE THAT IS EASILY DAMAGED SUCH THAT THE
 MATERIAL COULD BECOME ABSORBENT AND THUS, NOT READILY
 CLEANABLE AND SANITIZED. PAINTED DRYWALL, EVEN WHERE
 COATED WITH HIGHLY DURABLE PAINTS SUCH AS EPOXY, DOES
 NOT MEET THE INTENT OF SECTION 1210.2.2. THE TYPICAL
 MATERIALS USED FOR THIS APPLICATION ARE CERAMIC TILE,
 FIBERGLASS REINFORCED PLASTIC (FRP) PANELS, PHENOLIC
 PANELS, LAMINATED PLASTIC PANELS, PAINTED STEEL AND
 STAINLESS STEEL.
  
 6A. PLEASE NOTE THAT PER FBC PL 403.3, CUSTOMERS,
 PATRONS AND VISITORS SHALL BE PROVIDED WITH PUBLIC
 TOILET FACILITIES IN STRUCTURES AND TENANT SPACES
 INTENDED FOR PUBLIC UTILIZATION. THE NUMBER OF PLUMBING
 FIXTURES LOCATED WITHIN THE REQUIRED TOILET FACILITIES
 SHALL BE PROVIDED IN ACCORDANCE WITH SECTION 403 FOR
 ALL USERS. EMPLOYEES SHALL BE PROVIDED WITH TOILET
 FACILITIES IN ALL OCCUPANCIES. EMPLOYEE TOILET
 FACILITIES SHALL BE EITHER SEPARATE OR COMBINED
 EMPLOYEE AND PUBLIC TOILET FACILITIES. EXCEPTION:
 PUBLIC TOILET FACILITIES SHALL NOT BE REQUIRED IN:
 ....OPEN OR ENCLOSED PARKING GARAGES WHERE THERE ARE NO
 PARKING ATTENDANTS.
 ....STRUCTURES AND TENANT SPACES INTENDED FOR QUICK
 TRANSACTIONS, INCLUDING TAKEOUT, PICKUP AND DROP-OFF,
 HAVING A PUBLIC ACCESS AREA LESS THAN OR EQUAL TO 300
 SQUARE FEET (28 M2).
  
 6B. PER FBC PL 403.3, PROVIDE MINIMUM TOILET FACILITIES
 AS REQUIRED BY FBC PL 403.3. IT IS NOTED THAT A FUTURE
 TOILET ROOM IS INDICATED IN THE STORAGE ROOM. PER WPB
 FBC 107.2.1, PROVIDE ROUGH-IN PLUMBING FOR LAVATORY AS
 WELL AS THE WATER CLOSET. INCLUDE IN PLAN VIEW AND
 ISOMETRIC. AS NOTED IN FBC PL CHAPTER 2, DEFINITIONS,
 ROUGH-IN INCLUDES ALL PARTS OF THE PLUMBING SYSTEM THAT
 ARE INSTALLED PRIOR TO THE INSTALLATION OF FIXTURES.
 THIS INCLUDES DRAINAGE, WATER SUPPLY, VENT PIPING AND
 THE NECESSARY FIXTURE SUPPORTS (I INTERPRET THIS TO
 INCLUDE BACKING FOR GRAB BARS AS WELL AS FOR POSSIBLE
 WALL HUNG LAVATORIES) AND ANY FIXTURES THAT ARE BUILT
 INTO THE STRUCTURE.
 NOTE: HAND SINK SHALL NOT BE USED TO WET VENT WATER
 CLOSET; FBC PL 912.1.
  
 6C. RE: A2.0C; STORAGE ROOM NOTE 1 STATES GC TO PROVIDE
 ROUGH PLUMBING LINES IN STORAGE ROOM FOR FUTURE WATER
 CLOSET USE. NOTE SHALL BE AMENDED TO STATE GC TO
 PROVIDE ROUGH-IN PLUMBING LINES AND GRAB BAR BACKING IN
 STORAGE ROOM TO MAKE PROVISION FOR FUTURE RESTROOM TO
 BE COMPLETED BY FUTURE TENANT UNDER A SEPARATE PERMIT.
 PER WPB FBC 107.2.1, PROVIDE ACTUAL STORAGE ROOM
 DIMENSIONS, FIXTURE CENTERLINE DIMENSIONS AND GRAB BAR
 BACKING MATERIAL, DIMENSIONS (HORIZONTAL AND VERTICAL)
 TO SHOW COMPLIANCE WITH FBC ACC CHAPTERS 2, 3 AND 6 CAN
 BE ACCOMPLISHED.
  
 7. RE: P000 PLUMBING GENERAL NOTE 30; CODE REFERENCE
 FBC-P 6017.1 IS NOT VALID. REFERENCE SHOULD BE FBC-P
 607.1, 607.1.1 AND 607.1.2; TEXT NOTE SHALL ALSO
 INCLUDE A REFERENCE TO FBC-P 424.3 REQUIRING INDIVIDUAL
 SHOWER AND TUB-SHOWER COMBINATION VALVES SHALL BE
 BALANCED-PRESSURE, THERMOSTATIC OR COMBINATION
 BALANCED-PRESSURE/THERMOSTATIC VALVES THAT CONFORM TO
 THE REQUIREMENTS OF ASSE 1016/ASME A112.1016/CSA
 B125.16 OR ASME A112.18.1/CSA B125.1 AND SHALL BE
 INSTALLED AT THE POINT OF USE. PER WPB FBC 107.2.1,
 PLEASE REVISE THE NOTE ACCORDINGLY.
  
 8. RE: P301 (AND P401) PLUMBING NOTE 8; PER WPB FBC
 107.2.1, PROVIDE SPECIFICATION AND DETAIL FOR NOTED
 FIRE BLOCKING FOR PIPES PASSING THROUGH NOTED WALLS AND
 FLOOR. (NOTED THAT STRUCTURE IS WOOD FRAMED)
  
 9. PER WPB FBC 107.2.1, PROVIDE DETAIL AND
 SPECIFICATION FOR RODENT PROOFING OF FLOOR PIPE AND
 OTHER PLUMBING PENETRATIONS THROUGH THE FLOOR. SEE FBC
 PL 301.1 THROUGH 304.4.
  
 10. PER WPB FBC 107.2.1, PROVIDE PIPE HANGER DETAIL
 SHOWING HOW PIPING WILL BE HUNG FROM WOODEN FLOOR
 JOISTS AND ROOF RAFTERS WITH A NOTE STATING,
 "HORIZONTAL PIPE SHALL BE SUPPORTED IN ACCORDANCE WITH
 FBC PL TABLE 308.5."
  
 11. WATER HEATER SCHEDULE & DETAIL- PROVIDE DETAIL OF
 WATER HEATER SHOWING HEATER W/STORAGE CAPACITY, PIPING
 INCLUDING CW, HW, VALVES (INCLUDING VACUUM RELIEF VALVE
 IF APPLICABLE FBC PL 504.2) , THERMAL EXPANSION CONTROL
 DEVICE (INCLUDING SIZE), T&P DISCHARGE (INCLUDING
 TERMINATION) AND WATER HEATER PAN AND DRAIN (INCLUDING
 TERMINATION) PER WPB FPC 107.2.1; COMPLY WITH FBC PL
 607.3, 503.1, 504.1, 504.4, 504.4.1, 504.5, 504.6,
 504.7, 504.7.1 AND 504.7.2. RE: P701/DETAIL 5; WATER
 HEATER DETAIL. PROVIDE THERMAL EXPANSION DEVICE
 COMPLYING WITH FBC PL 607.3
 ...A)EXPANSION TANK IS SCHEDULED WITH INSTRUCTIONS FOR
 INSTALLATION ON P801.
 ...B)PER WPB FBC 107.2.1, PLEASE AMEND NOTE A IN THE
 EXPANSION TANK SCHEDULE TO NOTE ?EXPANSION TANK BE
 CONNECTED TO THE WATER HEATER COLD WATER SUPPLY PIPE AT
 A POINT THAT IS DOWNSTREAM OF ALL CHECK VALVES,
 PRESSURE REDUCING VALVES AND BACKFLOW PREVENTERS?,
 COMPLYING WITH FBC PL 607.3.
 ...C) PER WPB FBC 107.2.1, SHOW LOCATION OF SCHEDULED
 EXPANSION TANK. THIS MAY EASILY BE ACCOMPLISHED BY
 SHOWING IT ON P701/DETAIL 5; WATER HEATER DETAIL.
  
 12. RE: P701/DETAIL 5; WATER HEATER DETAIL. DETAIL
 INDICATES CONCRETE ANCHORS FOR WALL MOUNTED WATER
 HEATER SUPPORT. A2.0B ENLARGED FLOOR PLANS INDICATE
 METAL FRAMED PARTITIONS, NOT CONCRETE WALLS. PER WPB
 FBC 107.2.1, CLARIFY AND CORRECT AS NECESSARY.
  
 13. P701 DETAILS INDICATE CONCRETE SLAB ON GRADE.
 ACTUAL STRUCTURE IS WOOD FRAMED JOISTS AND BEAMS. PER
 WPB FBC 107.2.1, PROVIDE DETAIL(S) FOR INTERIOR
 PENETRATIONS THAT REFLECT THE ACTUAL CONSTRUCTION.
 PLEASE NOTE, ECOS NOTED ON P301 AND P601 ARE SHOWN AS
 FLOOR CLEANOUTS, NOT WALL CLEANOUTS AS INDICATED FOR
 INTERIOR CLEANOUT DETAIL. PER WPB FBC 107.2.1, PROVIDE
 A DETAIL FOR ECO AND INCLUDE IN PLUMBING SCHEDULE. IF
 ECO IS ACTUALLY ROUGH PLUMBING FOR A FUTURE WATER
 CLOSET, THEN PROVIDE A VENT FOR IT. PLEASE NOTE THAT
 THE HAND SINK FOR THE BREAK ROOM DOES NOT CONSTITUTE A
 LEGITIMATE WET VENT AS DETAILED IN FBC PL 912.1 AS IT
 DOES NOT QUALIFY AS A BATHROOM GROUP FIXTURE (SEE FBC
 PL CHAPTER 2, DEFINITIONS). ADDITIONALLY, PROVISIONS
 NEED TO BE MADE FOR THE REQUIRED LAVATORY.
  
  
 END OF COMMENTS.
 A COMPREHENSIVE REVIEW COULD NOT BE ACCOMPLISHED AT
 THIS TIME. PLEASE RESUBMIT CLEARLY LEGIBLE PLANS AND A
 RESPONSE NARRATIVE ADDRESSING THE GAS/PLUMBING COMMENTS
 FROM THE PRIOR REVIEW.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS. ALL PLANS TO BE SIGNED
 AND SEALED BY THE DESIGNER AS REQUIRED BY FAC AND FS.
  
 JERALD SMITH
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
 EMAIL [email protected]
 MOBILE 561-246-0882
 PLEASE NOTE THAT I TYPICALLY WORK ON TUESDAYS AND
 THURSDAYS
  
 21080542 632 7TH ST
 MASTER PERMIT 19120513 LOT 8B REVISION
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2022-06-29 Cont ID  
Sent By rwbrown Date 2022-06-29 Time 09:10 Rev Time 0.00
Received By rwbrown Date 2022-06-29 Time 09:10 Sent To  
Notes
2022-06-10 06:24:31ELECTRICAL SIGNATURE IS APPROVED JLEAHY

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-04-01 Cont ID  
Sent By jleahy Date 2022-04-01 Time 16:30 Rev Time 0.00
Received By jleahy Date 2022-04-01 Time 16:30 Sent To  
Notes
2022-03-21 15:09:25ARCHITECTURAL PLAN SIGNATURES OK - RMCP
2022-03-10 14:27:44SIGNATURES FOR PLUMBING: SELECTED CERTIFICATE HAS
 ERRORS; NOT TIME VALID. CORRECTIONS NEEDED. JS

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2021-08-30 Cont ID  
Sent By medwards Date 2021-08-30 Time 08:09 Rev Time 0.00
Received By medwards Date 2021-08-30 Time 08:09 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status N Date 2021-09-20 Cont ID  
Sent By rthermid Date 2021-09-20 Time   Rev Time  
Received By rthermid Date 2021-09-20 Time   Sent To I
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved