Plan Review Details - Permit 21071641
Plan Review Stops For Permit 21071641
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status P Date 2021-08-03 Cont ID  
Sent By cthroop Date 2021-08-03 Time 11:25 Rev Time 0.00
Received By cthroop Date 2021-08-02 Time 16:54 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2021-08-03 Cont ID  
Sent By cthroop Date 2021-08-03 Time 12:22 Rev Time 0.00
Received By cthroop Date 2021-08-02 Time 16:55 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2021-08-11 Cont ID  
Sent By jleahy Date 2021-08-11 Time 11:07 Rev Time 0.00
Received By jleahy Date 2021-08-11 Time 11:07 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2021-08-04 Cont ID  
Sent By jleahy Date 2021-08-04 Time 12:15 Rev Time 0.00
Received By jleahy Date 2021-08-04 Time 12:14 Sent To  
Notes
2021-08-04 12:19:24CITY REQUIRES AN ELECTRICAL PERMIT FOR A DEMOLITION
 PROJECT, JLEAHY
  
 ELECTRICAL PLAN REVIEW NEEDS AN ELECTRICAL PERMIT
 APPLICATION FOR APPROVAL. PLEASE EMAIL THE ELECTRICAL
 PERMIT APPLICATION TO [email protected] AND CC
 [email protected] AND [email protected] SO WE RECEIVE IT
 ALSO. WHEN THIS EMAIL IS RECEIVED ONE OF THE REVIEWERS
 WILL APPROVE THE PLAN REVIEW. THE ORIGINAL PERMIT
 APPLICATION MUST BE SUBMITTED WHEN THE PERMIT IS PICKED
 UP.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-08-04 Cont ID  
Sent By jleahy Date 2021-08-04 Time 12:20 Rev Time 0.00
Received By jleahy Date 2021-08-02 Time 07:16 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status N Date 2021-08-04 Cont ID  
Sent By medwards Date 2021-08-04 Time 09:23 Rev Time 0.00
Received By medwards Date 2021-08-04 Time 09:23 Sent To  
Notes
***NONE***

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 1 Status N Date 2021-08-03 Cont ID  
Sent By cthroop Date 2021-08-03 Time 11:26 Rev Time 0.00
Received By cthroop Date 2021-08-02 Time 16:55 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2021-08-04 Cont ID  
Sent By lcrespo Date 2021-08-04 Time 08:52 Rev Time 0.00
Received By lcrespo Date 2021-08-04 Time 08:52 Sent To  
Notes
2021-08-04 08:53:0308/04/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status N Date 2021-08-03 Cont ID  
Sent By cthroop Date 2021-08-03 Time 11:27 Rev Time 0.00
Received By cthroop Date 2021-08-02 Time 16:55 Sent To  
Notes
***NONE***