Plan Review Details - Permit 21071348
Plan Review Stops For Permit 21071348
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status P Date 2021-08-11 Cont ID  
Sent By rmcphers Date 2021-08-11 Time 11:43 Rev Time 0.00
Received By rmcphers Date 2021-08-11 Time 11:43 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2021-10-21 Cont ID  
Sent By rmcphers Date 2021-10-21 Time 12:55 Rev Time 0.00
Received By rmcphers Date 2021-10-21 Time 12:55 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2021-09-17 Cont ID  
Sent By rmcphers Date 2021-09-17 Time 07:59 Rev Time 0.00
Received By rmcphers Date 2021-09-17 Time 07:59 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2021-08-26 Cont ID  
Sent By rmcphers Date 2021-08-26 Time 13:49 Rev Time 0.00
Received By rmcphers Date 2021-08-26 Time 13:49 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2021-08-11 Cont ID  
Sent By rmcphers Date 2021-08-11 Time 11:43 Rev Time 0.00
Received By rmcphers Date 2021-08-11 Time 11:43 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 4 Status P Date 2021-10-21 Cont ID  
Sent By fgiaquin Date 2021-10-21 Time 11:55 Rev Time 0.00
Received By fgiaquin Date 2021-10-20 Time 21:29 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 3 Status F Date 2021-09-02 Cont ID  
Sent By fgiaquin Date 2021-09-02 Time 20:11 Rev Time 0.00
Received By fgiaquin Date 2021-09-02 Time 19:05 Sent To  
Notes
2021-09-02 20:11:31NO ELECTRICAL PLAN SUBMITTED ONLY A SCOPE OF WORK.
 SUBMIT ELECTRICAL PLAN SHOWING LOCATIONS OF ALL WORK TO
 BE DONE WITH INDUSTRY STANDARD ELECTRICAL SYMBOLS

Review Stop E ELECTRICAL
Rev No 2 Status F Date 2021-08-31 Cont ID  
Sent By fgiaquin Date 2021-08-31 Time 20:15 Rev Time 0.00
Received By fgiaquin Date 2021-08-31 Time 19:22 Sent To  
Notes
2021-08-31 20:15:07ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 1. PROVIDE ELECTRICAL PLAN FOR REVIEW USING INDUSTRY
 STANDARD SYMBOLS FOR ELECTRICAL DEVICES. ELECTRICAL
 PLAN MUST BE SIGNED AND SEALED BY DESGIN PROFESSIONAL
 OR SIGNED BY ELECTRICAL CONTRACTOR QUALIFIER. SHOW
 LOCATIONS OF ALL PROPOSED WORK. PLAN PROVIDED IS
 INSUFFICENT AND ONLY DESCRIBES WORK BRIEFLY UNDER THE
 "SCOPE OF WORK"BUT SHOWS NO LOCATIONS OF WORK. FBC
 107.2.1
  
 END OF COMMENTS.
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
 CODES IN EFFECT:
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 FBC = FLORIDA BUILDING CODE 2020 7TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA
 BUILDING CODE 2020 7TH ED.
 FBC EB = FLORIDA BUILDING CODE EXISTING BUILDING 2020
 7TH EDITION
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2020
 7TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2020 7TH EDITION
 NEC = NFPA 70 2017 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 V/R,
  
 FRANK GIAQUINTO III
 ELECTRICAL INSPECTOR
 ELECTRICAL PLANS EXAMINER
 CITY OF WEST PALM BEACH
 [email protected]
 CELL: 561-805-6744
  
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2021-08-06 Cont ID  
Sent By fgiaquin Date 2021-08-06 Time 23:28 Rev Time 0.00
Received By fgiaquin Date 2021-08-06 Time 22:44 Sent To  
Notes
2021-08-06 23:28:45ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 1. PROVIDE ELECTRICAL PLAN FOR REVIEW, SIGNED AND
 SEALED BY A LICENSED DESIGN PROFESSIONAL OR SIGNED BY
 THE ELECTRICAL CONTRACTOR QUALIFIER FS 471.003(2)(H);
 471.025; WPB FBC 107.2.1, 107.3.5
  
 END OF COMMENTS.
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
 CODES IN EFFECT:
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 FBC = FLORIDA BUILDING CODE 2020 7TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA
 BUILDING CODE 2020 7TH ED.
 FBC EB = FLORIDA BUILDING CODE EXISTING BUILDING 2020
 7TH EDITION
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2020
 7TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2020 7TH EDITION
 NEC = NFPA 70 2017 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 V/R,
  
 FRANK GIAQUINTO III
 ELECTRICAL INSPECTOR
 ELECTRICAL PLANS EXAMINER
 CITY OF WEST PALM BEACH
 [email protected]
 CELL: 561-805-6744
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 4 Status P Date 2021-10-22 Cont ID  
Sent By cwalker Date 2021-10-22 Time   Rev Time 0.00
Received By cwalker Date   Time   Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 2021-09-03 Cont ID  
Sent By cwalker Date 2021-09-03 Time   Rev Time 0.00
Received By cwalker Date   Time   Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2021-08-24 Cont ID  
Sent By cwalker Date 2021-08-24 Time   Rev Time 0.00
Received By cwalker Date   Time   Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2021-07-28 Cont ID  
Sent By cwalker Date 2021-07-28 Time   Rev Time  
Received By cwalker Date   Time   Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date 2021-11-17 Cont ID  
Sent By mpeterso Date 2021-11-17 Time 14:07 Rev Time 0.00
Received By mpeterso Date 2021-11-17 Time 14:06 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2021-11-16 Cont ID  
Sent By mpeterso Date 2021-11-16 Time 11:37 Rev Time 0.00
Received By mpeterso Date 2021-11-17 Time 14:06 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2021-11-01 Cont ID  
Sent By mpeterso Date 2021-11-01 Time 11:39 Rev Time 0.00
Received By mpeterso Date 2021-11-01 Time 11:39 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2021-10-25 Cont ID  
Sent By rmcphers Date 2021-10-25 Time 07:34 Rev Time 0.00
Received By medwards Date 2021-09-30 Time 10:45 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2021-09-20 Cont ID  
Sent By lcrespo Date 2021-09-20 Time 07:48 Rev Time 0.00
Received By lcrespo Date 2021-09-02 Time 07:13 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-08-31 Cont ID  
Sent By fgiaquin Date 2021-08-31 Time 20:15 Rev Time 0.00
Received By fgiaquin Date 2021-08-19 Time 14:47 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-08-11 Cont ID  
Sent By rmcphers Date 2021-08-11 Time 11:43 Rev Time 0.00
Received By rmcphers Date 2021-07-27 Time 13:50 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2021-10-25 Cont ID  
Sent By medwards Date 2021-10-25 Time 07:33 Rev Time 0.00
Received By medwards Date 2021-10-25 Time 07:32 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2021-08-24 Cont ID  
Sent By medwards Date 2021-08-24 Time 15:48 Rev Time 0.00
Received By medwards Date 2021-08-24 Time 15:47 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2021-08-09 Cont ID  
Sent By medwards Date 2021-08-09 Time 16:57 Rev Time 0.00
Received By medwards Date 2021-08-09 Time 16:57 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 4 Status P Date 2021-10-14 Cont ID  
Sent By lcrespo Date 2021-10-14 Time 10:46 Rev Time 0.00
Received By lcrespo Date 2021-10-14 Time 10:33 Sent To  
Notes
2021-10-14 10:47:3610/14/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop P PLUMBING
Rev No 3 Status P Date 2021-09-20 Cont ID  
Sent By lcrespo Date 2021-09-20 Time 07:47 Rev Time 0.00
Received By lcrespo Date 2021-09-20 Time 07:47 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2021-08-26 Cont ID  
Sent By lcrespo Date 2021-08-26 Time 17:02 Rev Time 0.00
Received By lcrespo Date 2021-08-26 Time 16:58 Sent To  
Notes
2021-08-26 17:03:0808/26/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop P PLUMBING
Rev No 1 Status P Date 2021-08-04 Cont ID  
Sent By lcrespo Date 2021-08-04 Time 19:56 Rev Time 0.00
Received By lcrespo Date 2021-08-04 Time 19:48 Sent To  
Notes
2021-08-04 19:56:5508/04/21 REVIEWED FOR CODE COMPLIANCE (GAS)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 7 Status P Date 2021-11-17 Cont ID  
Sent By mpeterso Date 2021-11-17 Time 14:03 Rev Time 0.00
Received By mpeterso Date 2021-11-17 Time 14:03 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 6 Status F Date 2021-11-16 Cont ID  
Sent By mpeterso Date 2021-11-16 Time 11:21 Rev Time 0.00
Received By mpeterso Date 2021-11-17 Time 14:02 Sent To  
Notes
2021-11-16 11:36:546TH FAILED SIGNATURE REVIEW
  
 THE ONLY DRAWINGS PASSED IN THIS REVIEW ARE DRAWINGS
 LABLED "E1" AND "F1"
 ALL OTHER DRAWINGS APPEAR TO BE COPIES OF DIGITAL SEAL
 AND SIGNATURE OF THE ENGINEER OF RECORD
 THE DOCUMENTS AND DRAWINGS UPLOADED TO PTOJECT DOX ARE
 NOT LABELED CORRECTLY. ALSO THERE ARE MULTIPLE COPIES
 OF THE SAME DRAWINGS
 PLEASE CORRECT THESE ISSUES AS OUTLINED BELOW
  
 FS471/FS481 DOCUMENTS PREPARED BY AN ARCHITECT OR
 ENGINEER AND SUBMITTED FOR PUBLIC RECORD ARE TO BE
 SIGNED, SEALED, DATED ORIGINALS OR DIGITALLY SEALED AND
 SIGNED.
  
 EITHER UPLOAD A DIGITALLY OR ELECTRONICALLY SIGNED PLAN
 TO THE SIGNATURE FOLDER WITH YOUR RESUBMITTAL (IF
 APPLICABLE) AND COMPLETE THE UPLOAD TASK IN PROJECTDOX,
 OR YOU CAN SUBMIT ONE ORIGINAL SIGNED AND SEALED PAPER
 ORIGINAL WITH A WET SIGNATURE TO THE BUILDING DIVISION.
 SIGNATURE DOCUMENTS ARE TYPICALLY REVIEWED WITHIN TWO
 BUSINESS DAYS AFTER SUBMITTAL; DIGITALLY SIGNED
 DOCUMENTS ARE PREFERRED.
  
 PLEASE EMAIL [email protected] AND CC TO
 [email protected]
  
 MICHAEL PETERSON
 ELECTRICAL PLANS EXAMINER
 [email protected]
 561-805-6746
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 5 Status F Date 2021-11-01 Cont ID  
Sent By mpeterso Date 2021-11-01 Time 11:34 Rev Time 0.00
Received By mpeterso Date 2021-11-01 Time 11:34 Sent To  
Notes
2021-11-01 11:39:21IT APPEARS THE DRAWINGS LABELED
 001 0 - COVER SHEET.PDF
 002 A1 - FLOOR PLAN & DETAILS.PDF
 005 GN - GENERAL NOTES.PDF
 ARE STILL JUST A COPIES OF A DIGITAL SIGNATURE
  
 PLEASE CORRECT THESE ISSUES BY PROPERLY SIGNING AND
 SEALING THEM AS DESCRIBED BELOW.
  
 FS471/FS481 DOCUMENTS PREPARED BY AN ARCHITECT OR
 ENGINEER AND SUBMITTED FOR PUBLIC RECORD ARE TO BE
 SIGNED, SEALED, DATED ORIGINALS OR DIGITALLY SEALED AND
 SIGNED.
 EITHER UPLOAD A DIGITALLY OR ELECTRONICALLY SIGNED PLAN
 TO THE SIGNATURE FOLDER WITH YOUR RESUBMITTAL (IF
 APPLICABLE) AND COMPLETE THE UPLOAD TASK IN PROJECTDOX,
 OR YOU CAN SUBMIT ONE ORIGINAL SIGNED AND SEALED PAPER
 ORIGINAL WITH A WET SIGNATURE TO THE BUILDING DIVISION.
 SIGNATURE DOCUMENTS ARE TYPICALLY REVIEWED WITHIN TWO
 BUSINESS DAYS AFTER SUBMITTAL; DIGITALLY SIGNED
 DOCUMENTS ARE PREFERRED.
  
 PLEASE EMAIL [email protected] AND CC TO
 [email protected]
  
 MICHAEL PETERSON
 ELECTRICAL PLANS EXAMINER
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status F Date 2021-10-21 Cont ID  
Sent By rmcphers Date 2021-10-21 Time 12:50 Rev Time 0.00
Received By rmcphers Date 2021-10-21 Time 12:50 Sent To  
Notes
2021-10-21 12:52:27SIGNATURE REVIEW
  
 ALL OF THE DRAWINGS IN PROJECTDOX DO NOT SHOW AS
 ELECTRONICALLY SIGNED IN ADOBE READER - SIGNED AND
 SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. - OR -
 IF YOUR ARCHITECT OR ENGINEER DOES NOT HAVE AN
 ELECTRONIC OR DIGITAL SIGNATURE - YOU CAN DROP OFF THE
 ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS TO THE
 FRONT DESK IN THE BUILDING DIVISION AT THE CITY HALL.
  
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status F Date 2021-09-17 Cont ID  
Sent By rmcphers Date 2021-09-17 Time 08:00 Rev Time 0.00
Received By rmcphers Date 2021-09-17 Time 07:59 Sent To  
Notes
2021-09-17 08:00:21SIGNATURE REVIEW
  
 DRAWINGS LABELED
 001 0 - COVER SHEET.PDF
 002 A1 - FLOOR PLAN & DETAILS.PDF
 005 GN - GENERAL NOTES.PDF
 IN PROJECTDOX DO NOT SHOW AS ELECTRONICALLY SIGNED IN
 ADOBE READER - SIGNED AND SEALED DRAWINGS IN PROJECTDOX
 NEED TO BE DIGITALLY/ELECTRONICALLY SIGNED BY THE
 ENGINEER OR ARCHITECT TO BE USED IN ELECTRONIC PLAN
 REVIEW. - OR - IF YOUR ARCHITECT OR ENGINEER DOES NOT
 HAVE AN ELECTRONIC OR DIGITAL SIGNATURE - YOU CAN DROP
 OFF THE ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS
 TO THE FRONT DESK IN THE BUILDING DIVISION AT THE CITY
 HALL.
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2021-08-26 Cont ID  
Sent By rmcphers Date 2021-08-26 Time 13:56 Rev Time 0.00
Received By rmcphers Date 2021-08-26 Time 13:56 Sent To  
Notes
2021-08-26 13:58:58SIGNATURE REVIEW
  
 DRAWINGS LABELED
 001 0 - COVER SHEET.PDF
 002 A1 - FLOOR PLAN & DETAILS.PDF
 005 GN - GENERAL NOTES.PDF
 IN PROJECTDOX DO NOT SHOW AS ELECTRONICALLY SIGNED IN
 ADOBE READER - SIGNED AND SEALED DRAWINGS IN PROJECTDOX
 NEED TO BE DIGITALLY/ELECTRONICALLY SIGNED BY THE
 ENGINEER OR ARCHITECT TO BE USED IN ELECTRONIC PLAN
 REVIEW. - OR - IF YOUR ARCHITECT OR ENGINEER DOES NOT
 HAVE AN ELECTRONIC OR DIGITAL SIGNATURE - YOU CAN DROP
 OFF THE ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS
 TO THE FRONT DESK IN THE BUILDING DIVISION AT THE CITY
 HALL.
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-07-27 Cont ID  
Sent By medwards Date 2021-07-27 Time 14:14 Rev Time 0.00
Received By medwards Date 2021-07-27 Time 14:14 Sent To  
Notes
2021-07-27 14:15:55SHEETS F-1 AND E-1 ORF THE SUBMITTED PAPER DRAWINGS
 MUST HAVE THE DESIGNERS SEAL AND SIGNATURE.
  
 PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved