Plan Review Details - Permit 21070458
Plan Review Stops For Permit 21070458
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2021-07-26 Cont ID  
Sent By mcdouga Date 2021-07-26 Time 13:15 Rev Time 0.00
Received By rmcdouga Date 2021-07-26 Time 13:15 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2021-07-26 Cont ID  
Sent By jleahy Date 2021-07-26 Time 17:53 Rev Time 0.00
Received By jleahy Date 2021-07-26 Time 17:50 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status P Date 2021-08-12 Cont ID  
Sent By lcrespo Date 2021-08-12 Time 17:27 Rev Time 0.00
Received By lcrespo Date 2021-08-12 Time 17:27 Sent To  
Notes
2021-08-12 17:28:3108/12/21 REVIEWED FOR CODE COMPLIANCE (GAS)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2021-07-23 Cont ID  
Sent By lcrespo Date 2021-07-23 Time 17:21 Rev Time 0.00
Received By lcrespo Date 2021-07-23 Time 13:46 Sent To  
Notes
2021-08-12 17:26:1907/23/21 1ST LP GAS REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. SHOW THE DISTANCE OF THE LP TANK FROM THE EXTERIOR
 WALL OF THE STRUCTURE TO THE CONTAINER SURFACE AND FROM
 THE PROPERTY LINE TO THE CONTAINER SURFACE TO COMPLY
 WITH NFPA 58-17 SEC. 6.4.1 & TABLE 6.4.1.1.
  
 2. SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS
 PER THE WPB AMENDMENTS TO THE FBC SEC. 107.2.1
 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 3. REGULATORS INSTALLED OUTDOORS SHALL BE DESIGNED,
 INSTALLED, OR PROTECTED SO THEIR OPERATION WILL NOT BE
 AFFECTED BY THE ELEMENTS. PROVIDE DOCUMENTATION FROM
 THE MANUFACTURER THAT THE REGULATORS ARE APPROVED FOR
 EXTERIOR USE PER THE NFPA 58-17 SEC. 6.10.1.4.
  
 4. LP-GAS CONTAINERS OR SYSTEMS INSTALLED WITHIN 10 FT
 OF PUBLIC VEHICULAR THOROUGHFARES SHALL BE PROVIDED
 WITH A MEANS OF VEHICULAR BARRIER PROTECTION PER THE
 2020 NFPA 58-17 SEC. 6.8.1.2.
  
 5. MANUFACTURES SPECIFICATION FOR THE FIRE PLEASE WERE
 NOT SUBMITTED AS STATED ON PCH-2 PER THE WPB AMENDMENTS
 TO THE FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION
 DOCUMENTS.
  
 6. HORIZONTAL ASME CONTAINERS DESIGNED FOR PERMANENT
 INSTALLATION IN STATIONARY ABOVEGROUND SERVICE SHALL BE
 PLACED ON MASONRY OR OTHER NONCOMBUSTIBLE STRUCTURAL
 SUPPORTS LOCATED ON CONCRETE OR MASONRY FOUNDATIONS
 WITH THE CONTAINER SUPPORTS PER THE NFPA 58-17 SEC.
 6.8.3.1
  
 7. ON SHEET PCH-1;
 A. IT SAYS 100 LBS; WOULD YOU PLEASE PROVIDE THE SIZE
 IN GALLONS AND THE MANUFACTURES SPECIFICATION PER THE
 WPB AMENDMENTS TO THE FBC SEC.107.2.1 INFORMATION ON
 CONSTRUCTION DOCUMENTS?
  
 B. TABLE GIVEN IS FOR NATURAL GAS, AND IT HAS AN LP
 TANK ON THE ISOMETRIC. WOULD YOU PLEASE PROVIDE THE
 CORRECT TABLE PER THE NFPA 58-17?
  
 C. WOULD YOU PLEASE PROVIDE THE CODE REFERENCE EDITION
 OR NFPA USED PER THE WPB AMENDMENTS TO FBC 102.3
 APPLICATION OF REFERENCES.
  
 8. WOULD YOU PLEASE PROVE THE STRAP DOWN METHOD FOR THE
 TANK THAT SHALL BE SECURELY ANCHORED TO WITHSTAND 170
 MPH ULT WIND LOAD PER THE WPB AMENDMENTS TO THE FBC
 SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-08-12 Cont ID  
Sent By lcrespo Date 2021-08-12 Time 17:33 Rev Time 0.00
Received By lcrespo Date 2021-08-04 Time 09:14 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-07-30 Cont ID  
Sent By medwards Date 2021-07-30 Time 08:43 Rev Time 0.00
Received By medwards Date 2021-07-12 Time 09:52 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2021-07-30 Cont ID  
Sent By medwards Date 2021-07-30 Time 08:40 Rev Time 0.00
Received By medwards Date 2021-07-30 Time 08:18 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2021-08-12 Cont ID  
Sent By lcrespo Date 2021-08-12 Time 17:28 Rev Time 0.00
Received By lcrespo Date 2021-08-12 Time 17:28 Sent To  
Notes
2021-08-12 17:41:4708/12/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop P PLUMBING
Rev No 1 Status N Date 2021-08-12 Cont ID  
Sent By lcrespo Date 2021-07-23 Time 17:19 Rev Time 0.00
Received By lcrespo Date 2021-07-23 Time 13:46 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2021-08-12 Cont ID  
Sent By lcrespo Date 2021-08-12 Time 17:33 Rev Time 0.00
Received By lcrespo Date 2021-08-12 Time 17:33 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-07-30 Cont ID  
Sent By medwards Date 2021-07-30 Time 08:41 Rev Time 0.00
Received By medwards Date 2021-07-30 Time 08:41 Sent To  
Notes
2021-07-30 08:42:46THE MEP SHEETS ARE MISSING THE DIGITAL SIGNATURES.
 PLEASE UPLOAD ORIGINAL DIGITALLY SIGNED DRAWINGS OR YOU
 MAY BRING ORIGINAL SIGNED AND SEALED PAPER DRAWINGS TO
 OUR OFFICE.
  
 PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved