Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2021-08-31 Cont ID  
Sent By rrossano Date 2021-08-31 Time   Rev Time 0.00
Received By rrossano Date 2021-08-31 Time   Sent To  
Notes
2021-08-31 13:26:31PASSED WITH PROVISO:
 THERE ARE WATER AND SEWER LINES IN THE VICINITY OF THIS
 PROJECT. PER CHAPTER 556 OF THE FLORIDA STATE STATUTES,
 YOU MUST CALL 811 FOR UTILITY LOCATES AT LEAST TWO FULL
 BUSINESS DAYS IN ADVANCE OF ANY CONSTRUCTION OR
 DEMOLITION WORK. INFORMATION CAN BE FOUND HERE:
 HTTP://WWW.SUNSHINE811.COM/
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
  
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 [email protected] WWW.WPB.ORG/ENGINEERING
  
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2021-07-19 Cont ID  
Sent By rrossano Date 2021-07-19 Time   Rev Time  
Received By rrossano Date 2021-07-19 Time   Sent To  
Notes
2021-07-19 11:44:58THE PAVER DRIVEWAY AGREEMENT IS A REQUIREMENT IF PAVERS
 ARE USED IN THE RIGHT OF WAY PORTION OF THE DRIVEWAY.
 THE AGREEMENT MUST BE RECORDED AT PALM BEACH COUNTY
 COURTHOUSE - RECORDING DEPT. 4.25. A RECORDED COPY OF
 THIS DOCUMENT SHOULD BE FAXED TO (561) 494-1116.
 ATTENTION: DRIVEWAY REVIEWER. DOCUMENT NEEDS TO BE
 RECORDED PRIOR TO FINAL SIGN OFF. FOR A PDF COPY OF THE
 PAVER DRIVEWAY AGREEMENT GO TO: HTTPS://WWW.WPB.ORG/HOM
 E/SHOWPUBLISHEDDOCUMENT/3298/637523652570000000
  
 TOTAL COMBINED WIDTH OF DRIVEWAYS AT RIGHT OF WAY SHALL
 NOT EXCEED 20 FT. PLUS 3 FT. FLARES. PLEASE SHOW
 DIMENSIONS OF PROPOSED WIDTHS OF DRIVEWAYS.
  
 3 FT. SETBACK OF PROPOSED DRIVEWAYS FROM ADJACENT
 PROPERTY LINES MUST BE MAINTAINED. PLEASE SHOW ON
 DRAWING.
  
  
 THANKS,
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR, WEST PALM BEACH, FL
 33401
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-09-01 Cont ID  
Sent By lmarchan Date 2021-09-01 Time 14:11 Rev Time 0.00
Received By lmarchan Date 2021-08-16 Time 10:34 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-07-23 Cont ID  
Sent By rmcphers Date 2021-07-23 Time 13:23 Rev Time 0.00
Received By rmcphers Date 2021-06-30 Time 11:00 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2021-09-01 Cont ID  
Sent By kalexand Date 2021-09-01 Time 11:50 Rev Time 0.00
Received By kalexand Date 2021-09-01 Time 11:50 Sent To I
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2021-07-22 Cont ID  
Sent By kalexand Date 2021-07-22 Time 13:22 Rev Time 0.00
Received By kalexand Date 2021-07-22 Time 13:22 Sent To I
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved