Plan Review Details - Permit 21041680
Plan Review Stops For Permit 21041680
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2021-07-06 Cont ID  
Sent By rmcdouga Date 2021-07-06 Time 08:23 Rev Time 0.00
Received By rmcdouga Date 2021-07-06 Time 08:23 Sent To  
Notes
2021-07-06 08:26:28PLAN
 REVIEW COMMENTS
  
 2ND REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING / THE PREVIOUS REVIEW COMMENTS HAVE
 NOT BEEN ADDRESSED
  
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) NOT COMPLIED. PROVIDE A FLOOR PLAN SHOWING THE
 LOCATION OF THE PROPOSED WORK. PLANS SHOULD BE
 DIMENSIONED AND DRAWN TO A MINIMUM 1/8" PER FOOT SCALE.
 SPECIFY THE SCOPE OF WORK ON THE PLANS AND CLEARLY
 INDICATE THE AREAS THAT THE WORK WILL BE PERFORMED. FBC
 AMENDMENTS 107.2.1 & 107.2.1.3
  
 2) NOT COMPLIED. FBC AMENDMENTS 107.2.1 - INFORMATION
 ON CONSTRUCTION DOCUMENTS. ALL INFORMATION, DRAWINGS,
 SPECIFICATIONS AND ACCOMPANYING DATA SHALL BEAR THE
 NAME AND SIGNATURE OF THE PERSON RESPONSIBLE FOR THE
 DESIGN.
  
 3) NOT COMPLIED. THE VALUATION FOR THE PROJECT APPEARS
 TO BE LOW. PROVIDE A COPY OF THE CONTRACT TO VERIFY THE
 VALUATION OF THIS PROJECT. FBC AMENDMENTS 109.3
 BUILDING PERMIT VALUATION. FOR PERMITTING PURPOSES,
 VALUATION OF BUILDINGS AND SYSTEMS SHALL BE TOTAL
 REPLACEMENT VALUE TO INCLUDE STRUCTURAL, ELECTRIC,
 PLUMBING, MECHANICAL, INTERIOR FINISH, RELATIVE SITE
 WORK, ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS,
 OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE.
 VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED
 DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES
 (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-05-26 Cont ID  
Sent By rmcdouga Date 2021-05-26 Time 08:38 Rev Time 0.00
Received By rmcdouga Date 2021-05-26 Time 08:38 Sent To  
Notes
2021-05-26 08:54:58PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) PROVIDE A FLOOR PLAN SHOWING THE LOCATION OF THE
 PROPOSED WORK. PLANS SHOULD BE DIMENSIONED AND DRAWN TO
 A MINIMUM 1/8" PER FOOT SCALE. SPECIFY THE SCOPE OF
 WORK ON THE PLANS AND CLEARLY INDICATE THE AREAS THAT
 THE WORK WILL BE PERFORMED. FBC AMENDMENTS 107.2.1 &
 107.2.1.3
  
 2) FBC AMENDMENTS 107.2.1 - INFORMATION ON CONSTRUCTION
 DOCUMENTS. ALL INFORMATION, DRAWINGS, SPECIFICATIONS
 AND ACCOMPANYING DATA SHALL BEAR THE NAME AND SIGNATURE
 OF THE PERSON RESPONSIBLE FOR THE DESIGN.
  
 3) THE VALUATION FOR THE PROJECT APPEARS TO BE LOW.
 PROVIDE A COPY OF THE CONTRACT TO VERIFY THE VALUATION
 OF THIS PROJECT. FBC AMENDMENTS 109.3 BUILDING PERMIT
 VALUATION. FOR PERMITTING PURPOSES, VALUATION OF
 BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT VALUE
 TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, MECHANICAL,
 INTERIOR FINISH, RELATIVE SITE WORK, ARCHITECTURAL AND
 DESIGN FEES, MARKETING COSTS, OVERHEAD AND PROFIT;
 EXCLUDING ONLY LAND VALUE. VALUATION REFERENCES MAY
 INCLUDE THE LATEST PUBLISHED DATA OF NATIONAL
 CONSTRUCTION COST ANALYSIS SERVICES (MARSHALL-SWIFT,
 MEANS, ETC.), AS PUBLISHED BY INTERNATIONAL CODE
 CONGRESS. FINAL BUILDING PERMIT VALUATION SHALL BE SET
 BY THE BUILDING OFFICIAL.
  
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-07-06 Cont ID  
Sent By rmcdouga Date 2021-07-06 Time 08:27 Rev Time 0.00
Received By rmcdouga Date 2021-06-28 Time 10:00 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-05-26 Cont ID  
Sent By rmcdouga Date 2021-05-26 Time 08:55 Rev Time 0.00
Received By rmcdouga Date 2021-05-05 Time 16:13 Sent To  
Notes
***NONE***

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 1 Status F Date 2021-07-05 Cont ID  
Sent By shill Date 2021-07-05 Time 15:46 Rev Time 0.00
Received By shill Date 2021-07-05 Time 15:46 Sent To  
Notes
2021-07-05 15:47:56****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
  
 1. FBC R 322, PROVIDE A DETAILED COST BREAKDOWN FOR
 THIS PROJECT. A SUBSTANTIAL IMPROVEMENT DETERMINATION
 MUST BE MADE FOR THIS PROJECT AS IT IS LOCATED IN A
 SFHA. PROVIDE A COPY OF THE ELEVATION CERTIFICATE FOR
 THIS PROJECT.
  
  

Review Stop P PLUMBING
Rev No 2 Status P Date 2021-07-02 Cont ID  
Sent By ccole Date 2021-07-02 Time 18:54 Rev Time 0.00
Received By ccole Date 2021-07-02 Time 18:54 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2021-05-11 Cont ID  
Sent By ccole Date 2021-05-11 Time 16:19 Rev Time 0.00
Received By ccole Date 2021-05-11 Time 13:51 Sent To  
Notes
2021-05-11 16:19:531ST REVIEW FBC-2020 RES.
 PERMIT- 21041680
 5/11/2021
  
 CODES IN EFFECT:
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE 7TH EDITION
 2020
 FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020
 FBC M- FLORIDA MECHANICAL CODE 7TH EDITION 2020
 FBC EC- FLORIDA ENERGY CONSERVATION CODE 7TH EDITION
 2020
 FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) PLEASE PROVIDE A BASIC PLUMBING FLOOR PLAN SHOWING
 THE LOCATION OF THE BATHROOM ALTERATIONS AND INCLUDE A
 SCOPE OF WORK OUTLINE- SECTION 107.2.1 WPB.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 1 Status P Date 2021-05-25 Cont ID  
Sent By rgathrig Date 2021-05-25 Time 16:15 Rev Time 0.00
Received By rgathrig Date 2021-05-25 Time 16:15 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2021-07-06 Cont ID  
Sent By rmcdouga Date 2021-07-06 Time 08:27 Rev Time 0.00
Received By rmcdouga Date 2021-07-06 Time 08:27 Sent To  
Notes
2021-07-06 08:26:51NO PLANS WERE SUBMITTED. THE SIGNATURE WILL BE
 EVALUATED WHEN THE REQUESTED PLANS HAVE BEEN SUBMITTED.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-05-26 Cont ID  
Sent By rmcdouga Date 2021-05-26 Time 08:39 Rev Time 0.00
Received By rmcdouga Date 2021-05-26 Time 08:39 Sent To  
Notes
2021-05-26 08:56:35NO PLANS WERE SUBMITTED. THE SIGNATURE WILL BE
 EVALUATED WHEN THE REQUESTED PLANS HAVE BEEN SUBMITTED.