Plan Review Details - Permit 21040531
Plan Review Stops For Permit 21040531
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2021-04-23 Cont ID  
Sent By rmcdouga Date 2021-04-23 Time 16:15 Rev Time 0.00
Received By rmcdouga Date 2021-04-23 Time 16:15 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2021-04-25 Cont ID  
Sent By jleahy Date 2021-04-25 Time 16:54 Rev Time 0.00
Received By jleahy Date 2021-04-25 Time 16:49 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2021-04-13 Cont ID  
Sent By lcrespo Date 2021-04-13 Time 09:13 Rev Time 0.00
Received By lcrespo Date 2021-04-13 Time 09:13 Sent To  
Notes
2021-04-13 09:14:37GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR
 FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS TO THE FBC
 SEC. 105.1.
  

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2021-04-20 Cont ID  
Sent By aborngra Date 2021-04-20 Time 10:09 Rev Time 0.00
Received By aborngra Date 2021-04-20 Time 10:09 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-05-13 Cont ID  
Sent By equinone Date 2021-05-13 Time 09:39 Rev Time 0.00
Received By equinone Date 2021-04-12 Time 14:16 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2021-04-13 Cont ID  
Sent By lcrespo Date 2021-04-13 Time 09:50 Rev Time 0.00
Received By lcrespo Date 2021-04-13 Time 09:08 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2021-05-13 Cont ID  
Sent By equinone Date 2021-05-13 Time 11:20 Rev Time 0.00
Received By equinone Date 2021-05-05 Time 11:20 Sent To  
Notes
2021-05-05 11:20:49CUSTOMER UPLOADED ELECTRONIC PLANS WITH ELECTRONIC
 CERTIFICATE TO SIGNATURE FOLDER. 5/13/2021 EQ
  
 ENRIQUE QUINONEZ PE
 ELECTRICAL PLANS EXAMINER
 DEVELOPMENT SERVICES
 CITY OF WEST PALM BEACH
 401 CLEMATIS STREET, 1ST FLOOR
 WEST PALM BEACH, FL 33401
  
 FEEL FREE TO CONTACT ME IF YOU WISH TO DISCUSS,
 561-805-6746.
  
 PAPER DRAWINGS ROUTED TO STORAGE. EQ
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-04-13 Cont ID  
Sent By lcrespo Date 2021-04-13 Time 10:21 Rev Time 0.00
Received By lcrespo Date 2021-04-13 Time 09:50 Sent To  
Notes
2021-04-13 09:51:35SIGNED AND SEALED DRAWINGS NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW - OR -
 IF YOUR ENGINEER DOES NOT HAVE AN ELECTRONIC OR DIGITAL
 SIGNATURE - PLEASE DROP OFF (CITY HALL DROPBOX) THE
 ORIGINAL SIGNED AND SEALED DOCUMENT ALONG WITH A "PLAN
 REVIEW REQUEST FORM" EXPLAINING THE REASON FOR
 SUBMITTING THE DOCUMENT OR DRAWINGS. THE PLAN REVIEW
 REQUEST FORM CAN BE OBTAINED BY EMAILING [email protected] AND
 ASKING FOR THE FORM.

Review Stop Z ZONING
Rev No 1 Status P Date 2021-05-12 Cont ID  
Sent By kalexand Date 2021-05-12 Time 13:43 Rev Time 0.00
Received By kalexand Date 2021-05-12 Time 13:43 Sent To I
Notes
***NONE***