Plan Review Details - Permit 21021229
Plan Review Stops For Permit 21021229
Review Stop E ELECTRICAL
Rev No 1 Status N Date 2021-03-26 Cont ID  
Sent By equinone Date 2021-03-09 Time 16:29 Rev Time 0.00
Received By equinone Date 2021-03-09 Time 16:29 Sent To  
Notes
2021-03-09 16:30:03ELECTRICAL WORK IS ALL LOCATED INSIDE THE SUBSTATION.
 EXEMPTED AS PER FBC 102.2 AND FLORIDA STATUTE 366.02.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-03-09 Cont ID  
Sent By equinone Date 2021-03-09 Time 16:30 Rev Time 0.00
Received By equinone Date 2021-03-05 Time 13:02 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2021-03-08 Cont ID  
Sent By lcrespo Date 2021-03-08 Time 11:24 Rev Time 0.00
Received By lcrespo Date 2021-03-08 Time 11:24 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status N Date 2021-03-09 Cont ID  
Sent By equinone Date 2021-03-09 Time 16:30 Rev Time 0.00
Received By equinone Date 2021-03-09 Time 16:30 Sent To  
Notes
***NONE***