| Plan Review Stops For Permit 21010049 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2021-02-02 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-02-02 |
Time |
10:03 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-02-02 |
Time |
10:02 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2021-01-11 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-01-11 |
Time |
10:12 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-01-11 |
Time |
10:12 |
Sent To |
|
|
| Notes |
| 2021-01-11 10:17:59 | PLAN REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC SEVENTH EDITION (2020) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | THE PLANS REFERENCE THE FBC SIXTH EDITION (2017). THE | | | FBC SEVENTH EDITION (2020) WENT INTO EFFECT ON DECEMBER | | | 31, 2020. ALL NEW PERMITS APPLIED FOR ON OR AFTER THAT | | | DATE ARE REQUIRED TO COMPLY WITH AND REFERENCE THE FBC | | | SEVENTH EDITION (2020). FS CHAPTER 553 | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2021-02-03 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2021-02-03 |
Time |
15:04 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2021-02-03 |
Time |
14:59 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
F |
Date |
2021-01-13 |
|
|
Cont ID |
|
| Sent By |
ppetty |
Date |
2021-01-13 |
Time |
10:51 |
Rev Time |
0.00 |
| Received By |
ppetty |
Date |
2021-01-13 |
Time |
10:45 |
Sent To |
|
|
| Notes |
| 2021-01-13 10:52:43 | PLEASE CORRECT CODE EDITION |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
N |
Date |
2021-02-03 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2021-02-03 |
Time |
16:35 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2021-02-03 |
Time |
16:35 |
Sent To |
|
|
| Notes |
| 2021-01-11 15:16:27 | GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN | | | THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN | | | PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS | | | WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE | | | RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT | | | REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER | | | THE WPB AMENDMENTS TO FBC SEC. 107.2.1. | | | | | | A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR | | | FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS TO THE FBC | | | SEC. 105.1. | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
F |
Date |
2021-02-03 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2021-02-03 |
Time |
16:37 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2021-01-15 |
Time |
17:53 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2021-01-20 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2021-01-20 |
Time |
12:38 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2021-01-08 |
Time |
16:27 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
P |
Date |
2021-02-02 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2021-02-02 |
Time |
11:10 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2021-02-02 |
Time |
11:10 |
Sent To |
|
|
| Notes |
| 2021-02-02 11:11:22 | 02/02/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING) | | | | | | BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE | | | COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN | | | PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES | | | FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, | | | STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT | | | THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK | | | OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM | | | REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES | | | / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO | | | AVOID VOIDING OF THE PERMIT. | | | | | | LUIS A. CRESPO | | | PLUMBING PLAN EXAMINER / INSPECTOR | | | EMAIL: [email protected] OFFICE: 561 805-6720 | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2021-01-11 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2021-01-11 |
Time |
15:16 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2021-01-11 |
Time |
15:16 |
Sent To |
|
|
| Notes |
| 2021-01-11 15:17:33 | 01/11/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING) | | | | | | BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE | | | COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN | | | PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES | | | FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, | | | STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT | | | THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK | | | OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM | | | REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES | | | / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO | | | AVOID VOIDING OF THE PERMIT. | | | | | | LUIS A. CRESPO | | | PLUMBING PLAN EXAMINER / INSPECTOR | | | EMAIL: [email protected] OFFICE: 561 805-6720 | | | |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2021-02-01 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2021-02-01 |
Time |
17:53 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2021-02-01 |
Time |
17:53 |
Sent To |
|
|
| Notes |
| 2021-02-01 17:53:31 | PAPER SUBMITTED 1/15 |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2021-01-11 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2021-01-11 |
Time |
10:13 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2021-01-11 |
Time |
10:13 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2021-01-19 |
|
|
Cont ID |
|
| Sent By |
rthermid |
Date |
2021-01-19 |
Time |
|
Rev Time |
|
| Received By |
rthermid |
Date |
2021-01-19 |
Time |
|
Sent To |
I |
|
| Notes |
|
|