Plan Review Details - Permit 20121179
Plan Review Stops For Permit 20121179
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status P Date 2021-05-27 Cont ID  
Sent By rmcphers Date 2021-05-27 Time 12:36 Rev Time 0.00
Received By rmcphers Date 2021-05-27 Time 12:36 Sent To  
Notes
***NONE***

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2021-01-12 Cont ID  
Sent By rmcphers Date 2021-01-12 Time 13:02 Rev Time 0.00
Received By rmcphers Date 2021-01-12 Time 13:02 Sent To  
Notes
2021-01-12 13:02:34PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING ASBESTOS
 REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2021-09-02 Cont ID  
Sent By rmcphers Date 2021-09-02 Time 16:13 Rev Time 0.00
Received By rmcphers Date 2021-09-02 Time 16:13 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2021-05-27 Cont ID  
Sent By rmcphers Date 2021-05-27 Time 12:34 Rev Time 0.00
Received By rmcphers Date 2021-05-27 Time 12:23 Sent To  
Notes
2021-05-27 12:34:46AC REPLACEMENT
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) PROVIDED PRODUCT APPROVAL (17-1221.35) AND
 (18-0212.09) HAVE BEEN MARKED BY THE STRUCTURAL
 ENGINEER OF RECORD AS NEEDING CORRECTIONS. WILL NEED
 PRODUCT APPROVALS MARKED APPROVED BY THE DESIGNER OF
 RECORD.
 2) PLEASE SEE DRAWING S1.1 NOTES NUMBER 11 - "ALL
 ROOFTOP EQUIPMENT........"
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-01-12 Cont ID  
Sent By rmcphers Date 2021-01-12 Time 12:40 Rev Time 0.00
Received By rmcphers Date 2021-01-12 Time 11:05 Sent To  
Notes
2021-01-12 12:38:44AC REPLACEMENT
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) PROVIDED PRODUCT APPROVAL (19-1205.07) DOES NOT MEET
 THE REQUIRED WIND DESIGN PRESSURES SHOWN ON DRAWING
 S1.1
 2) PLEASE PROVIDE COPIES OF THE PRODUCT APPROVALS
 LISTED ON DRAWING M0.2
 3) PRODUCT APPROVALS MAY BE DEFERRED SUBMITTALS BY
 LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION
 DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE
 PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE
 DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT
 SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE
 TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A
 SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL
 HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE
 REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE
 SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION
 DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL.
 DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE
 SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN
 RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD
 THEM TO THE BUILDING OFFICIAL WITH A NOTATION
 INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE
 BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO
 THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL
 ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED
 SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING
 OFFICIAL.
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2021-05-19 Cont ID  
Sent By jleahy Date 2021-05-19 Time 16:24 Rev Time 0.00
Received By jleahy Date 2021-05-19 Time 16:16 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2021-01-13 Cont ID  
Sent By fgiaquin Date 2021-01-13 Time 20:24 Rev Time 0.00
Received By fgiaquin Date 2021-01-12 Time 22:08 Sent To  
Notes
2021-01-13 20:24:32ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 1.VALUE LOW FOR AMOUNT OF WORK SHOWN. VALUE MUST
 INCLUDE ALL MATERIALS (INCLUDING CUSTOMER SUPPLIED) AND
 LABOR. FBC 109.3
  
 2. ALL FIRE ALARM WORK SHOWN (RELAYS, DUCT DETECTORS,
 ETC) WILL REQUIRE A SEPARATE FIRE ALARM PERMIT.
  
 END OF COMMENTS.
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
 CODES IN EFFECT:
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 FBC = FLORIDA BUILDING CODE 2017 6TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA
 BUILDING CODE 2017 6TH ED.
 FBC EB = FLORIDA BUILDING CODE EXISTING BUILDING 2017
 6TH EDITION
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017
 6TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION
 NEC = NFPA 70 2017 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 V/R,
  
 FRANK GIAQUINTO III
 ELECTRICAL INSPECTOR
 ELECTRICAL PLANS EXAMINER
 CITY OF WEST PALM BEACH
 [email protected]
 CELL: 561-657-1653
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2021-05-11 Cont ID  
Sent By pleduc Date 2021-05-11 Time   Rev Time 0.00
Received By pleduc Date 2021-05-11 Time 14:05 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2021-01-06 Cont ID  
Sent By pleduc Date 2021-01-06 Time   Rev Time 0.00
Received By pleduc Date 2021-01-06 Time 09:37 Sent To  
Notes
2021-01-06 16:16:45FIRE PROVISO:
  
 ANY WORK THAT INVOLVES THE FIRE ALARM OR FIRE SPRINKLER
 SYSTEMS, INCLUDING DEMO AND RECONSTRUCTION,
 SHALL BE DONE UNDER SEPARATE PERMITS AND SHOP DRAWINGS.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2021-09-02 Cont ID  
Sent By rmcphers Date 2021-09-02 Time 16:13 Rev Time 0.00
Received By rmcphers Date 2021-08-23 Time 08:12 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-05-27 Cont ID  
Sent By rmcphers Date 2021-05-27 Time 12:35 Rev Time 0.00
Received By rmcphers Date 2021-05-10 Time 14:10 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-01-13 Cont ID  
Sent By fgiaquin Date 2021-01-13 Time 20:26 Rev Time 0.00
Received By fgiaquin Date 2020-12-30 Time 14:25 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2021-05-14 Cont ID  
Sent By medwards Date 2021-05-14 Time 16:17 Rev Time 0.00
Received By medwards Date 2021-05-14 Time 16:17 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2021-01-08 Cont ID  
Sent By medwards Date 2021-01-08 Time 10:22 Rev Time 0.00
Received By medwards Date 2021-01-08 Time 10:22 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2021-09-02 Cont ID  
Sent By rmcphers Date 2021-09-02 Time 16:13 Rev Time 0.00
Received By rmcphers Date 2021-09-02 Time 16:13 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2021-05-14 Cont ID  
Sent By medwards Date 2021-05-14 Time 16:17 Rev Time 0.00
Received By medwards Date 2021-05-14 Time 16:17 Sent To  
Notes
2021-05-14 16:19:37THE NEW STRUCTURAL SHEETS WERE NOT SUBMITTED IN THIS
 SUBMITTAL. PLEASE PROVIDE DIGITALLY SIGNED AND SEALED
 DRAWINGS.
  
 PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-01-08 Cont ID  
Sent By medwards Date 2021-01-08 Time 10:48 Rev Time 0.00
Received By medwards Date 2021-01-08 Time 10:48 Sent To  
Notes
2021-01-08 10:52:00THE DESIGNER OF THE STRUCTURAL DRAWINGS MUST DIGITALLY
 SIGN THE DRAWINGS. ENGINEERS KURT PENNER AND DENNIS
 HERGENRETHER MUST HAVE THIRD PARTY CERTIFICATION FOR
 THEIR DIGITAL SIGNATURES. WE HAVE SENT NOTIFICATIONS OF
 THIS IN THE PAST FOR BOTH ENGINEERS.
  
 PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
 61G15?23.004 F.A.C.
 (2) A PROFESSIONAL ENGINEER UTILIZING A DIGITAL
 SIGNATURE TO ELECTRONICALLY SIGN AND SEAL ENGINEERING
 PLANS, SPECIFICATIONS, REPORTS OR OTHER DOCUMENTS SHALL
 HAVE THEIR IDENTITY AUTHENTICATED BY A CERTIFICATION
 AUTHORITY AND SHALL ASSURE THAT THE DIGITAL SIGNATURE
 IS: (A) UNIQUE TO THE PERSON USING IT; (B) CAPABLE OF
 VERIFICATION; AS OF NOVEMBER 16, 2020 63 (C) UNDER THE
 SOLE CONTROL OF THE PERSON USING IT; AND, (D) LINKED TO
 A DOCUMENT IN SUCH A MANNER THAT THE DIGITAL SIGNATURE
 AND CORRESPONDINGLY THE DOCUMENT IS INVALIDATED IF ANY
 DATA IN THE DOCUMENT IS CHANGED
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved