Plan Review Details - Permit 20120622
Plan Review Stops For Permit 20120622
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2021-01-25 Cont ID  
Sent By rmcphers Date 2021-01-25 Time 08:34 Rev Time 0.00
Received By rmcphers Date 2021-01-25 Time 08:34 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2021-01-07 Cont ID  
Sent By rmcphers Date 2021-01-07 Time 07:58 Rev Time 0.00
Received By rmcphers Date 2021-01-07 Time 07:57 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-12-30 Cont ID  
Sent By rmcphers Date 2020-12-30 Time 14:34 Rev Time 0.00
Received By rmcphers Date 2020-12-30 Time 14:23 Sent To  
Notes
2020-12-30 14:32:46SITE WALLS
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) SITE PLAN DRAWING NEEDS TO BE SIGNED BY THE
 DESIGNER. IF THE DESIGNER IS AN ARCHITECT OR ENGINEER
 IT NEEDS TO BE SIGNED AND SEALED BY THE DESIGNER.
 2) PLEASE CLARIFY WHICH FENCE/WALLS ARE FOR THIS
 PERMIT.

Review Stop B1 BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2021-01-07 Cont ID  
Sent By rmcphers Date 2021-01-07 Time 07:57 Rev Time 0.00
Received By rmcphers Date 2021-01-07 Time 07:57 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status N Date 2021-01-05 Cont ID  
Sent By jleahy Date 2021-01-05 Time 14:46 Rev Time 0.00
Received By jleahy Date 2021-01-05 Time 14:35 Sent To  
Notes
2021-01-05 14:46:59LIGHTING IS FOR SIGN AND NOT WALL JLEAHY

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2020-12-21 Cont ID  
Sent By pleduc Date 2020-12-21 Time   Rev Time 0.00
Received By pleduc Date 2020-12-21 Time 12:53 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-01-25 Cont ID  
Sent By rmcphers Date 2021-01-25 Time 08:34 Rev Time 0.00
Received By rmcphers Date 2021-01-12 Time 07:59 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-01-08 Cont ID  
Sent By lmarchan Date 2021-01-08 Time 14:00 Rev Time 0.00
Received By lmarchan Date 2020-12-18 Time 10:32 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2021-01-25 Cont ID  
Sent By rmcphers Date 2021-01-25 Time 08:34 Rev Time 0.00
Received By rmcphers Date 2021-01-25 Time 08:34 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-12-30 Cont ID  
Sent By rmcphers Date 2020-12-30 Time 14:34 Rev Time 0.00
Received By rmcphers Date 2020-12-30 Time 14:34 Sent To  
Notes
2020-12-30 14:35:50FOUNDATION DRAWING IS NOT ELECTRONICALLY SIGNED =
 SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW.
 DRAWINGS DO NOT SHOW IN "ADOBE READER" AS
 DIGITALLY/ELECTRONICALLY SIGNED. - OR - IF YOUR
 ARCHITECT OR ENGINEER DOES NOT HAVE AN ELECTRONIC OR
 DIGITAL SIGNATURE - YOU CAN MAIL IN OR DROP OFF THE
 ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS TO THE
 FRONT DESK IN THE BUILDING DEPT. AT THE CITY HALL

Review Stop Z ZONING
Rev No 1 Status P Date 2021-01-08 Cont ID  
Sent By eschneid Date 2021-01-08 Time 11:50 Rev Time 0.25
Received By eschneid Date 2021-01-07 Time 16:48 Sent To  
Notes
***NONE***