Plan Review Details - Permit 20110265
Plan Review Stops For Permit 20110265
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2021-04-27 Cont ID  
Sent By rmcdouga Date 2021-04-27 Time 08:01 Rev Time 0.00
Received By rmcdouga Date 2021-04-27 Time 07:32 Sent To  
Notes
2021-04-27 08:01:18PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) NOT COMPLIED. FBC 107.2.1 - INFORMATION ON
 CONSTRUCTION DOCUMENTS. ALL INFORMATION, DRAWINGS,
 SPECIFICATIONS AND ACCOMPANYING DATA SHALL BEAR THE
 NAME AND SIGNATURE OF THE PERSON RESPONSIBLE FOR THE
 DESIGN.
  
 2) NOT COMPLIED. [ PROVIDE TOTAL INSURANCE REPLACEMENT
 COST. ] THE VALUE OF $300.00 APPEARS TO BE LOW FOR THIS
 PROJECT. FBC 109.3 BUILDING PERMIT VALUATION. FOR
 PERMITTING PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS
 SHALL BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY
 LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST
 PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS
 SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 3) COMPLIED.
  
 4) NOT COMPLIED. PROVIDE THE MANUFACTURE'S
 SPECIFICATIONS AND INSTALLATION REQUIREMENTS WITH
 REQUIRED CLEARANCES, ETC. FBC 107
  
 5) NOT COMPLIED. PROVIDE STRUCTURAL DRAWINGS OF THE
 OUTDOOR KITCHEN. SPECIFY THE FOUNDATION, ALL
 CONSTRUCTION MATERIALS, REINFORCING, CONNECTORS,
 ANCHORS, ETC. FBC 107
  
 6) NOT COMPLIED. SHOW THAT THE PROPOSED STRUCTURE IS
 CAPABLE OF RESISTING THE REQUIRED WINDLOADS. FBC-R301
  
 7) A THOROUGH AND COMPLETE PLAN REVIEW CANNOT BE
 COMPLETED AT THIS TIME DUE TO LACK OF INFORMATION ON
 THE SUBMITTED PLANS. ADDITIONAL PLAN REVIEW COMMENTS
 MAY BE GENERATED WHEN MORE INFORMATION IS PROVIDED.
  
 8) WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A
 RESPONSE LETTER ADDRESSING EACH ITEM ALONG WITH THE
 CITY RE-SUBMITTAL FORM.
  
 9) NEW COMMENT. THIS PROJECT WAS APPLIED FOR BEFORE
 DECEMBER 31, 2020 THE DATE THAT THE 2020 FBC SEVENTH
 EDITION WENT INTO EFFECT. THIS PROJECT IS UNDER THE
 2017 FBC SIXTH EDITION. THE PLANS THAT WERE SUBMITTED
 REFERENCE THE 2020 FBC AND SHOULD BE REFERENCING THE
 2017 FBC. PLEASE CORRECT. FS CHAPTER 553
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-01-06 Cont ID  
Sent By rmcdouga Date 2021-01-06 Time 09:12 Rev Time 0.00
Received By rmcdouga Date 2021-01-06 Time 08:44 Sent To  
Notes
2021-01-06 09:12:23PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) FBC 107.2.1 - INFORMATION ON CONSTRUCTION DOCUMENTS.
 ALL INFORMATION, DRAWINGS, SPECIFICATIONS AND
 ACCOMPANYING DATA SHALL BEAR THE NAME AND SIGNATURE OF
 THE PERSON RESPONSIBLE FOR THE DESIGN.
  
 2) THE VALUE OF $300.00 APPEARS TO BE LOW FOR THIS
 PROJECT. FBC 109.3 BUILDING PERMIT VALUATION. FOR
 PERMITTING PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS
 SHALL BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY
 LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST
 PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS
 SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 3) PROVIDE A SITE PLAN THAT SHOWS THE LOCATION OF THE
 PROPOSED WORK. IF IT IS UNDER A COVERED PORCH, PROVIDE
 DETAILS OF THE PORCH. SHOW WHICH SIDES ARE OPEN, THE
 CEILING HEIGHT, CEILING MATERIAL (COMBUSTIBLE OR NOT),
 ETC. FBC 107
  
 4) PROVIDE THE MANUFACTURE'S SPECIFICATIONS AND
 INSTALLATION REQUIREMENTS WITH REQUIRED CLEARANCES,
 ETC. FBC 107
  
 5) PROVIDE STRUCTURAL DRAWINGS OF THE OUTDOOR KITCHEN.
 SPECIFY THE FOUNDATION, ALL CONSTRUCTION MATERIALS,
 REINFORCING, CONNECTORS, ANCHORS, ETC. FBC 107
  
 6) SHOW THAT THE PROPOSED STRUCTURE IS CAPABLE OF
 RESISTING THE REQUIRED WINDLOADS. FBC-R301
  
 7) A THOROUGH AND COMPLETE PLAN REVIEW CANNOT BE
 COMPLETED AT THIS TIME DUE TO LACK OF INFORMATION ON
 THE SUBMITTED PLANS. ADDITIONAL PLAN REVIEW COMMENTS
 MAY BE GENERATED WHEN MORE INFORMATION IS PROVIDED.
  
 8) WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A
 RESPONSE LETTER ADDRESSING EACH ITEM ALONG WITH THE
 CITY RE-SUBMITTAL FORM.
  
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2021-04-26 Cont ID  
Sent By jleahy Date 2021-04-26 Time 14:55 Rev Time 0.00
Received By jleahy Date 2021-04-26 Time 14:42 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2021-01-05 Cont ID  
Sent By jleahy Date 2021-01-05 Time 14:53 Rev Time 0.00
Received By jleahy Date 2021-01-05 Time 14:48 Sent To  
Notes
2021-01-05 14:53:59PLAN DOES NOT EXPLAIN WHAT THE ELECTRIC IS AND WHAT IT
 IS FOR. PLEASE EXPLAIN.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-04-29 Cont ID  
Sent By lcrespo Date 2021-04-29 Time 10:55 Rev Time 0.00
Received By lcrespo Date 2021-04-21 Time 14:16 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-01-06 Cont ID  
Sent By abelisle Date 2021-01-06 Time 15:25 Rev Time 0.00
Received By lmarchan Date 2020-12-18 Time 13:41 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2021-04-29 Cont ID  
Sent By lcrespo Date 2021-04-29 Time 10:55 Rev Time 0.00
Received By lcrespo Date 2021-04-29 Time 09:18 Sent To  
Notes
2021-04-29 10:52:2804/29/21 2ND PLUMBING REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1) TOTAL JOB COST SEEMS LOW. THE VALUE MUST INCLUDE THE
 COST OF ALL EQUIPMENT, LABOR, AND MATERIALS. PROVIDE
 BONA FIDE SIGNED CONTRACT PER WPB AMENDMENTS TO THE FBC
 109.3.
  
 IF, IN THE OPINION OF THE BUILDING OFFICIAL, THE
 CLAIMED VALUATION OF THE BUILDING, ALTERATION,
 STRUCTURE, ELECTRICAL, GAS, MECHANICAL, OR PLUMBING
 SYSTEMS APPEARS TO BE UNDERESTIMATED ON THE
 APPLICATION, THE PERMIT SHALL BE DENIED UNLESS THE
 APPLICANT CAN SHOW DETAILED, QUANTITY ESTIMATES, AND/OR
 BONA FIDE SIGNED CONTRACTS (EXCLUDING LAND VALUE) TO
 MEET THE APPROVAL OF THE BUILDING OFFICIAL. FOR
 PERMITTING PURPOSES, THE VALUATION OF BUILDINGS AND
 SYSTEMS SHALL BE TOTAL REPLACEMENT VALUE TO INCLUDE
 STRUCTURAL, ELECTRIC, PLUMBING, MECHANICAL, INTERIOR
 FINISH, RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN
 FEES, MARKETING COSTS, OVERHEAD, AND PROFIT, EXCLUDING
 ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE
 LATEST PUBLISHED DATA OF NATIONAL CONSTRUCTION COST
 ANALYSIS SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS
 PUBLISHED BY INTERNATIONAL CODE CONGRESS. THE FINAL
 BUILDING PERMIT VALUATION SHALL BE SET BY THE BUILDING
 OFFICIAL.
  
 2) PLEASE PROVIDE A SOURCE OF HOT WATER AND THE
 LOCATION OF CONNECTION PER THE 2020 FBC SEC. FBC R
 2722.2.
  
 3) IF HOT WATER IS COMING FROM THE MAIN HOUSE AND
 UNDERGROUND NEEDS TO BE INSULATED WITH A MINIMUM R-3
 PER THE 2020 FBC SEC. RE 403.5.3.
  
 4) PLEASE PROVIDE THE SIGNATURE OF ALL INFORMATION,
 DRAWINGS, SPECIFICATIONS, AND ACCOMPANYING DATA THAT
 SHALL BEAR THE PRINTED NAME AND SIGNATURE OF THE PERSON
 RESPONSIBLE FOR THE DESIGN PER THE WPB AMENDMENTS TO
 THE FBC SEC.107.2.1 INFORMATION ON CONSTRUCTION
 DOCUMENTS.
  
 5) THE PLUMBING SCOPE TO BE DONE IS UNCLEAR. PLEASE
 PROVIDE A SANITARY AND WATER ISOMETRIC DRAWING PER THE
 WPB AMEND TO FBC 107.3.5.3 (12) RESIDENTIAL PLUMBING.
  
 WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES.
 A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGES CAN BE FOUND WILL HELP EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2021-01-06 Cont ID  
Sent By abelisle Date 2021-01-06 Time 15:25 Rev Time 0.00
Received By abelisle Date 2021-01-06 Time 14:17 Sent To I
Notes
2021-01-06 15:25:041ST REVIEW FBC-2017 PLUMBING
 PERMIT-20110265
 1/6/2021
  
 CODES IN EFFECT:
 FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2017
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION
 2017
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) TOTAL JOB COST SEEMS LOW. THE VALUE MUST INCLUDE THE
 COST OF ALL EQUIPMENT, LABOR AND MATERIALS. PROVIDE
 BONA FIDE SIGNED CONTRACT PER WPB AMENDMENTS TO THE FBC
 109.3
 2) THE ADDRESS OF THE PROJECT OR RESIDENCE MUST BE ON
 PLAN. WPB AMENDMENTS TO THE FBC SEC.107.2.1 INFORMATION
 ON CONSTRUCTION DOCUMENTS.
 3) THE SCOPE OF THE PLUMBING TO BE DONE IS UNCLEAR
 PLEASE PROVIDE PLUMBING PLAN INCLUDING A SANITARY AND
 WATER ISOMETRIC DRAWING. PER WPB AMEND TO FBC
 107.3.5.1.3(13)
 4) A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME DUE TO NOT ENOUGH INFORMATION ON THE PROVIDED
 PLAN. ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED
 UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 ATELYO BELISLE
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6695
  
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status N Date 2021-04-27 Cont ID  
Sent By rmcdouga Date 2021-04-27 Time 08:01 Rev Time 0.00
Received By rmcdouga Date 2021-04-27 Time 08:01 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-01-05 Cont ID  
Sent By jleahy Date 2021-01-05 Time 14:52 Rev Time 0.00
Received By jleahy Date 2021-01-05 Time 14:48 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved