Plan Review Details - Permit 20100086
Plan Review Stops For Permit 20100086
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-11-18 Cont ID  
Sent By rmcdouga Date 2020-11-18 Time 07:22 Rev Time 0.00
Received By rmcdouga Date 2020-11-18 Time 07:13 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2020-10-19 Cont ID  
Sent By rmcdouga Date 2020-10-19 Time 10:12 Rev Time 0.00
Received By rmcdouga Date 2020-10-19 Time 09:50 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2020-11-19 Cont ID  
Sent By ppetty Date 2020-11-19 Time 08:52 Rev Time 0.00
Received By ppetty Date 2020-11-19 Time 08:50 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-10-19 Cont ID  
Sent By ppetty Date 2020-10-19 Time 10:27 Rev Time 0.00
Received By ppetty Date 2020-10-19 Time 10:20 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2020-10-20 Cont ID  
Sent By lcrespo Date 2020-10-20 Time 09:52 Rev Time 0.00
Received By lcrespo Date 2020-10-06 Time 12:39 Sent To  
Notes
2020-10-06 12:41:40GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR
 PER THE WPB AMENDMENTS TO THE FBC SEC. 105.1
  
  

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2020-10-21 Cont ID  
Sent By aborngra Date 2020-10-21 Time 10:16 Rev Time 0.00
Received By aborngra Date 2020-10-21 Time 10:16 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-11-24 Cont ID  
Sent By ccarvaja Date 2020-11-24 Time 14:00 Rev Time 0.00
Received By ccarvaja Date 2020-11-06 Time 11:02 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-10-31 Cont ID  
Sent By cpuell Date 2020-10-31 Time 19:07 Rev Time 0.00
Received By cpuell Date 2020-10-05 Time 16:16 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2020-11-12 Cont ID  
Sent By lcrespo Date 2020-11-12 Time 16:57 Rev Time 0.00
Received By lcrespo Date 2020-11-12 Time 16:57 Sent To  
Notes
2020-11-12 16:58:0111/12/20 REVIEWED FOR CODE COMPLIANCE (PLUMBING/POOL)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES
 FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL,
 STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT
 THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK
 OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2020-10-06 Cont ID  
Sent By lcrespo Date 2020-10-06 Time 11:57 Rev Time 0.00
Received By lcrespo Date 2020-10-06 Time 10:21 Sent To  
Notes
2020-10-06 11:58:05010/06/20 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. PLEASE SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR
 THE MAXIMUM SYSTEM FLOW. THE MAXIMUM FLOW OF THE PUMP
 FROM ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN
 DETERMINING THE MAXIMUM SYSTEM FLOW RATE PER
 ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE TDH
 CALCULATIONS MUST INCLUDE ALL THE SYSTEM COMPONENTS
 INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES,
 HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS
 EXCEPT THE PUMP.
  
 2. PLEASE IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS
 SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS
 IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE
 TDH CALCULATIONS PER THE ANSI/APSP/ICC 7 - 2013 SECS.
 4.4.9, 4.4.9.1.
  
 3. IT INDICATES ON THE PLANS THAT THERE IS NO POOL FILL
 AND ON THE CONTRACT, ON PAGE 4 IT CALLS OUT FOR FILL,
 PLEASE CLARIFY IF THE POOL IS EQUIPPED WITH AN
 AUTO-FILL PER THE WPB AMENDMENTS TO THE FBC SEC.
 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 4. SINCE THIS A DUAL DWELLING AND IT HAS A BACKFLOW
 REDUCED PRESSURE ZONE BACKFLOW DEVICE IS REQUIRED PER
 THE CITY OF WEST PALM CROSS CONNECTION CONTROL MANUAL.
  
 5. PLEASE PROVIDE FOR POOL HEATER SPECIFICATION THAT
 THE POOL HEATER HAS A MINIMUM THERMAL EFFICIENCY OF 82%
 PER THE 2017 FBC-ENERGY SEC. R403.10.4.
  
 6. PLEASE PROVIDE ALL SPECIFICATIONS ON THE POOL FILTER
 AS IT DOES NOT SAY WHO THE MANUFACTURE IS OR MODEL TO
 INDENTIFY FLOW RATES PER THE WPB AMENDMENTS TO THE FBC
 SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2020-11-18 Cont ID  
Sent By rmcdouga Date 2020-11-18 Time 07:23 Rev Time 0.00
Received By rmcdouga Date 2020-11-18 Time 07:13 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2020-10-19 Cont ID  
Sent By rmcdouga Date 2020-10-19 Time 10:12 Rev Time 0.00
Received By rmcdouga Date 2020-10-19 Time 09:50 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2020-11-23 Cont ID  
Sent By kalexand Date 2020-11-23 Time 10:39 Rev Time 0.00
Received By kalexand Date 2020-11-23 Time 10:39 Sent To I
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2020-10-30 Cont ID  
Sent By kalexand Date 2020-10-30 Time 17:12 Rev Time 0.00
Received By kalexand Date 2020-10-30 Time 17:12 Sent To I
Notes
2020-10-30 17:14:42AS STAMPED ON SURVEY: MECHANICAL EQUIPMENT MAY NOT
 PROJECT MORE THAN 4 FEET INTO A REQUIRED SETBACK
 PURSUANT TO THE CITY OF WEST PALM BEACH ZONING AND LAND
 DEVELOPMENT REGULATIONS (ZLDR), SECTION 94-305(B)(4):