| 2020-09-16 11:18:46 | 1ST REVIEW FBC-2017 FUEL GAS |
| | PERMIT- 20090572 |
| | 9/16/2020 |
| | |
| | CODES IN EFFECT: |
| | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| | FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017 |
| | FBC ACC- FLORIDA ACCESSIBILITY CODE SIXTH ADDITION 2017 |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION |
| | 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | |
| | PLAN REVIEW RESULTS: DENIED |
| | |
| | 1) PROVIDE A BASIC SITE PLAN TO SHOW THE LOCATIONS OF |
| | THE GAS METER, TANKLESS WATER HEATER, FUTURE GENERATOR |
| | AND UNDERGROUND PIPING RUN- SECTION 107.2.1 WPB. THIS |
| | IS A COMMERCIAL PROPERTY WITH PAVED DRIVE AND PARKING |
| | AREAS. CLARIFY IF THE METER IS NEW OR EXISTING, AND |
| | INDICATE HOW THE WATER HEATER WILL BE PROTECTED FROM |
| | VEHICULAR IMPACT- SECTION 303.4 FBC FG. THE GENERATOR |
| | WILL NOT BE REVIEWED AT THIS TIME, HOWEVER PLEASE SHOW |
| | THE REQUIRED CLEARANCES TO THE BUILDING AND ADJACENT |
| | PROPERTY LINES- SECTION 305.1 FBC FG. |
| | |
| | 2) SUBMIT MANUFACTURER'S SPECS FOR THE FUTURE GENERATOR |
| | INDICATING THE BTUH LOAD OF THE UNIT. A FULL SUBMITTAL |
| | IS NOT REQUIRED AT THIS TIME- SECTION 305.1 FBC FG. |
| | |
| | 3) PROVIDE A BASIC ELEVATION DETAIL SHOWING THE |
| | MOUNTING LOCATION OF THE WATER HEATER, AND CLEARANCE |
| | DISTANCES FROM GRADE, OVERHEAD CONSTRUCTION, |
| | COMBUSTIBLE MATERIAL, AND OPERABLE OPENINGS INTO THE |
| | BUILDING. THE MOUNTING LOCATION SHALL BE IN COMPLIANCE |
| | WITH THE MANUFACTURER'S GUIDELINES- SECTION 305.1, AND |
| | THE REQUIRED VENTING TERMINATION LOCATION SHALL BE PER |
| | THE GUIDELINES AND SECTIONS 501, 502, 503 FBC FG. |
| | PLEASE NOTE THE NAVIEN MAKES A COMMERCIAL AND A |
| | RESIDENTIAL NPE MODEL. PLEASE DESIGNATE THE CORRECT |
| | MODEL NUMBER AND SUBMIT THE WATER HEATER INSTALL |
| | MANUAL. SHOW THE CONDENSATE PIPING RUN AND TERMINATION |
| | LOCATION- SECTION 307.2 FBC FG. |
| | |
| | 4) GAS RISER |
| | A) INDICATE A NEW OR EXISTING METER AND SHOW ALL GAS |
| | PIPING RUNS TO APPLIANCES AND EQUIPMENT EXISTING AND |
| | NEW BEING SUPPLIED BY THE METER- SECTION 107.2.1 WPB. |
| | MODIFICATIONS TO EXISTING SYSTEMS WITH NEW LOADS ADDED |
| | REQUIRE SUBMITTAL OF A COMPLETE GAS PIPING RISER |
| | SHOWING ALL EXISTING PIPING RUNS TO EXISTING APPLIANCES |
| | AND THEIR BTUH LOADS- SECTIONS 401.3 & 401.4 FBC FG. |
| | B) PROVIDE THE LENGTH OF THE BRANCH PIPING RUNS TO THE |
| | WATER HEATER AND THE FUTURE GENERATOR AND THE TOTAL |
| | DEVELOPED LENGTH OF THE ENTIRE SYSTEM- SECTIONS 402.4.1 |
| | & 402.4.2 FBC FG. |
| | C) INDICATE THE MAKE AND MODEL NUMBER OF THE REGULATOR |
| | AND SHOW THE OUTLET PRESSURE (IN. WC.) TO THE WATER |
| | HEATER. PLEASE NOTE THE NAVIEN WATER HEATER SPECS |
| | INDICATE AN INLET PRESSURE OF 3.5 IN. TO 10.5 IN. WC. |
| | SUBMIT MANUFACTURER'S SPECS FOR THE REGULATOR MARKED UP |
| | TO SHOW THE SELECTED MODEL, INLET AND OUTLET PIPE SIZES |
| | AND PRESSURES, AND ORIFICE SIZE- SECTION 410.1 & 410.2 |
| | FBC FG. |
| | D) SHOW THE LOCATIONS OF THE REQUIRED PIPE UNIONS AT |
| | EACH SIDE OF THE REGULATOR- SECTION 410.2 (7). |
| | E) INDICATE HOW THE PE PIPING RISER WILL CONNECT TO THE |
| | SCHEDULE 40 METALLIC PIPE PER SECTION 404.17.2 FBC FG. |
| | PLEASE NOTE THAT SPECS FOR ANODELESS RISERS AND |
| | PE/METALLIC PIPE CONNECTORS SHALL BE ASTM D2513 |
| | CATEGORY 1 OR ASTM F1973 LISTED AND LABELED. |
| | F) REFER TO SECTIONS 410.17.1 & 410.17.2 FBC FG AND |
| | INDICATE THE TYPE OF RISER PIPE TO BE INSTALLED AT THE |
| | FUTURE GENERATOR. |
| | G) INDICATE THE BURIAL DEPTH OF THE UG PE PIPE PER |
| | SECTION 404.12 AND SHOW A TRACER WIRE WILL BE INSTALLED |
| | ADJACENT TO THE PIPE- SECTION 404.17.3 FBC FG. |
| | |
| | 5) CLARIFY IF THE $1800.00 JOB VALUE ON THE APPLICATION |
| | INCLUDES THE COST OF LABOR, MATERIALS, EQUIPMENT, AND |
| | THE TANKLESS WATER HEATER- SECTION 109.3 WPB. PLEASE |
| | PROVIDE A COPY OF THE CONTRACT AND/OR COPIES OF |
| | ESTIMATES AND INVOICES TO VERIFY TOTAL JOB COSTS. |
| | |
| | 6) PROVIDE AND ELECTRICAL PLAN AND AN ELECTRICAL |
| | SUB-PERMIT TO PROVIDE CIRCUITRY FOR THE HEATER- |
| | SECTIONS 105.1 AND 107.2.1 WPB. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL/PLUMBING PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |