| Plan Review Stops For Permit 20071430 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2020-10-20 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-10-20 |
Time |
14:16 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-10-20 |
Time |
13:08 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2020-09-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-09-09 |
Time |
11:29 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-09-09 |
Time |
11:29 |
Sent To |
|
|
| Notes |
| 2020-09-09 11:37:45 | PLAN | | | REVIEW COMMENTS | | | | | | 2ND REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) COMMENT NOT ADDRESSED. NOTE: IF SOMETHING ON THE | | | DRAWING APPLIES TO THIS PERMIT CROSS OUT THE ITEMS THAT | | | DO NOT APPLY TO THIS PERMIT #18100338, THAT YOU WISH TO | | | REVISE. THIS IS A REVISION TO PERMIT #18100338, THE | | | WALKIN COOLER BUILDING AND DUMPSTER ENCLOSURE ARE NOT | | | INCLUDED WITH THIS PERMIT. THE WALKIN COOLER BUILDING | | | AND THE DUMPSTER ENCLOSURE DRAWINGS WERE SUBMITTED | | | UNDER PERMIT NUMBER 17020359. ANY REVISIONS TO THESE | | | TWO STRUCTURES SHOULD BE MADE TO THE PERMIT THEY WERE | | | INCLUDED IN. PLEASE REMOVE THESE DRAWINGS FROM THE | | | REVISION AND SUBMIT THEM AS A REVISION TO THE | | | APPROPRIATE PERMIT. FBC 107.2 | | | | | | 2) COMMENT NOT ADDRESSED. REVISED SHEET A-101R NO | | | LONGER SHOWS THE ACCESSIBLE PORTION OF THE BAR THAT IS | | | REQUIRED BY FBC ACCESSIBILITY SECTION 902.1. | | | | | | I WAS NOT ABLE TO DETERMINE THAT THESE COMMENTS WERE | | | ADDRESSED. PLEASE SUBMIT A NARRAITIVE EXPLAINING HOW | | | EACH OF THE COMMENTS HAS BEEN CORRECTED. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2020-08-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-08-05 |
Time |
14:59 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-08-04 |
Time |
17:18 |
Sent To |
|
|
| Notes |
| 2020-08-05 15:29:20 | PLAN | | | REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THIS IS A REVISION TO PERMIT #18100338, THE WALKIN | | | COOLER BUILDING AND DUMPSTER ENCLOSURE ARE NOT INCLUDED | | | WITH THIS PERMIT. THE WALKIN COOLER BUILDING AND THE | | | DUMPSTER ENCLOSURE DRAWINGS WERE SUBMITTED UNDER PERMIT | | | NUMBER 17020359. ANY REVISIONS TO THESE TWO STRUCTURES | | | SHOULD BE MADE TO THE PERMIT THEY WERE INCLUDED IN. | | | PLEASE REMOVE THESE DRAWINGS FROM THE REVISION AND | | | SUBMIT THEM AS A REVISION TO THE APPROPRIATE PERMIT. | | | FBC 107.2 | | | | | | 2) REVISED SHEET A-101R NO LONGER SHOWS THE ACCESSIBLE | | | PORTION OF THE BAR THAT IS REQUIRED BY FBC | | | ACCESSIBILITY SECTION 902.1. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2020-08-14 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2020-08-14 |
Time |
16:51 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2020-08-14 |
Time |
16:51 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
2 |
Status |
P |
Date |
2020-10-09 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2020-10-09 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2020-10-09 |
Time |
11:18 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2020-07-31 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2020-07-31 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2020-07-31 |
Time |
10:53 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2020-10-20 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-10-20 |
Time |
14:16 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-10-08 |
Time |
14:34 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2020-09-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-09-09 |
Time |
11:39 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-08-20 |
Time |
15:50 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2020-08-14 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2020-08-14 |
Time |
16:51 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2020-07-30 |
Time |
16:23 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
P |
Date |
2020-08-22 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2020-08-22 |
Time |
10:10 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2020-08-22 |
Time |
10:10 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2020-08-05 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2020-08-05 |
Time |
13:46 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2020-08-05 |
Time |
12:58 |
Sent To |
|
|
| Notes |
| 2020-08-05 13:49:32 | THERE APPEAR TO BE SEVERAL REVISIONS ON THIS PROJECT. | | | PLEASE PROVIDE THE LAST PREVIOUSLY APPROVED SHEETS FOR | | | THIS PROJECT WITH THE NEXT UPLOAD OF THE MECHANICAL | | | SHEETS AS I AM NEW TO THIS PROJECT I NEED TO SEE WHAT | | | WAS APPROVED PREVIOUSLY. | | | | | | MICHAEL EDWARDS | | | MECHANICAL EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL. 33401 | | | 561-805-6728 | | | [email protected] | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2020-08-05 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2020-08-05 |
Time |
13:52 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2020-08-05 |
Time |
07:28 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
3 |
Status |
P |
Date |
2020-10-20 |
|
|
Cont ID |
|
| Sent By |
equinone |
Date |
2020-10-20 |
Time |
12:02 |
Rev Time |
0.00 |
| Received By |
equinone |
Date |
2020-10-20 |
Time |
12:02 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2020-09-09 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-09-09 |
Time |
11:38 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-09-09 |
Time |
11:38 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2020-08-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2020-08-05 |
Time |
15:38 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2020-08-05 |
Time |
15:38 |
Sent To |
|
|
| Notes |
|
|